As of October 2005

Month Major Activities (dates)
2005
January-March Planning and Inception Phase:
  • Interview ADB operations directors and staff to secure initial feedback on the review design and Review Panel selection process
  • Finalize Review Panel and Special advisers recruitment and schedule
  • Finalize schedule for consultations and regional meetings
  • Finalize communications strategy & schedule: coordinate with Water Awareness Program (WAP)
  • Finalize design of review process and submit inception report presenting work plan
April
May
June
August
September
October
November
December
2006
Ist Quarter Final Steps of Review Process:
  • DG RSDD and Panel Chair discuss interdepartmental comments and finalize the Panel Report
  • DG RSDD submits report to ADB's Management for endorsement to circulate to ADB's Board of Directors as a Board Information Paper (as stipulated in the policy)
  • RSDD posts Panel Report on ADB website
2nd Quarter
  • ADB initiates follow up actions in response to the Panel Report