Greater Mekong Subregion

Home : Regions and Countries : Regional Cooperation (Sub-regional Programs) : Greater Mekong Subregion : Publications : Proceedings of Ministerial, Forum, and Working Group Meetings : Appendix 3 - Status of Subregional Transport Activities

Table of Contents
p. 31 of 176 BACK | NEXT
Thirteenth Ministerial Conference on Subregional Economic Cooperation Program
Twelfth Ministerial Conference on Subregional Cooperation
Eleventh Ministerial Conference on Subregional Economic Cooperation
Ninth Ministerial Conference on Subregional Cooperation
Eighth Ministerial Conference on Subregional Cooperation
Sixth Meeting of the Subregional Transport Forum
Seventh Meeting of the Subregional Transport Forum
Fifth Meeting of the Subregional Transport Forum
Appendix 1
Appendix 2
>> Appendix 3
Fourth Meeting of the Subregional Transport Forum
Eleventh Meeting of the Subregional Electric Power Forum
Tenth Meeting of the Subregional Electric Power Forum
Ninth Meeting of the Subregional Electric Power Forum
Eighth Meeting of the Subregional Electric Power Forum
Seventh Meeting of the Subregional Electric Power Forum
Sixth Meeting of the Subregional Electric Power Forum
Fifth Meeting of the Subregional Electric Power Forum
Fourth Meeting of the Regional Power Trade Coordination Committee
Second Meeting of the Regional Power Trade Coordination Committee
First Focal Group Meeting of Regional Power Trade Coordination Committee
Ninth Meeting of the Experts Group on Power Interconnection and Trade
Eighth Meeting of the Experts Group on Power Interconnection and Trade
Seventh Meeting of the Experts Group on Power Interconnection and Trade
Sixth Meeting of the Experts Group on Power Interconnection and Trade
Fifth Meeting of the Experts Group on Power Interconnection and Trade
Fourth Meeting of the Experts Group on Power Interconnection and Trade
Third Meeting of the Experts Group on Power Interconnection and Trade
Second Meeting of the Experts Group on Power Interconnection and Trade
Sixth Meeting of the Subregional Telecommunications Forum
Fifth Meeting of the Subregional Telecommunications Forum
Steering Committee Meeting for the Regional Technical Assistance on the Establishment of the Backbone Telecommunications Project for the Greater Mekong Subregion - Phase 1 (RETA 5915)
Fourth Meeting of the Subregional Telecommunications Forum
Eleventh Meeting of the Working Group on Environment
Tenth Meeting of the Subregional Working Group on Environment
Ninth Meeting of the Working Group on Environment
Seventh Meeting of the Working Group on Environment
Sixth Meeting of the Working Group on Environment
Fifth Meeting of the Working Group on Environment
Fourth Meeting of the Working Group on Environment
Workshop on Drug Control Initiatives in the Greater Mekong Subregion
Sixth Meeting of the Working Group on Human Resource Development
Fourth Meeting of the Working Group on Human Resource Development
Third Meeting of the Working Group on Human Resource Development
Second Meeting of the Working Group on Human Resource Development
16th Meeting of the Working Group on the Greater Mekong Subregion Tourism Sector
15th Meeting of the Working Group on the Greater Mekong Subregion Tourism Sector
14th Meeting of the Working Group on the Greater Mekong Subregion Tourism Sector
Twelfth Meeting of the Subregional Working Group on Tourism
Eleventh Meeting of the Subregional Working Group on Tourism
Tenth Meeting of the Subregional Working Group on Tourism
Ninth Meeting of the Subregional Working Group on Tourism
Eighth Meeting of the Subregional Working Group on Tourism
Special Meeting of the Trade Facilitation Working Group
Fourth Meeting of the Trade Facilitation Working Group
Third Meeting of the Trade Facilitation Working Group
Second Meeting of the Trade Facilitation Working Group
Workshop on Customs Facilitation in the GMS
Inception Meeting of Trade Facilitation Working Group
Fourth Meeting of the Subregional Investment Working Group
Third Meeting of the Subregional Investment Working Group
Second Meeting of the Subregional Investment Working Group
GMS Mid-Term Review cum Senior Officials Meeting
Workshop on the Preinvestment Study for the Greater Mekong Subregion: East-West Economic Corridor
Quadripartite Meeting on the Chiang Rai-Kunming via Lao PDR Road Improvement Project

