Home : Projects : Theun-Hinboun Hydropower Project

Table of Contents
Project Completion Report
Project Profile
Location Map
Estimated Cost and Financing Plan
Project Description
Project Rationale
Implementation Arrangements
Current Status of Environmental and Social Impacts and Mitigation Measures
Status of Implementation
The Bank's Initial Response to "Power Struggle" The Impacts of Hydro-Development in Laos
The Theun-Hinboun Power Company's Mitigation and Compensation Program
Theun-Hinboun Power Company creates new Environmental Management Division (EMD) and appoints Manager of EMD
Home Page

Theun-Hinboun Hydropower - Project Profile

   

Country and Location
Lao PDR, Bolikhamxay and Khammouane Provinces
Sector/Subsector
Energy/Electric Power
Date of Initial Profile
November 1998
Executing Agency
Theun-Hinboun Power Co., Ltd.

Project Objective

Primary: Economic Growth

Secondary: Foreign Exchange Earnings
Missions Undertaken/Scheduled:

Nature of Mission Date of Mission
Consultation   12-16 August 1991
  20 & 22 April 1993
  21-26 April 1994
Reconnaisance   21-24 June 1993
Steering Committee Meeting   24-26 August 1993
  7-9 March 1994
  14-16 April 1994
  2-15 September 1994
  6-7 December 1994
  26 February - 3 March 1995
  19-24 April 1995
  20-22 May 1996
Appraisal   27 June - 12 July 1994
Review   6-16 March 1995
  21-29 May 1996
  20-31 January 1997
  12-23 June 1997
  10-21 November 1997
  5-12 May 1998

Implementation Schedule
Project implementation started in November 1994 and the Project was completed in March 1998

 