ADB's activities in Viet Nam span from projects in agriculture and natural resources, urban services, and public sector management to large infrastructure projects, particularly roads and energy. ADB's strategies and programs in the country have been carefully aligned with the government's development programs, and are particularly supportive of inclusive growth.
ADB is supporting Viet Nam by pursuing a country partnership strategy that seeks to remove key constraints to pro-poor, business-led development. In the coming years, ADB is also helping promote public–private partnerships and improve the efficiency of Viet Nam's economy.
Classrooms built or upgraded between 2004-2012: 3,152
Classrooms cover (i) classrooms; (ii) laboratory rooms, including those for science, computers, and languages; (iii) lecture halls; (iv) libraries and workshop facilities; (v) auditoriums; and (vi) sports facilities, which may include gyms, and basketball and volleyball courts.
Contributing ADB Projects
|
Project Name |
Type of Assistance |
Approval Number |
Approval Date |
Closing Date |
Success Rating at Completion* |
Contribution to Output |
|
31039-013: Teacher Training Project |
Loan |
1718 |
14-Dec-99 |
28-Nov-08 |
Successful |
182 |
|
25033-013: Vocational & Technical Education Project |
Loan |
1655 |
11-Dec-98 |
23-Oct-08 |
Successful |
266 |
|
25034: Lower Secondary Education Development Project |
Loan |
1537 |
16-Sep-97 |
12-Jun-06 |
Successful |
2,482 |
|
29204: Forestry Sector Project |
Loan |
1515 |
20-Mar-97 |
28-Nov-06 |
Successful |
200 |
|
40282-013: Emergency Rehabilitation of Calamity Damage Project |
Loan |
L2273 |
21-Nov-06 |
8-Aug-12 |
Successful |
22 |
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window. |
Teachers trained between 2004-2012: 34,904
The number of teachers or professors trained over the duration of the project as a result of the project, both pre-service in order to become teachers; and in-service, for teachers to acquire or improve their teaching capacity. Teachers refer to those employed in formal primary, secondary, and tertiary education.
Contributing ADB Projects
|
Project Name |
Type of Assistance |
Approval Number |
Approval Date |
Closing Date |
Success Rating at Completion* |
Contribution to Output |
|
31039-013: Teacher Training Project |
Loan |
1718 |
14-Dec-99 |
28-Nov-08 |
Successful |
7,431 |
|
25033-013: Vocational & Technical Education Project |
Loan |
1655 |
11-Dec-98 |
23-Oct-08 |
Successful |
4,709 |
|
25034: Lower Secondary Education Development Project |
Loan |
1537 |
16-Sep-97 |
12-Jun-06 |
Successful |
22,764 |
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window. |
Students benefiting from school improvement programs or direct support between 2004-2012: 1,695,298
Students benefiting from (i) school improvement programs (at the end of the project); or (ii) having received direct support through scholarships, feeding, or similar programs (total number over the duration of the project). School improvement programs include civil works and provision of equipment or furniture.
Contributing ADB Projects
|
Project Name |
Type of Assistance |
Approval Number |
Approval Date |
Closing Date |
Success Rating at Completion* |
Contribution to Output |
|
31039-013: Teacher Training Project |
Loan |
1718 |
14-Dec-99 |
28-Nov-08 |
Successful |
14,560 |
|
25033-013: Vocational & Technical Education Project |
Loan |
1655 |
11-Dec-98 |
23-Oct-08 |
Successful |
517,931 |
|
25034: Lower Secondary Education Development Project |
Loan |
1537 |
16-Sep-97 |
12-Jun-06 |
Successful |
1,154,000 |
|
29204: Forestry Sector Project |
Loan |
1515 |
20-Mar-97 |
28-Nov-06 |
Successful |
8,000 |
|
40282-013: Emergency Rehabilitation of Calamity Damage Project |
Loan |
L2273 |
21-Nov-06 |
8-Aug-12 |
Successful |
807 |
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window. |
Installed energy generation capacity between 2004-2012: 1,432 megawatt equivalent
The indicator, given in megawatt (MW) equivalent is the total incremental generating capacity of a generation project. This may be power sourced from renewable technology or from conventional sources e.g., oil, coal, or large hydro. A project may involve construction of a new power plant or simply acquisition of an asset, e.g., the private sector acquiring a government-owned coal plant. This includes the MW-equivalent capacity of additional heating supply as well as hydrocarbon-based energy added through production or additional import capacity. Energy export is excluded from Level 2 measurement as it does not add to the energy resources of a country.
