Chashma Right Bank Irrigation Project (Stage III)
| Project Title |
Chashma Right Bank Irrigation Project (Stage III)
|
| Loan / TA No. |
1146-PAK |
| Country |
Pakistan |
|
Top
| Date of Initial Complaint |
28/5/2002 |
| Received by Management |
4/6/2002 |
| Sender of Complaint |
Alisan Wagha, Damaan Dev Org, Taunsa Sharif; Zafar Iqbal Lund, Hirak Dev Centre, D.G. Khan; Mushtaq Gadi, SUNGI Dev Foundation, Islamabad; Muhammad Nauman, CREED, Karachi |
| Allegations of policy breaches as stated in the Complaint |
- Guidelines for Incorporation of Social Dimensions in Bank Operations
- ADB Guidelines for Social Analysis
- Environmental Considerations in Bank Operations
- Bank's Operational Missions
- Involuntary Resettlement
- Indigenous Peoples Policy
- Supplementary Financing of Cost Overruns on Bank-financed Projects
- Benefit Monitoring and Evaluation
- Agriculture and Natural Resource Research Policy
- Information Policy and Strategy
- Confidentiality and Disclosure of Information (Staff Instructions)
|
| Allegations of harm done |
- Design-related social and environmental problems
- Project induced flooding
- Negative impact on legal and historical rights to floodwater
- Lack of land acquisition, resettlement and compensation
- Livelihood disruptions
- Lack of information sharing, participation and consultation with the affectees
- Lack of response to and coordination with the affectees
|
| Date Management response sent (45 days) |
16/7/2002 Signed by Vice-President Shin |
|
Top
| Date of request for inspection |
19/11/2002 |
| Received by the Board Inspection Committee (BIC) |
25/11/2002 |
| Requester |
Zafar Iqbal Lund, Hirak Dev Center, Dear Ghazi Khan; Ahsan Wagha, Damaan Development Organization, Dear Ghazi Khan; Mohammad Nauman, Creed Alliance, Karachi; Mushtaq Gadi, Sungi Development Foundation, Islamabad; Khadim Hussain, Action Aid-Pakistan, Islamabad; Shafi Qiasrani, CRBIP Affectees Committee, Dear Ghazi Khan |
| Allegation of policy breaches as stated in the Request |
- ADB's Guidelines for Social Analysis of Development Projects
- Incorporation of Social Dimensions in Bank Operations
- Environmental Considerations in Bank Operations
- Bank's Operational Missions
- Involuntary Resettlement
- Indigenous People's Policy
- Supplementary Financing of Cost Overruns on Bank-financed Projects
- Benefit Monitoring and Evaluation
- Confidentiality and Disclosure of Information (Staff Instructions)
|
| Allegations of harm done |
- Design-related social and environmental problems
- Project induced flooding and involuntary resettlement
- Lifestyle disruptions, livelihood losses and threats of in-migration
- Lack of compensation and resettlement
- Environmental concerns
- Lack of information sharing, consultation and participation of the affected people
|
| Date forwarded to Management |
19/12/2002 |
| Due date of Management response to request (if any) (30 days) |
18/1/2003 Request for extension of time until 7/2/2003 approved by BIC Chairman |
| Date Management response received (if any) |
7/2/2003
|
| Due date of BIC recommendation on authorization of inspection (14 days) |
- The BIC requested additional information from both the Requesters and Management by 25/2/2003. As stipulated in paragraph 36 of the Inspection Policy, the 14-day period will start from the date of receipt of such information.
- The additional information requested from Management was received by the BIC on 25 February, and that requested from the requesters was sent by email to the BIC on 25 February and received by the BIC on 26/2/2003. Accordingly, the BIC's report to the Board is due on 12/3/2003.
- Read the additional
information provided by Management
- Read the additional
information provided by Requesters
- The BIC consulted a Roster member in its deliberations.
- Read the Roster
member's advice
|
| Date BIC recommendation made |
3/3/2003
|
| Date of Board consideration of Request (21 days) |
2/4/2003
- The Board approved the BIC's recommendation
- Report sent to requesters on 3/4/2003
- In accordance with paragraph 103 of the BIC's Recommendation to the Board on Inspection Request: Chashma Right Bank Irrigation Project (Stage III), (Loan 1146-PAK[SF]), Management submitted to the BIC, on 29/7/2003, a report on the progress of the grievance redress process relating to the Chashma Project.
