| Activity |
Target Date |
Estimated Cost ($) |
Financing |
1. Draft Policy Statement -Review and adoption by EGP -Presentation to the Ministerial Meeting |
October 1999 December 1999 |
30,000 |
ADB |
2. Draft Regional MOU -Review of principles by EGP -Discussion of First Draft MOU -Second Draft MOU -Third Draft MOU -Presentation to EGP -Adoption by EPF -Presentation to the Ministerial Meeting |
October 1999 February 2000 December 2000 February 2001 June 2001 November 2001 January 2002 |
40,000 |
World Bank |
3. Regional Indicative Master Plan -Approval of TOR by EGP -Inception Report -Interim Report -Draft Final Report -Final Report
|
October 1999 December 2000 May 2001 November 2001 February 2002 |
950,000 |
ADB |
4. Regulatory and Institutional Framework -Discussion and Approval of TOR by EGP -Interim Report -Final Report |
November 2001 November 2002 May 2003 |
250,000 |
World Bank |
5. Regional Workshops a)Workshop No. 1 -Coordination of technical issues b)Workshop No. 2 -Institutional/Regulatory and Commercial issues c)Workshop No.3 -Project Financing:financing instruments and role of private sector d)Technical Visits NORDPOOL or MAPP |
February 2000
December 2000
November 2001
Mid 2001 |
100,000
100,000
100,000
80,000 |
World Bank
World Bank
World Bank
To be explored |