Project Name Provincial Power Supply
Project Number 28191-013
Country Cambodia
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 1794-CAM: Provincial Power Supply
Asian Development Fund US$ 18.60 million
Loan: Provincial Power Supply
Agence Francaise de Developpement US$ 2.50 million
Strategic Agendas
Drivers of Change
Sector / Subsector For classification - For classification
Gender Equity and Mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Banlung, Kampong Speu, Kampot, Prey Veng, Serey Sophon, Stung Treng, Svay Rieng, Takeo, and Battambang.
Safeguard Categories
Environment B
Involuntary Resettlement
Indigenous Peoples
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Michael Bristol
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Cambodia Resident Mission
Executing Agencies
Ministry of Industry and HandicraftNo. 45, Preah Norodom Blvd(41),12205
Phnom Penh, Cambodia
Electricite Du CambodgeMr. Tan Kim VinnElectricite du Cambodge, Street 19, Watt Phnom, Daun Penh District, Phnom Penh
Timetable
Concept Clearance 04 Jul 1996
Fact Finding 10 Feb 2000 to 24 Feb 2000
MRM 17 Jul 2000
Approval 05 Dec 2000
Last Review Mission -
PDS Creation Date 20 Feb 2007
Last PDS Update 27 Feb 2007

Loan

Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 2.50 Cumulative Contract Awards
ADB 0.00 - 0.00 0.00 %
Counterpart 0.00 Cumulative Disbursements
Cofinancing 2.50 - 0.00 0.00 %

LoanĀ 1794-CAM

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
05 Dec 2000 05 Apr 2001 01 Aug 2001 31 Dec 2004 31 Dec 2006 05 Apr 2007
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 21.10 Cumulative Contract Awards
ADB 18.60 05 Dec 2000 19.39 0.00 100%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 2.50 05 Dec 2000 19.39 0.00 100%

This project data sheet was generated from http://www.adb.org/projects/28191-013/main on 31 August 2015