Asian Development Bank - Fighting Poverty in Asia and the Pacific
What's New  |   e-Notification  |   Sitemap  |   Contact Us  |   Help

Catalog

Home : Publications : Catalog : Online Publications : Document

Table of Contents
p. 62 of 68 BACK | NEXT
Foreword
1. Introduction
2. ADB Policies and Procedures
3. Project Stages
4. Project Scheduling and Resource Planning
5. Project Implementation
6. Project Manager
7. ADB and EA/IA Interaction
8. ADB Performance Review and Monitoring
9. Tutorials and Templates
9.1 Tutorial
- 9.1.1 Installing OpenProj
- 9.1.2 The Critical Path Method (CPM) on OpenProj
- 9.1.3 Entering Tasks and Task Durations
- 9.1.4 Creating Dependencies
>> - 9.1.5 Viewing the Critical Path on the Gantt Chart
- 9.1.6 The Sample Project Implementation File
- 9.1.7 Reviewing the Project Plan
9.2 Templates
10. Reference Material
Appendixes
FAQ
e-Handbook on Project Implementation : 9. Tutorials and Templates

9.1 Software Tool Kit for a Tutorial

9.1.5 Viewing the Critical Path on the Gantt Chart

The Gantt chart provides the network diagram for the CPM. Having identified the tasks and determined their dependencies, you can study the associations between tasks from here and determine the critical paths of the project. OpenProj is a convenient tool that can also help identify the critical paths.

To see the critical paths in the Gantt view of OpenProj, follow these steps:

  1. Open the project file.
  2. Click on the "Gantt" icon on the left menu or "View->Gantt Chart" on the top menu.
  3. OpenProj automatically indicates tasks in the critical path with a red bar on the Gantt chart. Tasks in blue are not part of the critical path.


<<Back
- 9.1.4 Creating Dependencies
Next>>
- 9.1.6 The Sample Project Implementation File