Anhui Hefei Urban Environment Improvement Project :  China,People'sRep.of :Go to Project Summary

Anhui Hefei Urban Environment Improvement Project :  China,People'sRep.of

Timetable  |  Financing Plan and Loan Utilization  |  Project Outcome  |  Implementation Progress  |  Status of Covenants

Loan Name Anhui Hefei Urban Environment Improvement Project
Country China,People'sRep.of
Loan Number 2328
Project Number 36595- 01
Type/Modality of Assistance[Approved]
Ordinary Capital Resources US$150.00  million
Thematic Classification Environmental Sustainability
Sustainable Economic Growth
Inclusive Social Development
Project Outcome
Description of Outcome Improved public wastewater management, flood control, and transport services in Hefei city.
Progress Toward Outcome Newly approved loan.
Implementation Progress
Description of Project Outputs Component I: Wastewater and Waste Management in Hefei city
1.1 Shiwuli River WWTP is operational
1.2. Wangtang WWTP Phase II and associated sewers are operational
1.3 Municipal sewers throughout Hefei City are improved
1.4 The closed Qingxi Road Landfill site is improved

Component II: River rehabilitation and flood control improvement of Hefei
2.1 Ershibu River rehabilitation and flood control is improved
2.2 Banqiao River rehabilitation and flood control is improved
2.3 Sili River rehabilitation and flood control is improved
2.4 Chao Lake flood control works are improved

Component III: Road infrastructure and traffic management in the Xinzhan Zone
3.1 Road infrastructure and traffic management in the Xinzhan Zone is improved

Project management capacity is improved
Status of Implementation Progress (Outputs, Activities and Issues) The Project was approved on 24 April 2007. The loan agreement was signed on 28 August 2007. Consulting services and civil works are ongoing.

Component I: Wastewater and Waste Management in Hefei city
1.1 Shiwuli River WWTP is operational - ICB contract for factory mechanics, electrical appliances and instruments awarded; 3 civil works contracts for oxidation ditch and and sewage lines construction awarded.
1.2. Wangtang WWTP Phase II and associated sewers are operational - ICB tender for mechanical and electrical equipment in progress; contract for equipment for Qianshanlu PS awarded; 2 civil works contracts for oxidation ditch and sewage lines construction awarded.
1.3 Municipal sewers throughout Hefei City are improved - 1 civil works contract for sewage lines construction awarded.
1.4 The closed Qingxi Road Landfill site is improved - not yet started.

Component II: River rehabilitation and flood control improvement of Hefei
2.1 Ershibu River rehabilitation and flood control is improved - not yet started.
2.2 Banqiao River rehabilitation and flood control is improved - bidding of contracts ongoing.
2.3 Sili River rehabilitation and flood control is improved - bidding of contracts ongoing.
2.4 Chao Lake flood control works are improved - not yet started.

Component III: Road infrastructure and traffic management in the Xinzhan Zone
3.1 Road infrastructure and traffic management in the Xinzhan Zone is improved - not yet started.

Project management capacity is improved - PMO is fully staffed. Consulting firm has been recruited. The first progress report has been submitted.
Linkage to Country/Regional Strategy The Project is consistent with ADB's water policy and will help the PRC achieve the Millennium Development Goals of environmental sustainability and increased access to safe drinking water and basic sanitation. The proposed Project is consistent with ADB's strategic objectives to make markets work more efficiently through infrastructure development and to promote environmental sustainability in the PRC. Over the past decade, ADB has stepped up its involvement in urban development and water resource management in the PRC through its lending and TA operations. The knowledge gained from similar investment projects in such urban centers as Shanghai, Tianjin, Wuhan, and Fuzhou and that generated from various policy-oriented studies will be incorporated in the design of the Project.
Geographical Location Hefei City, Anhui Province
Safeguard Categories Safeguard Categories explained (Launches new browser window)
  Environment A
  Resettlement A
  Indigenous People C
Summary of Environmental and Social Issues SEIA circulated to Board on 16 November 2006.
Consultations Planned or Carried Out June-August 2006
Responsible ADB Officer Raushan Mamatkulov
Responsible ADB Department East Asia Department
Responsible ADB Division Social Sectors Division, EARD
Executing Agencies Hefei Municipal Government
  Mr. Li Wuhao
  Director, PMO
  303 Hefei Finance Bureau, Anhui
  adbdecam@yahoo.com.cn
Timetable
Concept Clearance 31 Aug 2006
Fact-finding 09 Oct 2006 to 23 Oct 2006
Appraisal 04 Dec 2006 to 15 Dec 2006
Board Approval 24 Apr 2007
Last Review Mission 27 Oct 2008
CLOSING
Loan No. Approval Signing Effectivity Original Revised Actual
2328-PRC 24 Apr 07 28 Aug 07 08 Jan 08 31 Mar 13 - -

Financing Plan Top Loan Utilization
  TOTAL ( Amount in US$ million)
Project Cost 372.360
ADB 150.000
HMG 82.940
District Govt 71.400
Local Banks 55.700
Enterprise Bonds 12.320
Date ADB OTHERS Net Percentage
Cumulative Contract Awards
31 Oct 08 62.213 0.000 41%
Cumulative Disbursements
31 Oct 08 13.685 0.000 9%
Top Status of Covenants
Category Sector Environmental Social Financial Economic Others Overall
Rating Satisfactory Satisfactory Satisfactory Satisfactory - Satisfactory Satisfactory