 |
Table of Contents |
 |
|
|
Financial Management and Analysis of Projects :
3. Preparing and Appraising Investment Project
3.4. Forecasting
3.4.1.
Introduction to Forecasting
3.4.1.1.
ADB needs reasonable forecasts
of expenses, revenues, cash flows, and other financial items that
are necessary to ensure that projects are delivered in a timely
and effective manner. But as forecasting is not an exact science,
ADB requires its staff to work alongside their counterparts in borrowers'
agencies during project identification, preparation and appraisal
to ensure that all reasonable efforts have been made to develop
meaningful forecasts. These forecasts should, ideally, be prepared
by the borrower's agencies. However, where forecasts are prepared
by ADB staff, or PPTA consultants, it is essential that the borrower's
agencies take ownership of these forecasts.
3.4.1.2. ADB requires EAs to provide
updated forecasts after loan signing and the start of project implementation.
These will be updated forecasts-to-completion or, in the case of
revenue-earning projects, updated forecasts for a specified period.
The updated forecasts provide early warnings of project problems
so that timely corrective actions can be taken. In the case of a
revenue-earning project, the financial analyst will determine the
period during which EAs will be required to provide updated forecasts.
This requirement will be specified in the loan agreement. The exact
period is at the discretion of the financial analyst. This will
normally be from between 3 and 5 years following project completion
(i.e., normally a total period of 10 years).
3.4.1.3. During project preparation
and appraisal, staff should carefully examine project cost, revenue
and cash flow estimates. The project officer is responsible for
ensuring that these base costs are realistic. The financial analyst
and the project engineer are responsible for examining the cost
estimates in general. They are particularly responsible for ensuring
that: (i) the items included in the base cost are realistic; and
(ii) where items have not been included, this has been for sound
technical, financial or economic reasons.
3.4.1.4. The remainder of this section
discusses: (i) the use of the COSTAB model; (ii) the principal components
of cost estimates and how these should be developed; (iii) physical,
price contingencies, and risk contingencies; and (iv) disbursement
profiles. The section concludes with outline of a typical project
Cost Estimates table and Financing Plan.
Back
3.3. Appraisal Checklists | Next 3.4.1. Introduction to Forecasting |