Status of High Priority Subregional Projects

Bangkok-Phnom Penh-Vung Tau Corridor

Chiang Rai to Kunming via Lao PDR Road Improvement

East-West Transport Corridor Project

Kunming-Hanoi-Haiphong Transport Corridor

Bangkok-Phnom Penh-Vung Tau Corridor

Chronology of Events

  • Identified by the Subregional Transport Sector Study (STSS) as being among the highest priority GMS road links requiring improvement (1994)
  • The recommendations of the Final Report of the STSS endorsed and adopted at successive GMS Ministerial Meetings in 1994 and 1995 as to priorities
  • TA 5649-REG: GMS Infrastructure Improvement: Ho Chi Minh City to Phnom Penh Highway Project was approved for $3.0 million in November 1995
  • Consultant work started in May 1996, now virtually complete
  • Advance Action for Procurement approved by the Bank in 1997
  • Bank approved loans of $40.0 million to Cambodia and $100 million to Viet Nam in December 1998
  • Total Project cost = $195.5 million
  • Civil works contracts signed by Viet Nam in October 1999
  • Signing of civil works contracts in Cambodia expected soon
  • Civil works expected to take 3 years
  • Cross-border agreement has been signed. Work on necessary Annexes and Protocols to start soon under Bank technical assistance.

    Summary of the Phnom Penh to Ho Chi Minh City GMS Road Project

    Scope

    1. Cambodia

    1. Minor improvements to about 60 km of the Project Road from Phnom Penh to the Mekong River ferry;
    2. Reconstruction of 105 km of the Project Road from the Mekong River Ferry to Bavet at the border with Viet Nam

    2. Viet Nam

    1. Reconstruction of about 80 km of Project road. This length includes 58 km of Highway 22 between An Suong and the border with Cambodia at Moc Bai;
    2. 22 km of Highway 1 between Thu Duc and An Suong (part of outer ring road north of HCMC)

    3. For Both

    1. Consulting services for construction supervision and training of domestic Government and consultant staff

    Summary of the Bangkok-Phnom Penh-HCMC-Vung Tau Road

    Road Link Length (km) Present Condition Current Status
    Bangkok-Cambodia Border (Rt #s 33, 304 & 319)
    about 215 km
    good
     
    Cambodia Border to Sisophon (Rt # 5)
    about 48 km
    poor
    Grant aid being sought for upgrading
    Sisophon to Phnom Penh (Rt # 5)
    about 410 km
    poor
    To be improved under the Bank financed Road Network Improvement Project. Loan approved in 1999
    Phnom Penh to Mekong River (Rt # 1)
    about 60 km
    fair to poor
    Minor improvements under Bank loan approved in Dec. 1998
    Mekong River to Bavet-CAM/VIE Border (Rt # 1)
    about 105 km
    poor
    Reconstruction under Bank loan approved in Dec. 1998
    CAM/VIE Border at Moc Bai to HCMC (Rt # 22)
    about 80 km
    good/fair, congested
    Reconstruction and widening under Bank loan approved in Dec. 1998
    HCMC to Vung Tau (Rt # 51)
    about 85 km
    variable
    Improvements being undertaken by the Government of Viet Nam. Possible private sector provision of a parallel expressway

    Chiang Rai to Kunming via Lao PDR Road Improvement

    Chronology of Events

    • Identified by the Subregional Transport Sector Study (STSS) as being among the highest priority GMS road links requiring improvement (1994).
    • The recommendations of the Final Report of the STSS endorsed and adopted at successive GMS Ministerial Meetings in 1994 and 1995 as to priorities.
    • TA No. 5728-REG: Chiang Rai-Kunming Road Improvement via Lao PDR Project was approved for $0.6 million on 27 February 1997.
    • Consultants commenced work in July 1997, completed in 1998.
    • Bank loan to PRC to improve the Yuanjiang to Mohei approved for $250 million in June 1999. Total Project Cost: $770 million
    • Concession agreement for the Lao PDR portion of R3 is currently under review

    Summary of the TA 5728-REG: Chiang Rai to Kunming via Lao PDR Road Improvement Project

    For Yunnan Province, Route # 213

    • The technical and economic studies undertaken by Yunnan Province Communications Department were well done.
    • Further work required for the environmental and social aspects of the Project to meet Bank requirements was undertaken through further Bank funded technical assistance

    For Lao PDR, Route # 3

    The consultant identified three improvement levels:

    • Class 4/5: minimum level improvement needed to achieve all-weather capability. EIRR = 16%
    • Class 3: sealed road with capacity, alignment and gradient improvements. EIRR = 18 %
    • Class 2: high standard, greatly improved alignment (23 km shorter than existing road). EIRR = 22%

    The financial analysis showed that the road concession on its own would not be financially attractive. With land development, the financial internal rate of return is marginal.

    The social impact with road improvement is likely to be very positive, particularly in terms of health, education and income generating opportunities.

