Project Data Sheet

Project Data Sheets (PDS) contain summary information on the project or program: Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

PDS Creation Date 27 Nov 2006
PDS Updated as of 21 Oct 2013

Project Name Henan Wastewater Management and Water Supply Sector Project
Country China, People's Republic of
Project/Program Number 34473-013
Status Closed
Geographical Location Henan Province
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Sector and/or Subsector Classification Water supply and other municipal infrastructure and services
/ Waste Management
Strategic Agendas
Drivers of Change
Gender Mainstreaming Categories

Financing

Type/Modality of Assistance Approval Number Source of Funding Approved Amount (thousand)
Loan2207Ordinary capital resources100,000
Counterpart 72,800
TOTAL US$ 172,800

Safeguard Categories

For more information about the safeguard categories, please see http://www.adb.org/site/safeguards/safeguard-categories

Environment A
Involuntary Resettlement A
Indigenous Peoples C

Summary of Environmental and Social Issues

An environmental impact assessment was undertaken and the summary was circulated to the Board on 29 March 2005. Semi-annual environmental monitoring reports are required during the Project implementation. According to the Summary Resettlement Plan, the Project will temporarily occupy 173 ha of state and collective land, affecting 1,183 urban and rural households (4,663 people). Only 8 residential houses with 33 people need to be relocated. Detailed Resettlement Plan was prepared for each subproject, of which 17 have been approved by ADB. The remaining two are being reviewed. National Research Center for Resettlement of Hohai University has been engaged for independent monitoring and evaluation during Project implementation.

Environmental Aspects
An environmental impact assessment was undertaken and the summary was circulated to the Board on 29 March 2005. Semi-annual environmental monitoring reports are required during the Project implementation.
Involuntary Resettlement
According to the Summary Resettlement Plan, the Project will temporarily occupy 173 ha of state and collective land, affecting 1,183 urban and rural households (4,663 people). Only 8 residential houses with 33 people need to be relocated. Detailed Resettlement Plan was prepared for each subproject. National Research Center for Resettlement of Hohai University has been engaged for independent monitoring and evaluation during Project implementation.
Indigenous Peoples
n.a.

Stakeholder Communication, Participation and Consultation

During Project Design
Consultations with stakeholders, including various levels governments, implementing agencies, and beneficiaries were undertaken.
During Project Implementation
Consultations with stakeholders, including various levels governments, implementing agencies, and beneficiaries were undertaken.

Description

The development objective of the Henan provincial government (HPG) for the sector is to enhance (i) quality of life of the rapidly increasing urban population in the Hai River Basin (HRB), and (ii) economic competitiveness to sustain economic growth in key municipalities, by alleviating degradation of water resources and improving the quality of the urban environment. To meet this objective, the Project is designed to increase the collection and treatment of wastewater, and to reduce reliance on abstraction of groundwater from shallow wells (most of which are polluted by wastewater) in the project cities through physical investment, and institutional and financial reforms. The Project will support water quality improvement in several canal and river systems in the project cities through physical investment and improved water management. In addition, the Project will help strengthen water resource protection in the HRB through improved and integrated planning, water quality monitoring, and environmental management. The Project has identified 19 physical investment subprojects (8 representative and 11 candidate subprojects) to provide improved wastewater collection and treatment, and water supplies in the 15 project cities. The Project also identified the need for capacity building and training for the project institutions, including county water utility companies. The Project adopts a sector loan approach and will support an area and time slice of the Government?s Henan Hai River Basin Plan, which serves as a sector development plan for the HRB.

Project Rationale and Linkage to Country/Regional Strategy

To be determined during fact-finding. The water resource and availability varies significantly across regions and by season, and is one of the biggest challenges facing the PRC. Demand for water is rising with increasing urbanization; more than half of the population will live in cities by 2030. Despite the water shortage, only 34% of urban wastewater is treated. More investment is needed to supply clean drinking water and to treat wastewater and sewerage. Supporting projects for urban wastewater, sewage treatment, water supply, and water resources management is a priority of ADB's Operational Country Strategy in the PRC. Henan is the second largest polluting province in the Hai River basin next to Hebei. The main rivers in the Hai River basin in Henan flow into Bohai Bay through Hebei and Tianjin City. Upstream pollution control is essential to achieve the water quality targets of downstream rivers and lakes. This project will be the third ADB intervention in the Hai River basin, following the Hebei and Tianjin projects. The proposed Project will be pro-poor through its environmental protection, support of economic growth, and provisions to ensure access to sanitation for the poor. Environmental improvement is qualitatively linked to poverty reduction. The Project is listed in ADB's CSPU (2003-2005).

Development Impact

Improved urban environment and public health of the residents in the southern part of the Hai River Basin.

Project Outcome

Description of Outcome
Strengthened water supply and wastewater services in 15 project cities.
Progress Towards Outcome
The project has improved the environment and public health and safety in the project counties and provide improved wastewater for the service areas according to the implementing agencies report. The 17 subprojects have passed through the environment management completion review and acceptance by municipality environment authorities.

