ADB Processing Procedures for TA Proposals

I. Initial JSF Approval
TA requesting division programs and prioritizes TAs in the Country Partnership Strategy (CPS) paper and/or the Regional Cooperation Strategies and Programs (RCSPs) paper
|
After consultation with the local Japanese embassy, the TA Project Officer prepares JSF project profile for submission to OCO with documentation.
|
OCO reviews proposals and sends clarificatory questions/remarks to Project Officer
|
OCO submits proposals in a batch to the Government of Japan (GOJ) 1
|
After receiving advice from GOJ, OCO announces the results of batch processing, completing the first of the two-step approval process 2
|
- Usually ten working days after batch deadline but longer during heavy batch submission.
- Usually three to four weeks after batch deadline or earlier.
II. Final Approval Process
After a Staff Review Committee Meeting, TA division registers TA for final fund commitment, provided there is no change in amount and/or scope. If there is any change, TA Division requests for formal approval, with justification for the revision.
|
OCO examines the request and processes based on the justification for the revised TA.
|
OCO announces the results of the reprocessing. Once approved, the TA Division registers the TA for final fund commitment.
|
Top
The schedule of batch processing of TA proposals for 2009 is as follows:
| Batch
No. |
Deadline for Submission of Applications to OCO (ADB)* |
| 1st |
2 March |
| 2nd |
11 May |
| 3rd |
13 July |
| 4th |
14 September |
 |