Home : Projects : Expressway Financing in the Western Provinces of the PRC


Indonesia LOAN: INO 29336-01

Central Sulawesi Integrated Area Development and Conservation
Missions
Loan Approval Date
Estimated Completion Date
Cost and Financing Plan
Description
Development Objectives
Thematic Classification
Poverty Classification
Rationale
Objectives and Scope
Policy Dialogue
Environment Category
Env't Impact and Mitigation
Social Aspects and Remedies
Benefits and Beneficiaries
Public Consultation
Beneficiary Participation in Formulation
Beneficiary Participation in Implementation
Consulting Services
Procurement
Contacts
Remarks
Location
Central Sulawesi
Sector
Agriculture & Natural Resources /Agriculture Sector Development
Initial Listing
1 July 1995
Most Recent Update
27 March 2002
Executing Agency(ies)
  • Ministry of Home Affairs

  • Missions

    TA Fact-Finding Loan Fact-Finding Pre-Appraisal Appraisal
    14 Aug-1 Sep 1995 17 Mar-4 Apr 1997 TBD 28 Jul-19 Aug 1997
    Loan Approval Date
    27 January 1998
    Estimated Completion Date
    March 2005
    Cost and Financing Plan (in US$ million)

    Source Foreign Cost Local Cost Total
    Bank 15.20 16.80 32.00
    Cofinancing 0.80 2.40 3.20
    Borrower 0.00 14.20 14.20
    Beneficiaries 0.00 0.00 0.00
    Others 0.00 4.30 4.30
    Project/Program Cost 16.00 37.70 53.70

      OCR ADF Total
    Loan Amount 32.00 0.00 32.00

    Description
    Strategic Development Objectives
    Primary
    Sound Management of Environment
    Secondary
    Poverty Reduction
    Rationale

    Objectives and Scope
    The Project will promote sustainable development in an ecologically sensitive area, i.e., encouraging environmentally sound social and economic development in tandem with protection of the biological wealth and ecological functions that makes it possible. The Project has two inter-related objectives: (i) improved socioeconomic welfare of rural communities in the buffer zone of the Park (defined as the areas abutting the boundary of the Park and the two watersheds served by the Lariand and Gumbasa rivers); and (ii) improved Park management.

    Policy Dialogue

    Environment Category: A

    Environment Impact and Mitigation

    Social Aspects and Remedies

    Benefits and Beneficiaries

    Public Consultation
    1. Arranged by
    2. Date for Consultation :
    3. Groups Consulted :

    Beneficiary Participation in Formulation

    Beneficiary Participation in Implementation

    Consulting Services

    Procurement

    Contacts
    Bank
    Siew Tuan Chew
    Principal Innovation and Efficiency Initiative Specialist
    RSGS
    Tel. No.: (632) 632-4832
    E-mail: schew@adb.org

    Executing Agency
    Ministry of Home Affairs
    Contact Person :
    Tel. No. :
    Fax. No. :
    E-mail :
    Remarks