Asian Development Bank - Fighting Poverty in Asia and the Pacific
What's New  |   e-Notification  |   Sitemap  |   Contact Us  |   Help

Projects

Home : Projects : Expressway Financing in the Western Provinces of the PRC


Viet Nam,Soc Rep of PPTA: VIE31362-01

Se-san 3 Hydropower Project
Missions
TA Approval Date
Estimated Completion Date
Cost and Financing Plan
Description
Development Objectives
Thematic Classification
Poverty Classification
Objectives and Scope
Policy Dialogue
Environment Category
Env't Impact and Mitigation
Social Aspects and Remedies
Benefits and Beneficiaries
Beneficiary Participation in Formulation
Beneficiary Participation in Implementation
Consulting Services
Procurement
Contacts
Remarks
Location
Sector
Energy /Hydropower Generation
Initial Listing
15 February 1999
Most Recent Update
26 August 1999
Executing Agency(ies)
  • Viet Nam Electricity

  • TA Fact-Finding Mission Undertaken/Scheduled: 16-21 Mar 1999
     
    TA Approval Date
    14 July 1999
    Estimated Completion Date
    Cost and Financing Plan (in US$)

    Source Amount
    JSF 998,000.00
    Total 998,000.00

    Description
    Strategic Development Objectives
    Primary
    Economic Growth
    Secondary
    Objectives and Scope
    The objectives of the TA are to assist the Government in verifying that Se San 3 is a least cost development alternative and to prepare it as a model hydropower project to be managed commercially and adopting internationally recommended operational, financial, environmental and social practices. Building on lessons learned from past hydropower development in Viet Nam and the region, "best practices" will be incorporated into all aspects of Project design that will serve as a precedent for future hydropower development in Viet Nam. The Se San 3 Hydropower Project will involve the construction of a 260 MW hydropower station on the Se San river, which should be fully commissioned by the end of 2000.

    Policy Dialogue

    Environment Category: A

    Environment Impact and Mitigation
    Not required

    Social Aspects and Remedies

    Benefits and Beneficiaries

    Beneficiary Participation in Formulation

    Beneficiary Participation in Implementation

    Consulting Services
    Phase I of the TA will require about 8 person-months of international consultants (project finance, financial analyst, and project economist) and 5 person-months of domestic consultants (legal expert and interpreter). Phase II will require about 14 person-months of international consultants supported by about 16 person-months of domestic consultants with experience in environmental engineering, fisheries, watershed management, social development research, and webpage design together with interpreters. In addition, the international consultants will make appropriate arrangements to undertake three studies, i.e. rapid biodiversity assessment, fisheries study and water quality study.

    Procurement

    Contacts
    Bank
    Kathleen M. Moktan
    Director
    RSCG
    Tel. No.: (632) 632-6651
    E-mail: kmoktan@adb.org

    Executing Agency
    Viet Nam Electricity
    Contact Person :
    Tel. No. :
    Fax. No. : 844-8249462
    E-mail :
    Remarks

    © 2008 Asian Development Bank

    Privacy | Terms of Use