Community Empowerment for Rural Development Project (CERDP)
Complaint Registry
|
| Action |
Date |
Status |
|
1 |
Complaint received by SPF |
21 February 2005 |
|
2 |
Acknowledgement sent to:
|
|
|
| 3 | Complaint registered | 9 March 2005 | |
4 |
Eligibility determined |
23 March 2005 |
|
5 |
Complainants informed |
23 March 2005 |
|
6 |
Review and Assessment Report sent to |
||
|
26 April 2005 | ||
|
26 April 2005 | ||
|
05 May 2005 | ||
|
05 May 2005 | ||
7 |
Complainants’ decision to continue received by SPF |
30 May 2005 |
|
8 |
Complainants and OD informed to provide comments on Review and Assessment Report | 30 May 2005 |
|
9 |
Comments received from |
||
| 08 June 2005 | |||
| 13 June 2005 | |||
| 10 | Recommendation and proposed course of action forwarded to the ADB President for approval | 22 June 2005 | |
11 |
Concurrence sought from: |
||
|
05 July 2005 | ||
|
05 July 2005 | ||
|
05 July 2005 | ||
12 |
Concurrence received from: |
||
|
13 July 2005 | ||
|
15 July 2005 | ||
|
15 July 2005 | ||
13 |
Implementation of course of action
|
16 July-28 September 2005 26-28 September 2005 |
|
14 |
Submission of report on completed course of action by SPF to the ADB President | 28 November 2005 | |
15 |
President's approval received | 02 December 2005 | |
16 |
Issuance of Final Report to: |
||
|
13 December 2005 | ||
|
13 December 2005 | ||
|
13 December 2005 | ||
|
13 December 2005 | ||
17 |
Final Report posted on the internet | 14 December 2005 |
The SPF will be in charge of monitoring implementation of any agreement for three years. Monitoring reports will be sent to the complainant after submission to the ADB President and a copy furnished to the Board for information.