Date |
Activity |
| 2009 |
| 2-6 February 2009 |
Multicountry Secretariat/National Secretariat /National SLMIS Implementation Units Workshop, Bishkek, Kyrgyz Republic |
| 20 February 2009 |
Program Development Specialist on Board to prepare for CACILM II |
| February–March 2009 |
Evaluation of CACILM Phase I |
| Jan-March 2009 |
2008 CMPF Monitoring and Evaluation |
| 2-4 April 2009 |
3rd Steering Committee Meeting, Dushanbe, Tajikistan |
| 4 April 2009 |
NSEC Management Workshop, Dushanbe, Tajikistan |
| 25 April 2009 |
Mark Kunzer, Environment Specialist, took over as Project Officer |
| 18-21 May 2009 |
SLMIS Workshop, Almaty, Kazakhstan |
| 22-24 June 2009 |
CACILM Implementation Phase Planning Workshop, Issyk-Kul, Kyrgyz Republic |
| 25-27 June 2009 |
Training on Creation of Information Database, Issyk-Kul, Kyrgyz Republic |
| 2008 |
| 14-16 January 2008 |
National Secretariats' Workshop Planning, Bishkek, Kyrgyz, Republic |
| 08 February 2008 |
SLM-Research Prospectus Workshop, Tashkent, Uzbekistan |
| 22 April 2008 |
Strategic Partnership Agreement Meeting, Ashgabat, Turkmenistan |
| 24-25 April 2008 |
2nd CACILM Steering Committee Meeting, Ashgabat, Turkmenistan |
| 25-26 April 2008 |
Workshop on Integrated Financing Strategies for SLM, Ashgabat, Turkmenistan |
| 4-5 July 2008 |
Monitoring and Evaluation Workshop, Issyk-Kul, Kyrgyz Republic |
| 8 August 2008 |
Partnership Agreement between ADB Food and Agriculture Organization of UN (FAO) in conducting SLM-IS (date of signing) |
| 14 August 2008 |
Mobilization of NSIU-Uzbekistan |
| 25 August 2008 |
Mobilization of NSIU-Kyrgyz Republic |
| 2 September 2008 |
Partnership Agreement between ADB and International Food Policy Research Institute (IFPRI) in conducting the Economic Analysis of Sustainable Land Management Options in Central Asia (date of signing) |
| September 2008 |
Central Asia ATLAS of Natural Resources Team on Board |
| 19 September 2008 |
Mobilization of NSIU-Turkmenistan |
| 6 October 2008 |
Mobilization of NSIU-Kazakhstan |
| 6-10 October 2008 |
Sustainable Land Management Information System (SLMIS) Inception Workshop, Tashkent, Uzbekistan |
| 27 November 2008 |
Management Workshop, Bishkek, Kyrgyz Republic |
| 2007 |
| 24 January 2007 |
Signing TA Letter of Agreement of the Government of Kyrgyz Republic |
| 25 January 2007 |
Signing TA Letter of Agreement of the Government of Turkmenistan |
| 26 January 2007 |
Signing TA Letter of Agreement of the Government of Tajikistan |
| February 2007 |
Establishment of CACILM Multicountry Secretariat (MSEC) in Bishkek, Kyrgyz Republic |
| 24 February - 13 March 2007 |
TA 6357 Inception Mission in CACs |
| 1 March 2007 |
Establishment of National Secretariats in Kazakhstan, Kyrgyz Republic, Tajikistan, Turkmenistan, Uzbekistan |
| 5 March 2007 |
Establishment of National Coordination Council (NCC) of Uzbekistan by virtue of Statute on NCC issued by Uzhydromet
|
| 19 May 2007 |
Establishment of National Coordination Council (NCC) of Turkmenistan by virtue of Statute on NCC issued by the Ministry of Nature Protection |
| 28 May 2007 |
Establishment of National Coordination Council of Tajikistan by virtue of Order No. 49 issued by Agency of Land Management, Geodesy and Cartography |
| 13 June 2007 |
Establishment of National Coordination Council of Kazakhstan by virtue of Order No.193-0,Ministry of Nature Protection
|
| 2-4 July 2007 |
Sustainable Land Management Research Inception Workshop, Tashkent, Uzbekistan |
| 10-11 July 2007 |
CACILM Knowledge Network (CKN) Orientation Workshop, Bishkek, Kyrgyz Republic |
| 16 July 2007 |
GEF- CEO Endorsement of Uzbekistan Land Improvement Project |
| 7 September 2007 |
