| Action | Date | Status | |
| 1 | Complaint received by SPF
|
15 January 2009 |
|
| 2 | Acknowledgement sent to:
|
19 January 2009 19 January 2009 |
|
| 3 | Complaint registered | 19 January 2009 | |
| 4 | Eligibility determined | 12 February 2009 | |
| 5 | Complainants informed | 18 February 2009 | |
| 6 | Review and Assessment Report sent to
|
23 March 2009 23 March 2009 23 March 2009 23 March 2009 |
|
| 7 | Complainants' decision to continue received by SPF | 27 March 2009 | |
| 8 | Complainants and OD informed to provide comments on Review and Assessment Report | 27 March 2009 | |
| 9 | Comments received from
|
27 March 2009 28 March 2009 |
|
| 10 | Recommendation to work out course of action forwarded to the ADB President for approval | ||
| 11 | Stakeholder Consultation to work out course of action | ||
| 12 | Consent to publish RAR sought from:
|
||
| 13 | Consent to publish RAR received from:
|
||
| 14 | Consent to publish course of action sought from:
|
||
| 15 | Consent to publish course of action received from:
|
||
| 16 | Implementation of course of action | ||
| 17 | Submission of report on completed course of action by SPF to the ADB President | ||
| 18 | President's approval received | ||
| 19 | Issuance of Final Report to:
|
||
| 20 | Final Report posted on the internet |