Asian Development Bank - Fighting Poverty in Asia and the Pacific
What's New  |   e-Notification  |   Sitemap  |   Contact Us  |   Help

Catalog

Home : Publications : Catalog : Online Publications : Document

Table of Contents
p. 55 of 79 BACK | NEXT
Foreword
Abbreviations
Glossary
1. Introduction
2. The Resettlement Plan in the Project Cycle
3. Resettlement: Key Planning Concepts
4. Consultation and Participation
5. Socioeconomic Information
6. Relocation
7. Income Restoration
7.1 Issues in Income Restoration
7.2 Income Restoration Programs
>> 7.3 Income Restoration in the Project Cycle: Key Action Points
7.4 Checklist: Income Restoration
8. Institutional Framework
9. Monitoring and Evaluation
Selected Reading List
Appendix 1: The Bank's Policy on Involuntary Resettlement
Appendix 2: Sample Terms of Reference for Full Resettlement Plan
Appendix 3: Resettlement Policies in Selected DMCs
Appendix 4: Resettlement Monitoring: Sample Formats for Monthly Progress Reports
Handbook on Resettlement: A Guide to Good Practice : 7. Income Restoration

7.3. Income Restoration in the Project Cycle: Key Action Points


Project Cycle Key Action Point
Project Identification/ISA
  • Review existing data on APs income sources, patterns and levels.
  • Assess possible strategies for income restoration, e.g., for agricultural APs find out whether adequate agricultural land is available for income restoration.
PPTA Feasibility Study
  • Identify income restoration strategies and assess feasibility.
  • Include income sources, patterns and prospects in the survey TORs.
  • Involve APs/hosts in developing options for income restoration.
  • Conduct survey and census.
  • Draft income restoration plans with multiple options.
  • Develop special measures for income restoration plans for women and other vulnerable groups.
  • Field-test income generation plan with selected APs in trial activities.
MRM
  • Assess sources of funding and institutional options for implementation.
Appraisal
  • Review income restoration plan (included in RP).
Loan Negotiation
  • Include any outstanding issues as conditions.
Implementation
  • Involve APs and NGOs in the implementation.
  • Involve women's groups for women-centered projects.
  • Conduct benefit monitoring and evaluation.
Monitoring and Evaluation
  • Implementation monitoring by the resettlement agency or NGO
  • Independent evaluation by outside agency.