Project Data Sheet

Project Data Sheets (PDS) contain summary information on the project or program: Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

PDS Creation Date
PDS Updated as of 19 Apr 2010

Project Name Irrigation Management Transfer
Country Lao People's Democratic Republic
Project/Program Number 30254-012
Status Approved
Geographical Location
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Sector Agriculture, natural resources and rural development
Subsector Irrigation, Drainage, and Flood Protection
Strategic Agendas
Drivers of Change
Gender Equity and Mainstreaming Categories

Financing

Type/Modality of Assistance Approval Number Source of Funding Approved Amount (thousand)
Technical Assistance3189-0
TOTAL US$ 0

Summary of Environmental and Social Issues

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation and Consultation

During Project Design
During Project Implementation

Description

The Government has invested considerable resources in developing irrigation infrastructure throughout the country, especially since it complements its government food self-sufficiency program. Recent experience reveals that beneficiary farmers more effectively handle the management of such infrastructure themselves. Therefore, the Government has adopted a policy of handing over all management and financial responsibilities relating to irrigation systems to Water Users Associations. The Government has requested Bank support to assist in a widespread program to transfer medium and large-scale systems. The TA will assist the executing agency to prepare a strategy and a master plan for nationwide Irrigation Management Transfer (IMT) of such systems and will support formulating an investment proposal for the proposed IMT project. The master plan will essentially be a planning document to develop a prioritized program for achieving the national objective. The proposed IMT Project is expected to assist in implementing the first phase of the IMT program. The TA is expected to result in a sector type project based on criteria established for selection of individual schemes and preparing detailed design, cost estimates and economic and financial analysis for selected model schemes.

Project Rationale and Linkage to Country/Regional Strategy

Development Impact

Project Outcome

Description of Outcome
Progress Towards Outcome

Outputs and Implementation Progress

Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Status of Development Objectives
Material Changes

Business Opportunities

Date of First Listing 2006 Dec 18
Consulting Services
The TA will be implemented by a team of international and domestic consultants over a four months period expected to commence in September 1999 and end in December 1999. It is envisaged that 46.5 person-months of consulting services will be required, comprising 18 person-months of international consultants and 28.5 person-months of domestic consultants. The consultants should have proven expertise in handling all professional aspects of irrigation management issues in Asia and have direct experience in the irrigation sector in Lao PDR.
Procurement
Procurement and Consulting Notices
http://www.adb.org/projects/30254-012/business-opportunities

Timetable

Concept Clearance 28 Jul 1997
Fact-finding 01 Feb 1999 to 10 Feb 1999
Management Review Meeting
Approval 27 Apr 1999
Last Review Mission

Milestones

Approval No. Approval Signing Effectivity Closing
Original Revised Actual
Technical Assistance 3189 27 Apr 1999 17 Jun 1999 17 Jun 1999 30 Sep 2000

Utilization

Date Approval Number ADB (US$ thousand) Others (US$ thousand) Net Percentage
Cumulative Contract Awards
Cumulative Disbursements

TA Amount (US$ thousand)

Approval Number Approved Amount Revised Amount Total Commitment Uncommitted Balance Total Disbursement Undisbursed Balance
Technical Assistance 3189 650 650 635 15 635 15

Contacts and Update Details

Responsible ADB Officer C. R. Rajendran ( @adb.org)
Responsible ADB Department Southeast Asia Department
Responsible ADB Divisions Human and Social Development Division, SERD
Executing Agencies Ministry of Agriculture & Forestry-Irrigation Dep