Project Name Second Education Development Project
Project Number 31213-013
Country Mongolia
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 1908-MON: Second Education Development Project
Asian Development Fund US$ 14.00 million
Loan: Second Education Development Project
Japan International Cooperation Agency US$ 45.00 million
Nordic Development Fund US$ 4.80 million
Strategic Agendas
Drivers of Change
Sector / Subsector For classification - For classification
Gender Equity and Mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Project activities will be implemented nationwide, with greatest emphasis on improving educational services to the poorest communities in rural aimags.
Safeguard Categories
Environment C
Involuntary Resettlement
Indigenous Peoples
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Wolfgang G. Kubitzki
Responsible ADB Department East Asia Department
Responsible ADB Division Urban and Social Sectors Division, EARD
Executing Agencies
Ministry of Education,Culture and ScienceMr. R. BandiiLYANHUA@MECS.GOV.MNGovernment Building-III, Suite # 514,
Baga toiruu-44, Sukhbaatar district
Ulaanbaatar,Mongolia
Timetable
Concept Clearance 18 May 1997
Fact Finding 01 Oct 2001 to 20 Oct 2001
MRM 11 Jan 2002
Approval 06 Aug 2002
Last Review Mission -
PDS Creation Date 18 Dec 2006
Last PDS Update 03 Feb 2009

Loan

Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 54.50 Cumulative Contract Awards
ADB 0.00 - 0.00 0.00 %
Counterpart 4.70 Cumulative Disbursements
Cofinancing 49.80 - 0.00 0.00 %

LoanĀ 1908-MON

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
06 Aug 2002 26 Aug 2002 19 Nov 2002 30 Jun 2008 - 15 Jun 2009
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 68.50 Cumulative Contract Awards
ADB 14.00 06 Aug 2002 15.50 0.00 100%
Counterpart 4.70 Cumulative Disbursements
Cofinancing 49.80 06 Aug 2002 15.50 0.00 100%

This project data sheet was generated from http://www.adb.org/projects/31213-013/main on 30 August 2015