    The road and its improvement in currently under a concession agreement. This agreement was found to be faulty. It is currently under review and associated problems are expected to be worked out soon.

    For Thailand

    Various upgrading of the connecting links in Thailand are being planned. For example design of a bypass (32 km) of Chiang Sean has been made and implementation is scheduled soon.

    There is also a plan to replace substandard box culverts with small bridges on those links needing them.

    Summary of the Chiang Rai-Kunming Road Improvement via Lao PDR Project

    Road Link Length (km) Present Condition Current Status
    Kunming to Mohan/Lao PDR Border (Rt # 213)
    about 709 km
    various
    Upgrading complete or planned
       Kunming to Yuxi
    about 89 km
    good
    Being upgraded to 6-lanes, 1999, $240 million
       Yuxi to Yuanjiang
    about 114 km
    poor
    Being upgraded to 4-lanes, 1999-2000, $450 million
       Yuanjiang to Mohei
    about 146 km
    poor
    To be upgraded to 4-lanes for 1999-2003, improved alignment of 146 km, $770 million, ADB financing of $250 million approved in June 1999
       Mohei to Simao
    about 71 km
    good
    Completed 2-lane in 1997 for $50 million
       Simao to
       Xiaomengyang
    about 103 km
    poor
    Upgrading to 4-lane 2000-2003, $400 million
       Xiaomengyang
       to Mohan (PRC-Lao
       PDR border)
    about 186 km
    good to poor
    Upgrading in 2001-2005, $325 million
    Boten (PRC border) to Houei Sai (Route# 3)
    about 250 km
    good to very poor
    Est. cost $23-94 million
       Boten (PRC border)
       to Louang Namtha
    about 56 km
    poor
     
       Louang Namtha to
       B. Nam Ngeun
    about 80 km
    good to very poor
     
       B. Nam Ngeun to
       B. Houei Sai
    about 113 km
    fair
     
    Mekong River Crossing: Houei Sai-Chiang Khong
    about 400 m
    pax & veh. ferry
    Two possible bridge sites identified, est. cost $28-38 million. Bridge needed in 10-12 years
    Chiang Khong to Chiang Rai (various routings)
    144-112 km
    good
    Bypass and minor road improvements planned

    East-West Transport Corridor Project

    Chronology of Events

    • Identified by the Subregional Transport Sector Study (STSS) as being among the highest priority GMS road links requiring improvement (1994)
    • The recommendation of the STSS were endorsed and adopted at successive Ministerial Meetings in 1994 and 1995 as to priorities
    • TA 5586-REG: Study of the Lao PDR - Thailand - Viet Nam East - West Transport Corridor approved in June 1994
    • Three options were studied:
      1. a northern corridor using Road 8 in Lao PDR leading to the port of Cua Lo near Vinh in Viet Nam,
      2. a central corridor using Road 9 leading to Da Nang, and
      3. two alternative southern corridors from Pakse to the ports of either Da Nang or Quy Nhon.
    • The Central Corridor (East - West Corridor) was selected with the agreement of the three governments based on economic, environmental and strategic considerations
    • A second phase TA 5710-REG: Study of the Lao - Thailand - Viet Nam, East - West Transport Corridor involved detailed feasibility investigations including economic, engineering including detailed design of selected components, preparation of tender documents and assistance to Lao PDR for prequalification of contractors
    • Loan components include:
      1. Lao PDR: rehabilitation of Road 9 between Muang Phin and Dene Savanh at the Viet Nam border (about 78 km),
      2. Viet Nam: Upgrading and improvement of Road 9 between Lao Bao at the border with Lao PDR and Dong Ha at Highway 1 (about 83 km)
    • A parallel activity that has been actively pursued is the development of a cross-border agreement between the three governments
    • A draft cross-border agreement was discussed at a trilateral meeting in Bangkok in December 1998 comprising 44 articles. 40 were agreed at that meeting
    • All parties have been working hard to resolve the outstanding issues for the other 4 Articles. Agreement has essentially been reached and the cross-border agreement is expected to be finalized by Friday afternoon.
    • The Agreement is scheduled to be signed on 26 November 1999 in Vientiane by the Transport Ministers from each of the three countries.

    Kunming-Hanoi-Haiphong Transport Corridor

    Chronology of Events

    • This transport corridor was agreed as the next GMS priority project at the 4th STF and was endorsed at the 8th Ministerial Conference held in Manila in October 1998
    • A TA is in the Bank's Regional Technical Assistance Program in 2000
    • A loan for Viet Nam is in the pipeline for 2001


    <<Back
    Appendix 2
    Next>>
    Fourth Meeting of the Subregional Transport Forum

  • © 2010 Asian Development Bank

    Privacy | Terms of Use
     Top of page