1. Introduction
2. The Resettlement Plan in the Project Cycle
2.1 Deciding on the Type of Resettlement Plan
2.2 Requirements for Resettlement Plans
2.3 Full Resettlement Plan: Recommended Outline
>> 2.4 Short Resettlement Plan: Recommended Outline
2.5 Land Acquisition and Resettlement in the Project Cycle: Key Action Points
2.6 Land Acquisition and Resettlement in the Project Cycle: Key Action Points for Sector Loans/Subprojects
3. Resettlement: Key Planning Concepts
4. Consultation and Participation
5. Socioeconomic Information
6. Relocation
7. Income Restoration
8. Institutional Framework
9. Monitoring and Evaluation
Selected Reading List
Appendix 1: The Bank's Policy on Involuntary Resettlement
Appendix 2: Sample Terms of Reference for Full Resettlement Plan
Appendix 3: Resettlement Policies in Selected DMCs
Appendix 4: Resettlement Monitoring: Sample Formats for Monthly Progress Reports
Handbook on Resettlement: A Guide to Good Practice : 2. The Resettlement Plan in the Project Cycle

2.4. Short Resettlement Plan: A Recommended Outline


Topic Contents
Scope of land acquisition and resettlement
  • Describe alternative options, if any, considered to minimize land acquisition and its effects, and why the remaining effects are unavoidable.
  • Summarize key effects in terms of land acquired, assets lost, and people displaced from homes or livelihoods.
Objectives, policy framework, and entitlements
  • Describe key national and local land, compensation and resettlement policies, laws, and guidelines that apply to project.
  • Explain how Bank policy on Involuntary Resettlement will be achieved.
Consultation, and grievance redress participation
  • Describe consultation processes and procedures for redress of grievances.
Compensation, relocation, and income restoration
  • Describe arrangements for valuing and disbursing compensation.
  • Describe arrangements for housing relocation, including transfer and establishment.
  • Describe income restoration measures to be implemented.
  • Identify any environmental risks, describe management and monitoring steps.
Institutional framework
  • Identify main tasks and responsibilities in planning, managing and monitoring land acquisition and resettlement.
Resettlement budget and financing
  • Identify land acquisition and resettlement costs and funding sources.
Implementation schedule
  • Provide time schedule showing how people affected will be provided for before demolition begins.
Monitoring and evaluation
  • Specify arrangements for M&E.



<<Back
2.3 Full Resettlement Plan: Recommended Outline
Next>>
2.5 Land Acquisition and Resettlement in the Project Cycle: Key Action Points