Project Data Sheet

Project Data Sheets (PDS) contain summary information on the project or program: Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

PDS Creation Date
PDS Updated as of

Project Name
Country China, People's Republic of
Project/Program Number 32121-012
Status
Geographical Location Shanghai
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Sector Water supply and other municipal infrastructure and services
Subsector Waste Management
Strategic Agendas
Drivers of Change
Gender Equity and Mainstreaming Categories

Financing

Type/Modality of Assistance Approval Number Source of Funding Approved Amount (thousand)
0
TOTAL US$ 0

Summary of Environmental and Social Issues

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation and Consultation

During Project Design
During Project Implementation

Description

The technical assistance (TA) will help (i) firm the overall strategy and master plan for development/redevelopment of the Project area including proposals for land use, transportation and redevelopment of the Creek; (ii) adjust the existing feasibility studies for the proposed components including assessment of technical viability, least cost and cost effectiveness; (iii) prepare the cost estimates and financing plan, including arrangement for possible commercial cofinancing and/or private sector investment; (iv) recommend an improved institutional framework for water quality management, monitoring and enforcement of waste control measures, provision of Project services, and urban redevelopment; (v) prepare a capacity building program based on a detailed assessment of institutional capacity of Shanghai Suzhou Creek Rehabilitation Project Head Office (SSCRPHO) and involved Shanghai Municipal Government (SMG) agencies; (vi) prepare a Project implementation schedule; (vii) refine the existing environmental impact assessment; (vii) refine the existing social impact assessment, resettlement plan, and program to promote public awareness and participation; (ix) identify a strategy for cost recovery and revenue generation; (x) conduct economic analyses of the various components and financial analyses of the responsible agencies; (xi) prepare documents and other requirements for Bank loan processing; and (xii) provide an opportunity for senior officials of SMG to visit other cities with similar water resource management, pollution control, and urban renewal program.

Project Rationale and Linkage to Country/Regional Strategy

Development Impact

Project Outcome

Description of Outcome
Progress Towards Outcome

Outputs and Implementation Progress

Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Status of Development Objectives
Material Changes

Business Opportunities

Date of First Listing
Consulting Services
The total input of the consultants is estimated at 54 person-months, consisting of 23 person-months of international inputs and 31 of domestic. All consultants will be selected in accordance with the Bank's Guidelines on the Use of Consultants.
Procurement
Procurement and Consulting Notices
http://www.adb.org/projects/32121-012/business-opportunities

Timetable

Concept Clearance
Fact-finding 07 Mar 1998 to 17 Mar 1998
Management Review Meeting
Approval 04 Jun 1998
Last Review Mission

Milestones

Approval No. Approval Signing Effectivity Closing
Original Revised Actual
Technical Assistance 3025 04 Jun 1998 22 Jun 1998 22 Jun 1998 31 Oct 1999
Technical Assistance 3211 29 Jun 1999 14 Mar 2000 14 Mar 2000 31 May 2002

Utilization

Date Approval Number ADB (US$ thousand) Others (US$ thousand) Net Percentage
Cumulative Contract Awards
Cumulative Disbursements

TA Amount (US$ thousand)

Approval Number Approved Amount Revised Amount Total Commitment Uncommitted Balance Total Disbursement Undisbursed Balance
Technical Assistance 3025 0 0 0 0 0 0
Technical Assistance 3211 0 0 0 0 0 0

Contacts and Update Details

Responsible ADB Officer
Responsible ADB Department East Asia Department
Responsible ADB Divisions Urban and Social Sectors Division, EARD
Executing Agencies Anhui Provincial Finance Bureau
Mr. An Chengyao, Deputy Director, SSCRPHO

Links

Project Website http://www.adb.org/projects/32121-012/main
List of Project Documents http://www.adb.org/projects/32121-012/documents