Fuzhou Environmental Improvement Project
Complaint Registry
|
| Action | Date | Status | |
| 1 | Complaint received by SPF | 27 February 2009 |
|
| 2 | Acknowledgement sent to:
|
18 March 2009 |
|
| 3 | Complaint registered | 30 April 2009 | |
| 4 | Eligibility determined | 25 May 2009 | |
| 5 | Complainants informed | 25 May 2009 | |
| 6 | Review and Assessment Report sent to
|
2 July 2009 14 July 2009 2 July 2009 2 July 2009 |
|
| 7 | Complainants' decision to continue received by SPF | 9 July 2009 | |
| 8 | Complainants and OD informed to provide comments on Review and Assessment Report | 9 July 2009 12 July 2009 |
|
| 9 | Comments received from
|
9 July 2009 20 July 2009 |
|
| 10 | Recommendation to work out course of action forwarded to the ADB President for approval | 24 July 2009 | |
| 11 | Stakeholder Consultation to work out course of action | 6 August 2009 | |
| 12 | Consent to publish RAR sought from:
|
||
| 13 | Consent to publish RAR received from:
|
||
| 14 | Consent to publish course of action sought from:
|
||
| 15 | Consent to publish course of action received from:
|
||
| 16 | Implementation of course of action | ||
| 17 | Submission of report on completed course of action by SPF to the ADB President | ||
| 18 | President's approval received | ||
| 19 | Issuance of Final Report to:
|
||
| 20 | Final Report posted on the internet |