Completed and Ongoing Technical Assistance Projects (Priority Areas): 2000-2007
As of 30 April 2007

Project Number Approval Date Sector Project Name ADB Financing
($ '000)
Status
3530
31 October 2000
Transport
750.0
Completed
3531
31 October 2000
Transport
440.0
Completed
3494
5 September 2000
Transport
150.0
Completed
6024
12 March 2002
Transport
850.0
Completed
6044
9 August 2002
Transport
150.0
Completed
3964
4 November 2002
Transport
150.0
Completed
4091
21 March 2003
Transport
150.0
Completed
4374
12 August 2004
Transport
150.0
Completed
4382
31 August 2004
Transport
500.0
Ongoing
4444
23 November 2004
Transport
800.0
Ongoing
6223
23 December 2004
Transport
500.0
Ongoing
4643
5 September 2005
Transport
150.0
Ongoing
4684
3 November 2005
Transport
700.0
Ongoing
6294
21 December 2005
Transport
650.0
Ongoing
6309
9 March 2006
Transport
Maintenance of Regional Road Transport Corridors Project
500.0
Ongoing
4784
10 May 2006
Transport
Dushanbe-Kyrgyz Border Road Rehabilitation Project, Phase III (TAJ)
650.0
Ongoing
4785
10 May 2006
Transport
Preparing the Western Regional Road Development (MON)
650.0
Ongoing
4773
21 March 2006
Transport
Xinjiang Regional Road Improvement Project
600.0
Ongoing
4828
21 August 2006
Transport
Road Rehabilitation and Capacity Building Cluster(AFG)*
2,700.0
Ongoing
6347
12 October 2006
Transport
CAREC Transport Sector Development Strategy Study
950.0
Ongoing
4889
8 December 2006
Transport
Regional Infrastructure (Roads) (UZB)
300.0
Ongoing
4684
20 December 2006
Transport
Southern Road Corridor Improvement Project (Supplement)
430.0
Ongoing
4926
4 February 2007
Transport
Transport Sector Master Plan
600.0
Ongoing
23 TA Projects
Subtotal (Transport)
$13,470.0
 
6058
29 October 2002
Trade Facilitation
2,000.0
Ongoing
3950
29 October 2002
Trade Facilitation
Customs Infrastructure and Modernization3 - Kyrgyz Republic Component
500.0
Ongoing
3951
29 October 2002
Trade Facilitation
500.0
Ongoing
4450
26 November 2004
Trade Facilitation
500.0
Ongoing
4451
26 November 2004
Trade Facilitation
500.0
Ongoing
6203
2 December 2004
Trade Facilitation
900.0
Ongoing
4873
22 November 2006
Trade Facilitation
Logistics Development and Capacity Building in Xinjiang
425.0
Ongoing
4906
18 December 2006
Trade Facilitation
Capacity Building for Customs and Trade Facilitation
1,200.0
Ongoing
8 TA Projects
Subtotal (Trade Facilitation)
6,525.0
 
6184
20 August 2004
Trade Policy
350.0
Ongoing
1 TA Project
Subtotal
350.0
 
5960
12 December 2000
Energy
900.0
Completed
6023
12 March 2002
Energy
900.0
Ongoing
3956
30 October 2002
Energy
600.0
Ongoing
6163
19 December 2003
Energy
700.0
Ongoing
4596
10 June 2005
Energy
500.0
Ongoing
6267
3 November 2005
Energy
500.0
Ongoing
6371
18 December 2006
Energy
Mitigation of Trans-Boundary Air Pollution from Coal-Fired Power Plants in Northeast Asia
900.0
Ongoing
6383
15 January 2006
Energy
Central Asia South Regional Electricity Market Project
3,000.0
Ongoing
6389
26 March 2007
Energy
CAREC Members Electricity Regulators Forum (CMERF)
500.0
Ongoing
9 TA Projects
Subtotal (Energy)
8,500.0
 
41 TA Projects
TOTAL (2000-2005)
$28,845.0
 
1Attached to a loan - Almaty-Bishkek Regional Road Rehabilitation.
2Attached to a loan - Southern Transport Corridor Road Project, Phase I
3Attached to a loan - Regional Trade Facilitation and Customs Cooperation Program
4Attached to a loan - Regional Customs Modernization and Infrastructure Development Project
5Attached to a loan - Power Transmission and Distribution Project (AFG)

*Note: Afghanistan joined CAREC in November 2005