Project Data Sheet

Project Data Sheets (PDS) contain summary information on the project or program: Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

PDS Creation Date
PDS Updated as of

Project Name
Country Bhutan
Project/Program Number 28079-013
Status
Geographical Location Bhutan/ Thimphu and Phuentsholing Cities
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Sector and/or Subsector Classification Water supply and other municipal infrastructure and services
/ Water and Other Municipal Infrastructure and Services
Thematic Classification Economic growth
Environmental sustainability
Gender equity
Gender Mainstreaming Categories

Financing

Type/Modality of Assistance Approval Number Source of Funding Approved Amount (thousand)
0
TOTAL US$ 0

Summary of Environmental and Social Issues

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation and Consultation

During Project Design
During Project Implementation

Description

The objectives of the Project are to (i) further human development through environmental improvements; (ii) improve the urban environment through appropriate urban infrastructure development; (iii) promote the development of effective and sustainable management of urban services; and (iv) support economic growth through the development and management of sustainable and well-planned infrastructure development, and provision of urban services. The scope will include drainage improvements and river training works, infrastructure improvements, such as roads, drainage, a bridge, footpaths, and parking areas; and implementation assistance and training.

Project Rationale and Linkage to Country/Regional Strategy

Development Impact

Project Outcome

Description of Outcome
Progress Towards Outcome

Outputs and Implementation Progress

Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Status of Development Objectives
Material Changes

Business Opportunities

Date of First Listing
Consulting Services
A total of 52 person-months of consultants' input will be required (28 person-months of international and 24 person-months of domestic consultants) with the international consultants composed of a municipal engineer/implementation expert, a bridge engineer and a hydraulics engineer, and the domestic consultants composed of an architect and urban planners. Advance action to recruit consultants was approved by the Bank on 20 March 1998.
Procurement
The bridge contract in Phuentsholing will follow international competitive bidding procedures. As the size of various civil works will be extremely small, these will be carried out by local contractors on the basis of the Government's local competitive bidding procedures satisfactory to the Bank. Equipment and vehicles required for the Project will be carried out using international shopping procedures and/or direct purchase procedures.
Procurement and Consulting Notices
http://www.adb.org/projects/28079-013/business-opportunities

Timetable

Concept Clearance
Fact-finding 26 Jan 1998 to 08 Feb 1998
Management Review Meeting 20 Mar 1998
Approval 30 Jul 1998
Last Review Mission

Milestones

Approval No. Approval Signing Effectivity Closing
Original Revised Actual
Technical Assistance 2666 17 Oct 1996 25 Oct 1996 25 Oct 1996 28 Feb 1998

Contacts and Update Details

Responsible ADB Officer
Responsible ADB Department South Asia Department
Responsible ADB Divisions Urban Development and Water Division, SARD
Executing Agencies Ministry of Communications
Hon. Dasho Leki Dorji, Deputy Minister

Links

Project Website http://www.adb.org/projects/28079-013/main
List of Project Documents http://www.adb.org/projects/28079-013/documents