Contributing ADB Projects
|
Project Name |
Type of Assistance |
Approval Number |
Approval Date |
Closing Date |
Success Rating at Completion* |
Contribution to Output |
|
36901-014: Phu My 3 |
Private Sector |
7178/1923 |
18-Oct-02 |
29-Mar-04 |
Highly successful / successful |
717 |
|
35914-014: Mekong Energy Co. Ltd. |
Private Sector |
7176/1906 |
02-Jul-02 |
31-Oct-02 |
Highly successful / successful |
715 |
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window. |
Transmission lines installed or upgraded between 2004-2012: 2,021 kilometers
The indicator covers power, gas, and oil transmission lines. It is the measure of the ground distance, in kilometers, traversed by the transmission line. For power transmission lines, we are looking for the simple distance from tower A to tower B and not the circuit-kilometers.
Contributing ADB Projects
|
Project Name |
Type of Assistance |
Approval Number |
Approval Date |
Closing Date |
Success Rating at Completion* |
Contribution to Output |
|
28187: Central & Southern Vietnam Power Distribution Project |
Loan |
1585 |
27-Nov-97 |
30-May-05 |
Highly successful / successful |
1,497 |
|
25096: Power Distribution Rehabilitation Project |
Loan |
1358 |
08-Jun-95 |
10-Apr-02 |
Highly successful / successful |
20 |
|
32273-013: Northern Power Transmission Sector Project |
Loan |
2128 |
13-Dec-04 |
10-May-12 |
Successful |
504 |
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window. |
Distribution lines installed or updgraded between 2004-2012: 4,976 kilometers
"Distribution lines installed or upgraded" is the aggregate of the following three sub-indicators: (i) km of power distribution lines installed or upgraded, generally at 110 kv or lower); (ii) km of district heating network pipes installed or upgraded; and (iii) km of urban gas supply network pipes installed or upgraded.
Contributing ADB Projects
|
Project Name |
Type of Assistance |
Approval Number |
Approval Date |
Closing Date |
Success Rating at Completion* |
Contribution to Output |
|
28187: Central & Southern Vietnam Power Distribution Project |
Loan |
1585 |
27-Nov-97 |
30-May-05 |
Highly successful / successful |
2,588 |
|
25096: Power Distribution Rehabilitation Project |
Loan |
1358 |
08-Jun-95 |
10-Apr-02 |
Highly successful / successful |
2,388 |
|
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available. |
New households connected to electricity between 2004-2012: 222,799
The indicator is the number of new households connected to the grid. Only new household connections resulting from a project are counted; households already connected to the grid and receiving improved services through a project are not counted. The number of new household connections resulting from a project is counted in total and not proportional to the ADB funding component only. The guiding principle is that ADB assistance is integral to the completion of the entire project; without the ADB assistance, the total target household connections would not be attained.
Contributing ADB Projects
|
Project Name |
Type of Assistance |
Approval Number |
Approval Date |
Closing Date |
Success Rating at Completion* |
Contribution to Output |
|
28187: Central & Southern Vietnam Power Distribution Project |
Loan |
1585 |
27-Nov-97 |
30-May-05 |
Highly successful / successful |
222,799 |
|
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available. |
Greenhouse gas emission reduction between 2004-2012: 132,140 tons of carbon dioxide equivalent per year
A proxy emission factor is to be used for developing Asia (countries where ADB may implement projects), which is 793.73 tons of carbon dioxide (CO2) per gigawatt-hour (GWh). This proxy factor is to be used to calculate emission reduction/ avoidance accruing from the projects, i.e., GWh generated using renewable energy, and GWh saved through efficiency improvement.
Contributing ADB Projects
|
Project Name |
Type of Assistance |
Approval Number |
Approval Date |
Closing Date |
Success Rating at Completion* |
Contribution to Output |
|
36901-014: Phu My 3 |
Private Sector |
7178/1923 |
18-Oct-02 |
29-Mar-04 |
Highly successful / successful |
2,565 |
|
35914-014: Mekong Energy Co. Ltd. |
Private Sector |
7176/1906 |
02-Jul-02 |
31-Oct-02 |
Highly successful / successful |
129,575 |
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window. |
Microfinance loan accounts opened / end borrowers reached between 2004-2012: 206,601
All those reached by microfinance lending or saving group activities of the project will be counted, including participants in self-help groups.
Small and medium-sized enterprise loan accounts opened or end borrowers reached between 2004-2012: 170,857
The definition of SME follows the definition as generally used in the country of the project.
