| Date of request for inspection |
9/2/1998 |
| Received by the Board Inspection Committee (BIC) |
Received by Board Inspection Committee (BIC) on 18/2/1998 and acknowledged on 23/2/1998; BIC's letter to CREED dated 5/3/1998 for additional information; CREED's letter to BIC dated 22/4/1998 and acknowledged on 19/5/1998 |
| Requester |
CREED |
| Allegation of policy breaches as stated in the Request |
Project Design, Benefits to Consumers, Cost-benefit Analysis |
| Allegations of harm done |
Substantial waste of resources, unnecessary large burden on consumers and taxpayers, idle infrastructure, insignificant progress towards Project goals |
| Date forwarded to Management |
25/5/1998 |
| Due date of Management response to request (if any) (30 days) |
26/6/1998 |
| Date Management response received (if any) |
22/6/1998 Signed by President Sato |
| Due date of BIC recommendation on authorization of inspection (14 days) |
|
| Date BIC recommendation made |
31/7/1998
|
| Date of Board consideration of Request (21 days) |
21/8/1998
- Recommendation approved on a no objection basis
- Requesters were informed on 9/9/1998
|