Project Data Sheet

Project Data Sheets (PDS) contain summary information on the project or program: Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

PDS Creation Date
PDS Updated as of

Project Name
Country China, People's Republic of
Project/Program Number 30386-012
Status
Geographical Location Liaoning Province
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Sector Energy
Subsector Electricity Transmission and Distribution
Strategic Agendas
Drivers of Change
Gender Equity and Mainstreaming Categories

Financing

Type/Modality of Assistance Approval Number Source of Funding Approved Amount (thousand)
0
TOTAL US$ 0

Summary of Environmental and Social Issues

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation and Consultation

During Project Design
During Project Implementation

Description

The proposed TA is required to upgrade the Feasibility Report for the ensuing project and to review and analyze the technical, economic, financial, environmental, resettlement, poverty analysis and institutional aspects of the Project and the Executing Agency (EA), the Liaoning Electric Power Company (LEPC). The TA will (i) review the least-cost generation expansion and long-term transmission master plans of the Northeast Power System and Liaoning Province; (ii) review the Distribution Systems Master Plans of Shenyang and Dalian cities; (iii) carry out an economic analysis of the Project based on Bank guidelines; (iv) improve the Initial Environmental Examination (IEE) report for the Project; (v) recommend investment components that could be included as a part of the Project that would directly benefit poorer rural and urban people in the Province; (vi) review EA's proposed program for the closure of small, old power plants in the Province for technical and environmental benefits; and (vii) carry out financial and institutional analysis of the EA.

Project Rationale and Linkage to Country/Regional Strategy

Development Impact

Project Outcome

Description of Outcome
Progress Towards Outcome

Outputs and Implementation Progress

Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Status of Development Objectives
Material Changes

Business Opportunities

Date of First Listing
Consulting Services
A total of 23.5 person-months of consulting time will be required, comprising 17.5 person-months of international consultants and 6.0 person-months of domestic consultants. The team of international consultants will include (i) Power Transmission/Substation Engineer as Team Leader; (ii) Power System Planning Engineer; (iii) Power Distribution Engineer; (iv) Power Economist; (v) Environment Specialist; (vi) Resettlement Specialist; (vii) Poverty Analyst/Specialist; (viii) Financial Analyst; and (ix) Institutional Specialist. The Domestic onsultants will include a Financial Analyst, a Power Economist, and a Social Sector Specialist.
Procurement
Procurement and Consulting Notices
http://www.adb.org/projects/30386-012/business-opportunities

Timetable

Concept Clearance
Fact-finding 13 Sep 1999 to 22 Sep 1999
Management Review Meeting
Approval 17 Dec 1999
Last Review Mission

Milestones

Approval No. Approval Signing Effectivity Closing
Original Revised Actual
Loan 1901 20 Dec 2001 11 Apr 2002 20 Feb 2003 31 Dec 2005 15 Nov 2006 29 Nov 2006
Technical Assistance 3346 17 Dec 1999 17 May 2000 17 May 2000 30 Nov 2000 30 Jun 2003

Utilization

Date Approval Number ADB (US$ thousand) Others (US$ thousand) Net Percentage
Cumulative Contract Awards
22 Aug 2014 Loan 1901 0 0 90.00%
Cumulative Disbursements
22 Aug 2014 Loan 1901 0 0 100.00%

TA Amount (US$ thousand)

Approval Number Approved Amount Revised Amount Total Commitment Uncommitted Balance Total Disbursement Undisbursed Balance
Technical Assistance 3346 0 0 0 0 0 0

Contacts and Update Details

Responsible ADB Officer
Responsible ADB Department East Asia Department
Responsible ADB Divisions Energy Division, EARD
Executing Agencies Liaoning Electric Power Co. Ltd.
Mr. Fan Chongmin, Dept. of Int'l. Cooperation

Links

Project Website http://www.adb.org/projects/30386-012/main
List of Project Documents http://www.adb.org/projects/30386-012/documents