Outputs and Implementation Progress

Description of Project Outputs
1. Increased collection and treatment of urban wastewater in the project cities. 2. Adequate urban water supplies (in terms of quantity and quality) for project cities. 3. Reformed and integrated water and wastewater utilities. 4. An effective WWTP operating regime introduced. 5. Improved public awareness of health and environment.
Status of Implementation Progress (Outputs, Activities, and Issues)
The project has made significant progress on construction of wastewater and water supply facilities. Under 14 WWTP subprojects, a wastewater treatment capacity of 540,500 m3 per day has been built up. With the Puyang wastewater management subproject, wastewater collection systems with a capacity of 50,000 m3 per day have been built up. Thus, a total capacity of 590,500 m3 per day, or 100.1% of the proposed capacity for wastewater treatment as per the appraisal has been completed. Associated intercepting/trunk sewers with a total length of 716.5 kilometers (km), or 107% of the planned have been completed. A water supply capacity of 150,000 m3/day has been developed. A total of 251 km, or 109% of the planned water supply pipelines have been constructed. The overall capacity of wastewater management and water supply will be achieved with the completion of remaining works. The wastewater and water supply facilities currently serve for over 1.5 million people in the project areas. Wastewater Management Component. This component includes 15 wastewater subprojects, of which 14 subprojects involve construction of wastewater treatment plants (WWTPs) and sewer networks and one subproject (i.e. Puyang wastewater subproject) involves only wastewater collection systems. All WWTPs have been completed with the domestic acceptance approval and been in commission. Water Supply Component. The component includes four subprojects involving construction of water supply plants (WSPs) and water pipelines. All WSPs are in full operation. Institutional Capacity-Building Component. All WWTP and WSP companies have developed operational procedures. Over 80% of staff have achieved necessary skill level through various training and capacity building activities. The HFD and implementing agencies have undertaken trainings on technical and engineering management and project administration effectively.
Status of Development Objectives
Material Changes

Business Opportunities

Date of First Listing 2006 Jul 24
Consulting Services
Twenty eight person-months of international and 300 person-months of domestic consulting services are required, with expertise in international competitive bidding and international shopping procedures, including international specifications, bid evaluation, contracts, quality control, and project performance management systems. The consultants provide guidance and training for capacity building to ensure that (i) the IAs in the project cities are able to function as effective project management units; (ii) appropriate institutional, managerial, financial, and operational arrangements are in place to enhance operational effectiveness, management efficiency, and financial sustainability; (iii) the water supply/wastewater companies become effective operating companies upon completion of implementation; and (iv) social, resettlement, and environmental impacts are monitored and mitigated. Consultants were recruited in accordance with ADB's Guidelines on the Use of Consultants and other arrangements satisfactory to ADB on the engagement of domestic consultants. Detailed design engineering and construction supervision is carried out by qualified local design institutes recruited by the project cities with local counterpart financing.
Procurement
ADB-financed civil works, equipment and materials are procured in accordance with ADB's Guidelines for Procurement. Major contracts for equipment and materials are tendered through international competitive bidding or international shopping procedures, depending on the contract amount. Civil works contracts are procured through local competitive bidding.
Procurement and Consulting Notices
http://www.adb.org/projects/34473-013/business-opportunities

Timetable

Concept Clearance 13 Jul 2000
Fact-finding 18 Jan 2005 to 04 Feb 2005
Management Review Meeting 13 Apr 2005
Approval 09 Dec 2005
Last Review Mission

Milestones

Approval No. Approval Signing Effectivity Closing
Original Revised Actual
Loan 2207 09 Dec 2005 23 Feb 2006 24 May 2006 30 Jun 2011 31 Dec 2011 06 Jun 2012

Utilization

Date Approval Number ADB (US$ thousand) Others (US$ thousand) Net Percentage
Cumulative Contract Awards
01 Aug 2014 Loan 2207 94,313 0 94.00%
Cumulative Disbursements
01 Aug 2014 Loan 2207 100,000 0 100.00%

Status of Covenants

Covenants are categorized under the following categories—audited accounts, safeguards, social, sector, financial, economic, and others. Covenant compliance is rated by category by applying the following criteria: (i) Satisfactory—all covenants in the category are being complied with, with a maximum of one exception allowed, (ii) Partly Satisfactory—a maximum of two covenants in the category are not being complied with, (iii) Unsatisfactory—three or more covenants in the category are not being complied with. As per the 2011 Public Communications Policy, covenant compliance ratings for Project Financial Statements apply only to projects whose invitation for negotiation falls after 2 April 2012.

Approval No. Category
Sector Social Financial Economic Others Safeguards Project Financial Statements
Loan 2207 Satisfactory Satisfactory Satisfactory Satisfactory Satisfactory

Contacts and Update Details

Responsible ADB Officer Zhiming Niu (niuzhm@adb.org)
Responsible ADB Department East Asia Department
Responsible ADB Divisions PRC Resident Mission
Executing Agencies Henan Provincial Government (HPG)
Li Suyun

Links

Project Website http://www.adb.org/projects/34473-013/main
List of Project Documents http://www.adb.org/projects/34473-013/documents