Results of ADB-supported Operations: India

ADB operations in India began in 1986. Assistance has focused mainly on transport, energy, and urban development. In recent years, ADB has also been providing support for improving water resource management, promoting financial inclusion, and facilitating public–private partnerships in infrastructure.

ADB operations cover 22 Indian states, and the country has been one of the top three borrowers of ADB's ordinary capital resources loans since 2007. ADB is guided by the principles of the 3Rs (relevance, responsiveness, and results) as it designs and implements its program in India. ADB remains committed to supporting the government's efforts toward making India's growth inclusive and environmentally sustainable.

This country brief summarizes how the partnership between the Government of India and ADB has contributed to the development of the country.

Development Results of ADB-Supported Operations in India, 2004-2011

As of 31 December 2011 Download Excel file

Sector Results Achieved
Energy
Installed energy generation capacity (megawatt equivalent) 318
Transmission lines installed or upgraded (kilometers) 10,813
Distribution lines installed or updgraded (kilometers) 27,007
New households connected to electricity (number) 2,020,912
Greenhouse gas emission reduction (tons of carbon dioxide equivalent per year) 2,437,000
Finance
Microfinance loan accounts opened / end borrowers reached (number) 42,707
Transport
Expressway built or updgraded (kilometers) 244
National highways and provincial, district, and rural roads built or upgraded (kilometers) 15,471
Beneficiaries from road projects (number) 140,400,000
Water
Water supply pipes installed or upgraded: length of network (kilometers) 5,450
New households served with water supply (number) 7,111,000
Wastewater treatment capacity created (cubic meters) 225,995
New households served with sanitation (number) 3,547,902

The table includes operations completed during the period, and funded by ADB's ordinary capital resources, special fund resources, which include the Asian Development Fund and other special funds, cofinanciers, and the government. The results presented are limited to ADB's core sectors, as defined under Strategy 2020 and tracked through indicators in the ADB Results Framework. ADB monitors results achievement in the annual Development Effectiveness Review. The numbers represent the sum of outputs and beneficiaries of individual projects. Therefore, the beneficiary numbers reported under education—teachers trained, and students benefitting from school improvement programs or direct support—include those who benefited from more than one project.

Source: ADB project completion reports

Installed energy generation capacity between 2004-2011: 318 megawatt equivalent

The indicator, given in megawatt (MW) equivalent is the total incremental generating capacity of a generation project. This may be power sourced from renewable technology or from conventional sources e.g., oil, coal, or large hydro. A project may involve construction of a new power plant or simply acquisition of an asset, e.g., the private sector acquiring a government-owned coal plant. This includes the MW-equivalent capacity of additional heating supply as well as hydrocarbon-based energy added through production or additional import capacity. Energy export is excluded from Level 2 measurement as it does not add to the energy resources of a country.

Contributing ADB Projects
Project Name Type of Assistance Approval Number Approval Date Closing Date Success Rating at Completion* Contribution to Output
27068: Renewable Energy Development Project   1465 26-Sep-96 25-Oct-02 Highly successful / successful 318
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.

Transmission lines installed or upgraded between 2004-2011: 10,813 kilometers

The indicator covers power, gas, and oil transmission lines. It is the measure of the ground distance, in kilometers, traversed by the transmission line. For power transmission lines, we are looking for the simple distance from tower A to tower B and not the circuit-kilometers.

Contributing ADB Projects
Project Name Type of Assistance Approval Number Approval Date Closing Date Success Rating at Completion* Contribution to Output
36318-013: Assam Power Sector Development Program Loan 2036/2037 10-Dec-03 28-Jun-05 Successful 355
29473-023: Madhya Pradesh Power Sector Development Project Loan 1869 06-Dec-01 28-Nov-03 Partly successful 1,813
35068-013: Gujarat Earthquake Rehabilitation and Reconstruction Program Loan 1826 26-Mar-01 06-Nov-07 Successful 2,547
29694-013: Gujarat Power Sector Development Program Loan 1804 13-Dec-00 20-Mar-07 Successful 1,321
32107-013: Power Transmission Improvement Sector Project Loan 1764 06-Oct-00 10-Aug-07 Successful 2,388
24273: Power Transmission Sector Project   1405 16-Nov-95 09-Jul-03 Highly successful / successful 2,389
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window.

