Project Name Xi'an Urban Transport
Project Number 33459-012
Country China, People's Republic of
Project Status Closed
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 3907-PRC: Xi'an Urban Transport
Italy Fund US$ 250,000.00
Strategic Agendas Inclusive economic growth
Drivers of Change Partnerships
Sector / Subsector

Transport - Urban public transport

Gender Equity and Mainstreaming No gender elements
Description The TA aims to assist the Government in preparing an urban transport project to facilitate growth and poverty reduction by providing efficient and safe urban transport infrastructure and services, and to support policy reform and institutional development in the urban transport sector. The TA will (i) assist the Xi'an Municipal Government in refining the feasibility study, environmental impact assessment, and resettlement plan in conformity with ADB's requirements, and (ii) review the urban transport sector issues, such as urban transport policy and regulations, public transport, vehicle emission controls, road safety, and non-motorized transport, and prepare a policy and institutional development component under the Project.
Project Rationale and Linkage to Country/Regional Strategy
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Xi'an Municipality
Safeguard Categories
Environment A
Involuntary Resettlement
Indigenous Peoples
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Business Opportunities
Consulting Services About 18 person-months of international consultants and 23 person-months of domestic consultants are required with expertise in road engineering, traffic engineering, urban transport planning/public transport, transport economics and finance, environmental analysis, resettlement planning, social and poverty analysis. Consultants were fielded on 2 December 2002.
Procurement N.A.
Responsible ADB Officer Makoto Ojiro
Responsible ADB Department East Asia Department
Responsible ADB Division Transport and Communications Division, EARD
Executing Agencies
Xi'an Municipal Urban & Rural Constrction Commssn
Mr. Mao Zhongan
51 Housaimen Street Xi'an 710003, People's Rep of China Mr. Wang Dean, Deputy Manager
Concept Clearance 10 Mar 2002
Fact Finding 05 Jun 2002 to 13 Jun 2002
Approval 27 Aug 2002
Last Review Mission -
Last PDS Update 03 Jan 2007

TA 3907-PRC

Approval Signing Date Effectivity Date Closing
Original Revised Actual
27 Aug 2002 23 Sep 2002 23 Sep 2002 30 Apr 2003 28 Feb 2005 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
0.00 250,000.00 0.00 0.00 0.00 0.00 250,000.00 27 Aug 2002 749,991.55

This project data sheet was generated from on 28 November 2015