Project Name Decentralized Irrigation Development and Management Sector Project
Project Number 30254-013
Country Lao People's Democratic Republic
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 1788-LAO: Decentralized Irrigation Development and Management Sector Project
Asian Development Fund US$ 15.50 million
Loan: Decentralized Irrigation Development and Management Sector Project
Agence Francaise de Developpement US$ 2.70 million
Loan 1788-LAO: Decentralized Irrigation Development and Management Sector Project (Supplementary)
Asian Development Fund US$ 117,000.00
Strategic Agendas Environmentally sustainable growth
Drivers of Change Partnerships
Sector / Subsector

Agriculture, natural resources and rural development - Irrigation

Gender Equity and Mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location The Project would be implemented in Bolikhamsay, Vientiane Municipality, Vientiane Province, Savannahkhet, Sayaboury and Luang Probang provinces on the basis of the area under irrigation and the number of existing irrigation systems.

Safeguard Categories

Environment B
Involuntary Resettlement
Indigenous Peoples

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation

Responsible Staff

Responsible ADB Officer C. Rajendran
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Lao Resident Mission
Executing Agencies
Ministry of Agriculture and Forestry
Mr. Pasonexay Insisiengmay
DIDMONPD@LAOTEL.COM
Department of Livestock and Fisheries
Ministry of Agriculture and Forestry

Timetable

Concept Clearance 11 Jul 1996
Fact Finding 20 Mar 2000 to 07 Apr 2000
MRM 19 May 2000
Approval -
Last Review Mission -
PDS Creation Date 29 Nov 2006
Last PDS Update 19 Apr 2010

LoanĀ 1788-LAO

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
28 Nov 2000 16 Feb 2001 07 May 2001 30 Jun 2007 30 Jun 2009 05 Feb 2010
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 24.22 Cumulative Contract Awards
ADB 15.62 28 Nov 2000 17.05 0.00 97%
Counterpart 5.90 Cumulative Disbursements
Cofinancing 2.70 28 Nov 2000 17.63 0.00 100%

 
This page was generated from http://www.adb.org/projects/30254-013/main on 26 June 2016