Project Name GMS: Cambodia Road Improvement Project Engineering Design Update
Project Number 30240-012
Country Cambodia
Project Status Closed
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 3868-CAM: GMS: Cambodia Road Improvement Project Engineering Design Update
Technical Assistance Special Fund US$ 400,000.00
Strategic Agendas Inclusive economic growth
Drivers of Change Knowledge solutions
Sector / Subsector

Transport - Road transport (non-urban)

Gender Equity and Mainstreaming Some gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location

Safeguard Categories

Environment B
Involuntary Resettlement
Indigenous Peoples

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation

Business Opportunities

Consulting Services The TA will be undertaken by a reputable international consulting engineering company. A total of 16 person-months of specialists' inputs will be required. The expertise required will include highway engineering, pavement design, bridge engineering, road safety, hydrology, topology, geology and geotechnics and contract management. The consulting engineering company will be engaged by ADB in accordance with ADBs Guidelines on the Use of Consultants.
Procurement No civil works/goods are required.

Responsible Staff

Responsible ADB Officer Peter Broch
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Infrastructure Division, SERD
Executing Agencies
Ministry of Public Works and Transport
Minister Khy Tainglim
1st Floor West Building, Corner Norodom Boulevard Street 106 Phnom Penh, Cambodia

Timetable

Concept Clearance 21 Jun 1996
Fact Finding 28 Jan 2002 to 05 Feb 2002
MRM -
Approval -
Last Review Mission -
Last PDS Update 06 Dec 2006

TA 3868-CAM

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
21 May 2002 28 Jun 2002 28 Jun 2002 - 30 Sep 2003 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
400,000.00 0.00 0.00 0.00 0.00 0.00 400,000.00 21 May 2002 392,579.89

 