The Requesters submitted their comments on the progress report on 29/8/2003, and again on 4/9/2003.
In response to a request from the BIC, Management submitted supplementary information to the BIC on 12/9/2003.
- As recommended by the BIC and approved by the Board on 2/4/2003, the following documents are now available to the public:
- Chashma Right Bank Irrigation Project (Stage III), Loan 1146-PAK[SF]:
Mid-term Report on Progress of the Grievance Redress Process, dated 29 July 2003
- Appendix 1: Gazette Notification Announcing Establishment of GRSC
- Appendix 2: Inception Report and Work Plan
- Appendix 3: GRSC Poster and Handbill
- Appendix 4: Entitlement Matrix
- Appendix 5: Note to File of ADB Staff and Minutes of the GRSC Meeting on 5 June 2003
- Appendix 6: GRSC’s Invitation Letters Sent to the Inspection Requestors
- Appendix 7: GRSC’s Letter to Land Acquisition Collectors
- Requesters' response to the progress report, dated 29 August 2003
- Requesters' response to the progress report, dated 4 September
- Supplementary Information from Management to the BIC, dated 12 September 2003
- Final Report on the Grievance Redress Process dated February 2004
- Appendix 1: GRSC's End of Tenure Report
- Appendix 2: Entitlement Matrix Advertised in Local Newspaper
- Appendix 3: GRSC's Receipt-of-Grievances Report, September 2003
- Appendix 4: GRSC's Recommendations for Adverse Impact Mitigation and Grievance Redress and Settlement, October 2003
- Appendix 5: Summary of GRSC Recommendations Announced Through Local Newspapers
- Appendix 6: Terms of Reference for Three Consultants
- Appendix 7: Summary of Discussions with Mr. Qaisrani at His Home on 7/8/2003 in Tibbi Qaisrani Village
- Appendix 8: Progress of Construction Works for Causeways Along the Indus Highway
- Appendix 9: Pictures of Flood Sites in August 2003, Showing Improvements
- Comments from Mr. M. Gadi, One of the Requesters, with Chashma Trip Report and Annexes, and some selected complaints attached
- Management's Response to Questions from BIC (with Attachment)
|
|
Top
| Date of appointment of Panel members |
- Appointed December 2003:
- Anthony Ranjit Bevis Amerasinghe
- Goran Eklof
- Neeraj Narayan Joshi
- Lawrence Williams
- The terms of reference of the Inspection Panel were finalized by the BIC on 30/1/2004, after consideration of comments from various parties, and signed by the Panel on 2/2/2004.
- Paragraph 102 of the BIC's recommendation to the Board dated 12/3/2003 states "...draft terms of reference [would be] circulated to Management, the Requesters, the Government of Pakistan, and the Panel members with a request for comments by mid-January 2004. The BIC would expect to finalize terms of reference and a timetable for the inspection by end January."
- Accordingly, in early December 2003, the BIC provided the draft terms of reference to the relevant parties with a request for comments by 15/1/2004. The BIC received comments from Management in a memorandum from Vice-President (Operations 1) on 16/1/2004; from Mr. Mustaq Gadi, one of the Requesters, in an e-mail on 20/1/2004; and consolidated comments from the Panel on 27/1/2004.
|
| Date of submission of Panel work plan |
|
| Date of Panel's visit to Project area (if any) |
|
| Date Panel report forwarded to Management |
- Draft report forwarded to Management and Requesters for comments on 23/4/2004
- Comments received on 24/5/2004
- Panel's final report received by BIC and forwarded to Management on 10/6/2004
|
| Due date of Management's response to report (30 days) |
9/7/2004 |
| Date Management response received |
24/6/2004 |
| Due date BIC recommendation circulated to Board |
8/7/2004 |
| Date BIC recommendation circulated to the Board |
8/7/2004BIC Recommendation
Appendix 1: Panel's Terms of Reference
Appendix 2: Panel's Recommendation
Appendix 3: Executive Summary of Panel's Report
Appendix 4: Management's Response
Appendix 5: GRSC Composition, Function and Recommendations
Appendix 6: Panel's Report
Appendix 7: Annexes of Panel's Report
|
| Date of Board consideration of report (21 days) |
19/8/2004 |
|
Top
| Remedial steps recommended by BIC |
BIC Recommendation |
| Remedial steps approved by Board |
The Board approved the BIC's recommendation |
| Action taken by Management |
|
|
|