Project Data Sheet

Project Data Sheets (PDS) contain summary information on the project or program: Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

PDS Creation Date
PDS Updated as of

Project Name
Country China, People's Republic of
Project/Program Number 32526-013
Status
Geographical Location
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Sector Transport and ICT
Subsector Road Transport
Strategic Agendas
Drivers of Change
Gender Equity and Mainstreaming Categories

Financing

Type/Modality of Assistance Approval Number Source of Funding Approved Amount (thousand)
0
TOTAL US$ 0

Summary of Environmental and Social Issues

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation and Consultation

During Project Design
During Project Implementation

Description

The Changchun-Harbin Expressway Project will promote economic and social development in the northeastern part of the country by completing a key section of the transport infrastructure. The Project will (i) improve access from Heilongjiang Province and parts of Jilin Province to the more developed provinces of the east and south, (ii) provide additional transport capacity and reduce transport costs in the Project area to enhance business and trade opportunities and attract investment, (iii) alleviate congestion and reduce accidents on existing roads, (iv) improve access for trade between the PRC and the Russian Federation and Mongolia, (v) enhance road safety standards on the Project and related facilities. and (vi) support the corporatization of expressway construction and operations. The Changyu Expressway component comprises (i) construction of about 161 km of four-lane access controlled toll expressway between Changchun and the Lalin River, including two Changchun ring road sections, interchanges, service areas, a large bridge and link roads; (ii) procurement of equipment for toll collection, traffic management and safety, communications, highway maintenance, vehicle-axle load testing, and office administration; and (iii) consulting services for engineering design, construction supervision, contract management, road safety, human resource development and training, and benefit monitoring and evaluation.

Project Rationale and Linkage to Country/Regional Strategy

Increasing demand associated with the PRC's rapid economic growth has created bottlenecks that are evident in all transport modes. The Project will remove a major bottleneck on the Northeast road transport corridor. The proposed Project will promote economic growth by reducing the cost of transport, enhance the safety of road transport, and support the development of new corporate structures for expressway management in both provinces. The Project is consistent with the Government's current economic policy of stimulating the domestic market through infrastructure investment to offset the declining production of state-owned enterprises (SOEs). The Project will provide quicker and cheaper transport to major seaports from these landlocked provinces, sustain international trade, encourage foreign direct investment especially in agroprocessing activities, and sustain employment levels in two provinces with high levels of SOE production. The Project will complement several completed and ongoing Bank-financed road sector invetments in the Northeastern road transport corridor.

Development Impact

Project Outcome

Description of Outcome
Progress Towards Outcome

Outputs and Implementation Progress

Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Status of Development Objectives
Material Changes

Business Opportunities

Date of First Listing
Consulting Services
For the Changyu Expressway component, about 5,700 person-months of domestic consultant services will be required for construction supervision and training, and about 10 person-months of international consultant services for advice on road safety, pavement design and construction, contracts management, and monitoring and evaluation, and to assist in drawing up a human resource development and training plan for Jilin Provincial Expressway Corporation staff. Training will be provided in such topics as expressway operations and maintenance, and environmental protection. Consultants financed under the loan will be selected and engaged in accordance with the Bank's Guidelines on the Use of Consultants and other arrangements acceptable to the Bank on the selection and engagement of domestic consultants.
Procurement
Major civil works contracts and goods and services financed under the loans will be procured through international competitive bidding in accordance with the Bank's Guidelines for Procurement. Most equipment also will be procured through international competitive bidding and through international shopping in some cases.
Procurement and Consulting Notices
http://www.adb.org/projects/32526-013/business-opportunities

Timetable

Concept Clearance
Fact-finding 13 Apr 1998 to 29 Apr 1998
Management Review Meeting 19 Jun 1998
Approval 27 Nov 1998
Last Review Mission

Milestones

Approval No. Approval Signing Effectivity Closing
Original Revised Actual

Contacts and Update Details

Responsible ADB Officer
Responsible ADB Department East Asia Department
Responsible ADB Divisions Transport and Communications Division, EARD
Executing Agencies Jilin Provincial Expressway Corporation

Links

Project Website http://www.adb.org/projects/32526-013/main
List of Project Documents http://www.adb.org/projects/32526-013/documents