Distribution lines installed or updgraded between 2004-2011: 27,007 kilometers

"Distribution lines installed or upgraded" is the aggregate of the following three sub-indicators: (i) km of power distribution lines installed or upgraded, generally at 110 kv or lower); (ii) km of district heating network pipes installed or upgraded; and (iii) km of urban gas supply network pipes installed or upgraded.

Contributing ADB Projects
Project Name Type of Assistance Approval Number Approval Date Closing Date Success Rating at Completion* Contribution to Output
36318-013: Assam Power Sector Development Program Loan 2036/2037 10-Dec-03 28-Jun-05 Successful 10,784
29473-023: Madhya Pradesh Power Sector Development Project Loan 1869 06-Dec-01 28-Nov-03 Partly successful 5,666
35068-013: Gujarat Earthquake Rehabilitation and Reconstruction Program Loan 1826 26-Mar-01 06-Nov-07 Successful 2,676
29694-013: Gujarat Power Sector Development Program Loan 1804 13-Dec-00 20-Mar-07 Successful 7,881
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window.

New households connected to electricity between 2004-2011: 2,020,912

The indicator is the number of new households connected to the grid. Only new household connections resulting from a project are counted; households already connected to the grid and receiving improved services through a project are not counted. The number of new household connections resulting from a project is counted in total and not proportional to the ADB funding component only. The guiding principle is that ADB assistance is integral to the completion of the entire project; without the ADB assistance, the total target household connections would not be attained.

Contributing ADB Projects
Project Name Type of Assistance Approval Number Approval Date Closing Date Success Rating at Completion* Contribution to Output
36318-013: Assam Power Sector Development Program Loan 2036/2037 10-Dec-03 28-Jun-05 Successful 600,000
35068-013: Gujarat Earthquake Rehabilitation and Reconstruction Program Loan 1826 26-Mar-01 06-Nov-07 Successful 41,902
29694-013: Gujarat Power Sector Development Program Loan 1804 13-Dec-00 20-Mar-07 Successful 1,379,010
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window.

Greenhouse gas emission reduction between 2004-2011: 2,437,000 tons of carbon dioxide equivalent per year

A proxy emission factor is to be used for developing Asia (countries where ADB may implement projects), which is 793.73 tons of carbon dioxide (CO2) per gigawatt-hour (GWh). This proxy factor is to be used to calculate emission reduction/ avoidance accruing from the projects, i.e., GWh generated using renewable energy, and GWh saved through efficiency improvement.

Contributing ADB Projects
Project Name Type of Assistance Approval Number Approval Date Closing Date Success Rating at Completion* Contribution to Output
36318-013: Assam Power Sector Development Program Loan 2036/2037 10-Dec-03 28-Jun-05 Successful 480,000
27068: Renewable Energy Development Project   1465 26-Sep-96 25-Oct-02 Highly successful / successful 1,957,000
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window.

Microfinance loan accounts opened / end borrowers reached between 2004-2011: 42,707

All those reached by microfinance lending or saving group activities of the project will be counted, including participants in self-help groups.

Contributing ADB Projects
Project Name Type of Assistance Approval Number Approval Date Closing Date Success Rating at Completion* Contribution to Output
35068-013: Gujarat Earthquake Rehabilitation and Reconstruction Program Loan 1826 26-Mar-01 06-Nov-07 Successful 14,147
30204-043: Housing Finance II Project-NHB Loan 1759/1761 21-Sep-00 10-Oct-07 Partly successful 28,560
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window.