Contributing ADB Projects
|
Project Name |
Type of Assistance |
Approval Number |
Approval Date |
Closing Date |
Success Rating at Completion* |
Contribution to Output |
|
31361-013: Rural Enterprise Finance Project |
Loan |
1802 |
12-Dec-00 |
07-Oct-08 |
Successful |
170,857 |
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window. |
National highways and provincial, district, and rural roads built or upgraded between 2004-2012: 5,846 kilometers
Length of open access road networks built or upgraded in km (without full access control). "Upgrading" includes all activity to restore a degraded road to originally intended design capacity (repair/rehabilitation) and to improve on its design capacity (e.g. by widening). Upgrading does not cover road signage (only).
Beneficiaries from road projects between 2004-2012: 87,074,681
Includes all beneficiaries defined by reports and recommendations of the President or project completion reports as beneficiaries of roads constructed or upgraded; generally those in the vicinity of the road or in the project area. Beneficiaries of railway projects are not included.
Contributing ADB Projects
|
Project Name |
Type of Assistance |
Approval Number |
Approval Date |
Closing Date |
Success Rating at Completion* |
Contribution to Output |
|
31367-013: Provincial Roads Improvement Sector Project |
Loan |
1888 |
18-Dec-01 |
08-Jul-10 |
Successful |
24,092,100 |
|
33301-013: Central Region Livelihood Project |
Loan |
1883 |
17-Dec-01 |
28-Apr-10 |
Successful |
2,987,680 |
|
32105-013: GMS:Greater Mekong Subregion:East West Corridor Project |
Loan |
1728 |
20-Dec-99 |
30-Mar-07 |
Successful |
1,137,900 |
|
30316-013: GMS: Phnom Penh-HCMC Road Improvement |
Loan |
1660 |
15-Dec-98 |
12-May-06 |
Successful |
10,293,400 |
|
30076-013: Third Road Improvement Component |
Loan |
1653 |
10-Dec-98 |
27-Apr-06 |
Successful |
15,313,500 |
|
29259: Rural Infrastructure Sector Project |
Loan |
1564 |
23-Oct-97 |
28-Sep-05 |
Highly successful / successful |
33,064,104 |
|
29204: Forestry Sector Project |
Loan |
1515 |
20-Mar-97 |
28-Nov-06 |
Successful |
35,997 |
|
40282-013: Emergency Rehabilitation of Calamity Damage Project |
Loan |
L2273 |
21-Nov-06 |
8-Aug-12 |
Successful |
150,000 |
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window. |
Water supply pipes installed or upgraded: length of network between 2004-2012: 2,651 kilometers
All sizes of pipes intended to transport water for urban water use for domestic and (non agricultural) business purposes, expressed in their aggregate length in the network, irrespective of pipe diameter, comprising mains as well as reticulation pipes. Both new and repaired/upgraded pipes are aggregated and they are not distinguished through subindicators.
Contributing ADB Projects
|
Project Name |
Type of Assistance |
Approval Number |
Approval Date |
Closing Date |
Success Rating at Completion* |
Contribution to Output |
|
28315-013: Third Provincial Towns Water Supply and Sanitation Project |
Loan |
1880 |
13-Dec-01 |
20-Jul-11 |
Successful |
1,050 |
|
27405: Second Provincial Towns Water Supply and Sanitation Project |
Loan |
1514 |
27-Feb-97 |
29-Mar-06 |
Highly successful / successful |
1,056 |
|
25180: Provincial Towns Water Supply and Sanitation Proje |
Loan |
1361 |
17-Aug-95 |
01-Dec-04 |
Highly successful / successful |
469 |
|
25095: Ho Chi Minh City Water Supply & Sanitation Rehabilitation |
Loan |
1273 |
29-Nov-93 |
17-Feb-04 |
Highly successful / successful |
76 |
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window. |
New households served with water supply between 2004-2012: 392,294
This refers to all additional households that benefit from projects that offer piped or non-piped water supply systems, which is of a higher order than the system that the households used before. Non-piped supply may include standpipes.
