Review of ADB's Inspection Function:
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Activity | Target date | Status |
|---|---|---|
| ADB's Working Group on the Review of the Inspection Function (WG) meets to discuss work plan and timetable | November 2001 | Completed |
| WG meets to discuss problems, issues and possible solutions | December 2001 - March 2002 | Completed |
| Outcome of discussion presented to ADB's Steering Committee on the Review of the Inspection Function (SC) | January 2002 | Completed |
| Establish website links | January 2002 | Completed |
| Prepare Report on External Consultations to Review the Inspection Function | February - April 2002 | Completed |
| Recruit consultants to assist in reviewing policy | February 2002 | Completed |
| Post notice of review on website, inviting comments | March 2002 | Completed |
| Meetings by consultants with members of ADB's Board of Directors (Board), the Board Inspection Committee (BIC) members, members of WG and SC, other ADB staff, civil society (including NGOs), private sector, and institutions such as multilateral development banks (MDBs) | March - April 2002 June 2002 August 2002 |
Completed Completed Completed |
| Prepare an issues paper and post on website, inviting comments | April 2002 | Completed |
| Prepare 1st draft of working paper (with options) and executive summary | April 2002 | Completed |
| Post 1st draft working paper (with options) and executive summary on website and email/post to NGOs and other civil society and private sector, inviting comments | May 2002 | Completed |
| Hold consultations on 1st draft working paper in Tokyo, Manila (regional workshop), Frankfurt, Ottawa, and Washington DC with government officials, representatives of civil society (including NGOs), private sector and MDBs | June 2002 | Completed |
| Incorporate comments and prepare 2nd draft working paper (with options) and executive summary | July 2002 | Completed |
| Post 2nd draft working paper (with options) and executive summary on website and email/post to NGOs and other civil society and private sector, inviting comments | July 2002 | Completed |
| Hold special consultations in Karachi with project-affected people about their experiences in accessing the inspection process | August 2002 | Completed |
| Hold consultations on 2nd draft working paper in Phnom Penh, Kathmandu, Beijing, and Sydney (subregional workshops) with government officials, representatives of civil society (including NGOs), and private sector | August 2002 | Completed |
| Incorporate comments and prepare 3rd draft working paper (with recommendation) for ADB interdepartmental comments and ADB Management approval | September 2002 - February 2003 | Completed |
| Circulate the Working Paper to the Board and post on the web site for comments | February 2003 | Completed |
| Board consideration of the Working Paper | March 2003 | Completed |
| Board consideration of the Report (R-Paper) | May 2003 | Completed |