Expressway built or updgraded between 2004-2011: 244 kilometers

Length of expressways (i.e. fully access-controlled highways) built or upgraded, expressed in km. Access control means no direct crossings. "Expressways" can include roads that in certain countries are called highways if they have full access control. "Upgrading" includes all activity to restore a degraded road to originally intended design capacity (repair/rehabilitation) and to improve on its design capacity (e.g. by widening). Upgrading does not cover road signage (only).

Contributing ADB Projects
Project Name Type of Assistance Approval Number Approval Date Closing Date Success Rating at Completion* Contribution to Output
34262-013: Private Sector Infrastructure Facility At State Level Project Loan 1871 11-Dec-01 06-Sep-07 Partly successful 68
29250-013: Surat-Manor Tollway Project Loan 1747 27-Jul-00 30-Sep-05 Highly successful 176
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window.

National highways and provincial, district, and rural roads built or upgraded between 2004-2011: 15,471 kilometers

Length of open access road networks built or upgraded in km (without full access control). "Upgrading" includes all activity to restore a degraded road to originally intended design capacity (repair/rehabilitation) and to improve on its design capacity (e.g. by widening). Upgrading does not cover road signage (only).

Contributing ADB Projects
Project Name Type of Assistance Approval Number Approval Date Closing Date Success Rating at Completion* Contribution to Output
36320-013: Rural Roads Sector I Project Loan 2018 20-Nov-03 30-Jun-09 Successful 9,575
34263-013: Madhya Pradesh State Roads Sector Development Program (Project) Loan 1959 05-Dec-02 10-Dec-08 Highly successful 1,603
34262-013: Private Sector Infrastructure Facility At State Level Project Loan 1871 11-Dec-01 06-Sep-07 Partly successful 52
35068-013: Gujarat Earthquake Rehabilitation and Reconstruction Program Loan 1826 26-Mar-01 06-Nov-07 Successful 3,600
29120-013: Rajasthan Urban Infrastructure Development Project Loan 1647 03-Dec-98 11-Jun-09 Successful 96
27132: Karnataka Urban Infrastructure Development Project   1415 14-Dec-95 07-Dec-04 Highly successful / successful 215
23251: National Highways Project   1274 29-Nov-93 10-Feb-03 Successful 330
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window.

Beneficiaries from road projects between 2004-2011: 140,400,000

Includes all beneficiaries defined by reports and recommendations of the President or project completion reports as beneficiaries of roads constructed or upgraded; generally those in the vicinity of the road or in the project area. Beneficiaries of railway projects are not included.

Contributing ADB Projects
Project Name Type of Assistance Approval Number Approval Date Closing Date Success Rating at Completion* Contribution to Output
36320-013: Rural Roads Sector I Project Loan 2018 20-Nov-03 30-Jun-09 Successful 11,000,000
34263-013: Madhya Pradesh State Roads Sector Development Program (Project) Loan 1959 05-Dec-02 10-Dec-08 Highly successful 77,000,000
35068-013: Gujarat Earthquake Rehabilitation and Reconstruction Program Loan 1826 26-Mar-01 06-Nov-07 Successful 1,200,000
29250-013: Surat-Manor Tollway Project Loan 1747 27-Jul-00 30-Sep-05 Highly successful 14,000,000
29120-013: Rajasthan Urban Infrastructure Development Project Loan 1647 03-Dec-98 11-Jun-09 Successful 3,000,000
27132: Karnataka Urban Infrastructure Development Project   1415 14-Dec-95 07-Dec-04 Highly successful / successful 1,200,000
23251: National Highways Project   1274 29-Nov-93 10-Feb-03 Successful 33,000,000
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window.

Water supply pipes installed or upgraded: length of network between 2004-2011: 5,450 kilometers

All sizes of pipes intended to transport water for urban water use for domestic and (non agricultural) business purposes, expressed in their aggregate length in the network, irrespective of pipe diameter, comprising mains as well as reticulation pipes. Both new and repaired/upgraded pipes are aggregated and they are not distinguished through subindicators.