Partnership Agrement between ADB and International Center for Agricultural Research in Dry Areas (ICARDA) in conducting SLM-Research (date of signing)
|
| 29 November 2007 |
Monitoring and Evaluation Workshop, Bishkek, Kyrgyz Republic |
| 30-31 November 2007 |
1st CACILM Steering Committee Meeting, Bishkek, Kyrgyz Republic |
| 2006 |
| January - March 2006 |
CMPF and related documents preparation/finalization |
|
6-7 February
2006
|
3rd
National Workshop in Kyrgyzstan
|
|
7 February
2006
|
3rd
National Workshop in Turkmenistan
|
|
8-10 February
2006
|
CACILM
Development Cooperation Partners Meeting, Rome,
Italy
|
|
15-17
February 2006
|
5th
task Force Meeting and 3rd
Multicountry Workshop
|
| 6-8 March 2006 |
3rd National Workshop in Tajikistan |
| 21 March 2006 |
Receipt of letter confirming GTZ's indicative contributions up to $1,900,000 |
| |
- Letter from ICARDA's commitment of $800,000 |
| |
- Letter from FAO confirming
commitment of $300,000
|
|
|
- letter from
IFAD confirming commitment $400,000
|
|
24 March
2006
|
Submission of
CMPF and related documents to GEF Secretariat
|
|
March-May
2006
|
CPP
Evaluation Study
|
|
May-July
2006
|
Preparation
and distribution of New CACILM Brochure (English)
|
|
August-Sept
2006
|
Translation/preparation
of Brochure (Russian)
|
|
August
2006
|
Approval of
GEF Council of CACILM Multicountry Partnership Framework
|
|
September
2006
|
Submission of
request for GEF Endorsement
|
|
15-16
November 2006
|
6th
Task Force Meeting and Launching of CACILM Press Meeting to launch CACILM
|
|
21 November
2006
|
Creation
of National
Coordination Council of Kyrgyz Republic by virtue of The DECREE on the
21 of November 2006 No 47-p
|
|
24 November
2006
|
Approval of
TA 6357-REG: CACILM Multicountry Partnership Framework Support Project
(CMPFSP) by ADB
Management
|
|
1 December
2006
|
Interim
Multicountry Secretariat established in ADB
|
| 1 December - 28 February 2007 |
Interim National Secretariats in Kazakhstan, Kyrgyz Republic, Tajikistan, Turkmenistan, and Uzbekistan |
| 12 December 2006 |
Signing TA Letter of Agreement of the Government of Uzbekistan |
| 20 December 2006 |
Signing TA Letter of Agreement of the Government of Kazakhstan |
| 2005 |
| 1 January 2005 |
PDF-B approval |
|
23 March
2005
|
TA approval
/ADB cofinancing approval
|
|
11-12 April
2005
|
CACILM
Multicountry Workshop to Launch Design Phase, Dushanbe,
Tajikistan
|
|
13-14 April
2005
|
1st National
Workshop in Tajikistan
|
| 15 April 2005 |
2nd CACILM
Task Force Meeting, Dushanbe, Tajikistan |
|
26-27 April
2005
|
1st
National Workshop in Kyrgyzstan
|
|
19-20 May
2005
|
1st
National Workshop in Uzbekistan
|
|
1-2 June
2005
|
1st
National Workshop in Kazakhstan
|
|
24-25 June
2005
|
3rd
Task Force Meeting, Almaty, Kazakhstan
|
|
19-20 August
2005
|
1st
National Workshop in Turkmenistan
|
|
19-20
September 2005
|
2nd
National Workshop in Turkmenistan
|
|
September
2005
|
Preparation
of CACILM brochures and other COPP materials
|
|
17-18 October
2005
|
UNCCD
Conference of Parties (COP 7), Nairobi, Kenya
|
|
1 November
2005
|
2nd National
Workshop in Uzbekistan
|
|
9-10 November
2005
|
2nd
National Workshop in Kyrgyzstan
|
|
17-19
November 2005
|
4th
task Force Meeting & 2nd
Multicountry Workshop, Tashkent, Uzbekistan
|
|
25-26
November 2005
|
2nd
National Workshop in Kazakhstan
|
|
28-29
November 2005
|
2nd
National Workshop in Tajikistan
|
| 2004 |
| 17 May 2004 |
Concept Note approved by GEF/Sec for pipeline entry |
|
23-24 August
2004
|
Inaugural Task
Force Meeting, Almaty, Kazakhstan to review PDF-B
|
| 20 October 2004 |
Revised PDF-B circulated to Task Force members |
| 17 December 2004 |
PDF-B proposal submitted to GEF Sec |