Publications

Home : Publications : Online Publications : Document


Table of Contents
p. 64 of 68 BACK | NEXT
Foreword
1. Introduction
2. ADB Policies and Procedures
3. Project Stages
4. Project Scheduling and Resource Planning
5. Project Implementation
6. Project Manager
7. ADB and EA/IA Interaction
8. ADB Performance Review and Monitoring
9. Tutorials and Templates
9.1 Tutorial
- 9.1.1 Installing OpenProj
- 9.1.2 The Critical Path Method (CPM) on OpenProj
- 9.1.3 Entering Tasks and Task Durations
- 9.1.4 Creating Dependencies
- 9.1.5 Viewing the Critical Path on the Gantt Chart
- 9.1.6 The Sample Project Implementation File
>> - 9.1.7 Reviewing the Project Plan
9.2 Templates
10. Reference Material
Appendixes
FAQ
e-Handbook on Project Implementation : 9. Tutorials and Templates

9.1 Software Tool Kit for a Tutorial

9.1.7 Review the Project Plan

Periodically, you will need to review the project plan and see if the tasks are being completed within schedule. You can use OpenProj to indicate the level of completion of tasks. Tasks that are not being completed according to schedule should be updated to reflect their current status. Updating the task dates will also update the total project duration and reflect the effect across dependent tasks. To update a task

  1. Double click on a task from either the "Gantt chart view" or "Tasks view" to bring up the "Task Information" dialog box.
  2. To update task completion, simply indicate the percentage of the task that is completed.


  3. To adjust the task dates, indicate an appropriate date constraint for the start date for the task.
  4. Click on "Close" to save your updated task.
  5. View the resulting Gantt chart. The middle black bar on a task bar indicates the percentage of that task that is completed.


<<Back
- 9.1.6 The Sample Project Implementation File
Next>>