Contributing ADB Projects
Project Name Type of Assistance Approval Number Approval Date Closing Date Success Rating at Completion* Contribution to Output
35068-013: Gujarat Earthquake Rehabilitation and Reconstruction Program Loan 1826 26-Mar-01 06-Nov-07 Successful 3,279
29120-013: Rajasthan Urban Infrastructure Development Project Loan 1647 03-Dec-98 11-Jun-09 Successful 1,763
27132: Karnataka Urban Infrastructure Development Project   1415 14-Dec-95 07-Dec-04 Highly successful / successful 408
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window.

New households served with water supply between 2004-2011: 7,111,000

This refers to all additional households that benefit from projects that offer piped or non-piped water supply systems, which is of a higher order than the system that the households used before. Non-piped supply may include standpipes.

Contributing ADB Projects
Project Name Type of Assistance Approval Number Approval Date Closing Date Success Rating at Completion* Contribution to Output
35068-013: Gujarat Earthquake Rehabilitation and Reconstruction Program Loan 1826 26-Mar-01 06-Nov-07 Successful 97,000
29120-013: Rajasthan Urban Infrastructure Development Project Loan 1647 03-Dec-98 11-Jun-09 Successful 7,000,000
27132: Karnataka Urban Infrastructure Development Project   1415 14-Dec-95 07-Dec-04 Highly successful / successful 14,000
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window.

Wastewater treatment capacity created between 2004-2011: 225,995 cubic meters

Wastewater treatment capacity added is equivalent to the maximum amount of cubic meter (m3) of waste water at the new or improved treatment plant intake per day. It excludes waste treatment capacity of septic tanks and the removal of the waste. Sewage received from residential, non-residential, and non-trade waste sources includes volumes collected in the sewage system due to storm water, illegal connection inflows, and infiltration to the sewerage system. Residential (domestic) sewage is the waterborne waste derived from human origin comprising fecal matter, urine, and liquid household waste from water closet pans, sinks, baths, basins, and similar fixtures designed for use in private dwellings.

Contributing ADB Projects
Project Name Type of Assistance Approval Number Approval Date Closing Date Success Rating at Completion* Contribution to Output
34262-013: Private Sector Infrastructure Facility At State Level Project Loan 1871 11-Dec-01 06-Sep-07 Partly successful 185
35068-013: Gujarat Earthquake Rehabilitation and Reconstruction Program Loan 1826 26-Mar-01 06-Nov-07 Successful 35,640
29120-013: Rajasthan Urban Infrastructure Development Project Loan 1647 03-Dec-98 11-Jun-09 Successful 170
27132: Karnataka Urban Infrastructure Development Project   1415 14-Dec-95 07-Dec-04 Highly successful / successful 190,000
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window.

New households served with sanitation between 2004-2011: 3,547,902

This refers to all additional households that benefit from projects offering a variety of sanitation systems to households that either did not benefit from sanitation systems before, or benefited from systems of lesser order. The situation at the end of the project is to be reflected.

Contributing ADB Projects
Project Name Type of Assistance Approval Number Approval Date Closing Date Success Rating at Completion* Contribution to Output
35068-013: Gujarat Earthquake Rehabilitation and Reconstruction Program Loan 1826 26-Mar-01 06-Nov-07 Successful 41,902
29120-013: Rajasthan Urban Infrastructure Development Project Loan 1647 03-Dec-98 11-Jun-09 Successful 3,500,000
27132: Karnataka Urban Infrastructure Development Project   1415 14-Dec-95 07-Dec-04 Highly successful / successful 6,000
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window.

Sewage treatment plants constructed in Mangalore, Udupi, Bhatkal, and Karwar are helping in the proper treatment and reuse of waste water in the fast-growing towns of Karnataka. During 2004-2011, ADB support has contributed an additional 225,995 cubic meters of water treatment capacity in India.