Contributing ADB Projects
|
Project Name |
Type of Assistance |
Approval Number |
Approval Date |
Closing Date |
Success Rating at Completion* |
Contribution to Output |
|
33301-013: Central Region Livelihood Project |
Loan |
1883 |
17-Dec-01 |
28-Apr-10 |
Successful |
31,402 |
|
28315-013: Third Provincial Towns Water Supply and Sanitation Project |
Loan |
1880 |
13-Dec-01 |
20-Jul-11 |
Successful |
128,609 |
|
27405: Second Provincial Towns Water Supply and Sanitation Project |
Loan |
1514 |
27-Feb-97 |
29-Mar-06 |
Highly successful / successful |
61,963 |
|
25180: Provincial Towns Water Supply and Sanitation Proje |
Loan |
1361 |
17-Aug-95 |
01-Dec-04 |
Highly successful / successful |
40,320 |
|
25095: Ho Chi Minh City Water Supply & Sanitation Rehabilitation |
Loan |
1273 |
29-Nov-93 |
17-Feb-04 |
Highly successful / successful |
130,000 |
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window. |
Wastewater treatment capacity created between 2004-2012: 167,000 cubic meters
Wastewater treatment capacity added is equivalent to the maximum amount of cubic meter (m3) of waste water at the new or improved treatment plant intake per day. It excludes waste treatment capacity of septic tanks and the removal of the waste. Sewage received from residential, non-residential, and non-trade waste sources includes volumes collected in the sewage system due to storm water, illegal connection inflows, and infiltration to the sewerage system. Residential (domestic) sewage is the waterborne waste derived from human origin comprising fecal matter, urine, and liquid household waste from water closet pans, sinks, baths, basins, and similar fixtures designed for use in private dwellings.
Contributing ADB Projects
|
Project Name |
Type of Assistance |
Approval Number |
Approval Date |
Closing Date |
Success Rating at Completion* |
Contribution to Output |
|
28315-013: Third Provincial Towns Water Supply and Sanitation Project |
Loan |
1880 |
13-Dec-01 |
20-Jul-11 |
Successful |
167,000 |
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window. |
New households served with sanitation between 2004-2012: 33,469
This refers to all additional households that benefit from projects offering a variety of sanitation systems to households that either did not benefit from sanitation systems before, or benefited from systems of lesser order. The situation at the end of the project is to be reflected.
Contributing ADB Projects
|
Project Name |
Type of Assistance |
Approval Number |
Approval Date |
Closing Date |
Success Rating at Completion* |
Contribution to Output |
|
33301-013: Central Region Livelihood Project |
Loan |
1883 |
17-Dec-01 |
28-Apr-10 |
Successful |
347 |
|
28315-013: Third Provincial Towns Water Supply and Sanitation Project |
Loan |
1880 |
13-Dec-01 |
20-Jul-11 |
Successful |
18,902 |
|
27405: Second Provincial Towns Water Supply and Sanitation Project |
Loan |
1514 |
27-Feb-97 |
29-Mar-06 |
Highly successful / successful |
14,170 |
|
25180: Provincial Towns Water Supply and Sanitation Proje |
Loan |
1361 |
17-Aug-95 |
01-Dec-04 |
Highly successful / successful |
50 |
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window. |
Land improved through irrigation services, drainage, and flood management between 2004-2012: 1,518,341 hectares
The rural land area improved through new/improved irrigation (and drainage) services and/or flood management. This indicator is the aggregate of 2 sub-indicators: (i) land area improved through irrigation (and drainage) services in hectares, and (ii) land area improved through flood management in hectares.
Contributing ADB Projects
|
Project Name |
Type of Assistance |
Approval Number |
Approval Date |
Closing Date |
Success Rating at Completion* |
Contribution to Output |
|
33301-013: Central Region Livelihood Project |
Loan |
1883 |
17-Dec-01 |
28-Apr-10 |
Successful |
3,062 |
|
29259: Rural Infrastructure Sector Project |
Loan |
1564 |
23-Oct-97 |
28-Sep-05 |
Highly successful / successful |
60,314 |
|
29204: Forestry Sector Project |
Loan |
1515 |
20-Mar-97 |
28-Nov-06 |
Successful |
210 |
|
25095: Ho Chi Minh City Water Supply & Sanitation Rehabilitation |
Loan |
1273 |
29-Nov-93 |
17-Feb-04 |
Highly successful / successful |
24 |
|
25019: Irrigation and Flood Protection Rehabilitation |
Loan |
1259 |
26-Oct-93 |
08-Apr-03 |
Highly successful / successful |
113,516 |
|
30292-013: Second Red River Basin Sector Project |
Loan |
1855 |
13-Nov-01 |
14-Feb-11 |
Successful |
1,298,000 |
|
40282-013: Emergency Rehabilitation of Calamity Damage Project |
Loan |
L2273 |
21-Nov-06 |
8-Aug-12 |
Successful |
43,215 |
*The above table reflects project ratings from project completion reports. These ratings are updated with those from the project completion report validation reports and/or project/program performance evaluation reports when these reports become available.
NOTE: Links open in a new window. |