Publications

Home : Publications : Online Publications : Document


Table of Contents
p. 32 of 203 BACK | NEXT
Foreword
1. Introduction to the Guidelines
2. User Instructions
3. Preparing and Appraising Investment Project
3.1. Investment Projects Overview
3.2. Possible Investment Projects
3.3. Appraisal Checklists
3.4. Forecasting
3.4.1. Introduction to Forecasting
3.4.2. Using the COSTAB Model
3.4.3. Preparing Project Cost Estimates
3.4.4. Determining Contingencies
3.4.5. Disbursement Profiles
>>3.4.6. Preparing Financing Plans
3.4.7. Computing Incremental Project Cash Flows
3.5. Preparing Financial Benefit-Cost Analyses
3.6. Loan Covenants
3.7. ADB Reports
4. Financial Management of Executing Agencies
5. Reporting and Auditing
6. Financial Institutions
7. Knowledge Management
Financial Management and Analysis of Projects : 3. Preparing and Appraising Investment Project : 3.4. Forecasting

3.4.6. Preparing Financing Plans

3.4.6.1. The project Cost estimate table will provide as its bottom line, the total financing required for a project. It is essential that the means of financing this total expenditure is specifically defined in the appraisal report. The illustration and discussion of the financing plan for a project to be implemented by a revenue-earning enterprise usually consists of a summaryall in current terms-of:

  • the project financing requirements and the external sources of finance from the cash flow statement
  • other capital and incremental working capital expenditures occurring during the project development period
  • incremental and initial operating costs to be incurred during the implementation period, to be financed out of either project capital funding, or from local budgetary provisions
  • net income from any ongoing operations, and
  • debt servicing.

3.4.6.2. In a nonrevenue-earning entity, where there are rarely any internally generated sources of funds, project financing is usually not related to the future financial performance of the entity. In such cases, the illustration and discussion of the financing plan would be confined to the project only and set out with the discussion on project costs.

3.4.6.3. The text of an appraisal report requires a discussion of the financing plan. In the case of a nonrevenue-earning project, this is normally an extension of the discussion of the Cost Estimates. In the case of a revenue-earning project to be implemented by an executing agency, a summary financing plan may be included after the Project Cost Estimates table. A detailed discussion on the financing plan (with a comprehensive table showing the financing plan, where necessary) should be included as part of the Financial Analysis Chapter. The following items should be covered, with detailed explanations, where necessary, in an appendix to the report: (i) any cofinancing arrangements; (ii) availability of internal funds, referenced as necessary to the cash flow statements; (iii) the self-financing ratio, particularly when this is to be incorporated in an operating covenant; (iv) equity contributions; (v) terms of loans, including interest rates (or onlending rates, where applicable), grace periods, repayment periods, incidence of foreign exchange risk, guarantee fees, and interest during construction; and (vi) the dependability of the financing plan in terms of firm commitments that have been received, the progress of negotiations where loans or equity contributions have not been finalized, the availability of additional sources of funds in the event of cost overruns or lower-than-expected generation of internal funds, and a sensitivity analysis relating to the latter items.

3.4.6.4.Funds from all principal sources should be identified as line items in a financing plan. Funds sources should be set out in terms of foreign and local currencies, using the US dollar as the foreign currency, and grouped in the table under local and foreign sources, including ADB loans, funds from other foreign lenders and donors, local loans, local equity including government grants and subsidies, and internally generated funds.

3.4.6.5. In cases where the EA is conducting an ongoing operation, as in the case of a public sector enterprise, it may, or may not, be generating sufficient funds from ongoing operations to support these activities. It is, therefore, advisable to include in the financing plan either the net funding through the period of the financing plan that the agency will generate, or the additional funding needs that it will require, to operate and maintain its existing and new facilities. The sources of additional funding should be identified, for example, subsidies from government. The financing plan should contain an explicit reference to any contributions to investment to be made by the agency during implementation, with specific reference to the acceptability to ADB of a policy of deficit funding by government, including any policy that, in effect, contributes to the capital investment of the EA.

3.4.6.6. The following is an example of a typical summarized Financing Plan.

  Local Currency Foreign Exchange Total %
Funds Required        
Proposed Project        
     Capital expenditures 0.00 0.00 0.00  
     Operating expenditures 0.00 0.00 0.00  
     Financial charges during development 0.00 0.00 0.00  
TOTAL PROJECT REQUIREMENTS 0.00 0.00 0.00 100%
         
Sources of Funds        
Proposed ADB loan 0.00 0.00 0.00  
Other loans 0.00 0.00 0.00  
Equity or capital contributions        
     Government 0.00 0.00 0.00  
     Other sources 0.00 0.00 0.00  
Subsidies for operations 0.00 0.00 0.00  
Internal cash generation 0.00 0.00 0.00  
TOTAL SOURCES 0.00 0.00 0.00 100%


<<Back
3.4.5. Disbursement Profiles
Next>>
3.4.7. Computing Incremental Project Cash Flows