Handbook on Resettlement: A Guide to Good Practice
Appendix 4: Resettlement Monitoring : Sample Formats for Monthly Progress Reports
Administrative Monitoring System
| Resettlement Activities |
Total Task |
Targeted Achievement in Year 1 |
Targeted Achievement Year 2 |
Targeted Achievement Year 3 |
| First Quarter |
Second Quarter |
Third Quarter |
Fourth Quarter |
| 1. Consultation with stakeholders |
|
|
|
|
|
|
|
| 2. Socioeconomic survey & APs identification |
|
|
|
|
|
|
|
| 3. Land acquisition |
|
|
|
|
|
|
|
| 4. Compensation payment |
|
|
|
|
|
|
|
| 5. Site selection and development |
|
|
|
|
|
|
|
| 6. Plot distribution |
|
|
|
|
|
|
|
| 7. Relocation of displaced persons |
|
|
|
|
|
|
|
| 8. Income restoration programs |
|
|
|
|
|
|
|
Field-Level Monitoring of Resettlement Activities
| Resettlement Activities |
Total Task |
Targeted Achievement in Year 1 |
Targeted Achievement Year 2 |
Targeted Achievement Year 3 |
| First Quarter |
Second Quarter |
Third Quarter |
Fourth Quarter |
| 1. Land acquisition |
|
|
|
|
|
|
|
| 2. Finalization of APs list |
|
|
|
|
|
|
|
| 3. Final list of displaced persons |
|
|
|
|
|
|
|
| 4. ID card of APs |
|
|
|
|
|
|
|
| 5. Compensation payments |
|
|
|
|
|
|
|
| 6. Site selection |
|
|
|
|
|
|
|
| 7. Site development |
|
|
|
|
|
|
|
| 8. Plot distribution |
|
|
|
|
|
|
|
| 9. Relocation/ Shifting |
|
|
|
|
|
|
|
| 10. Formation of APs committees |
|
|
|
|
|
|
|
| 11. Replacement land |
|
|
|
|
|
|
|
| 12. Income restoration plan |
|
|
|
|
|
|
|
| 13. Training |
|
|
|
|
|
|
|
| 14. Employment |
|
|
|
|
|
|
|
| 15. Group-specific development project |
|
|
|
|
|
|
|