Project Data Sheet

Project Data Sheets (PDS) contain summary information on the project or program: Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

PDS Creation Date
PDS Updated as of

Project Name
Country Cambodia
Project/Program Number 34541-013
Status
Geographical Location
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Sector Multisector
Subsector Multisector
Strategic Agendas
Drivers of Change
Gender Equity and Mainstreaming Categories

Financing

Type/Modality of Assistance Approval Number Source of Funding Approved Amount (thousand)
0
TOTAL US$ 0

Safeguard Categories

For more information about the safeguard categories, please see http://www.adb.org/site/safeguards/safeguard-categories

Environment B

Summary of Environmental and Social Issues

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation and Consultation

During Project Design
During Project Implementation

Description

The main objective of the Project is to assist the Government to rehabilitate key infrastructure damaged by the 2000 floods, and to enable the early restoration of economic and social activity, especially for the rural poor. The Project provides for rehabilitation of facilities in key sectors to pre-flood levels. The Project will rehabilitate flood-damaged facilities by providing civil works; equipment and materials; and consulting services for design work, evaluation and implementations, supervision and coordination

Project Rationale and Linkage to Country/Regional Strategy

The unprecedented intensity and duration of the 2000 floods have resulted in major disruption of people's lives and economic activitie, and have severely damaged physicla infrastructure. The cost of rehabilitation is beyond the capacity of the Government. By providing funds for rehabilitation works, the Project will permit the Government to maintain its development programs at a reasonable level.

Development Impact

Project Outcome

Description of Outcome
Progress Towards Outcome

Outputs and Implementation Progress

Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Status of Development Objectives
Material Changes

Business Opportunities

Date of First Listing
Consulting Services
The Project is expected to use 473 person-months of international and 1,134 person-months of domestic consultants, some of which will be contracted under existing contract arrangements.
Procurement
Advance action and retroactive financing has been approved for certain components, for eligible expenditures after the date of appraisal and subject to approval of the loan by ADB. As the Project sites are scattered throughout the country, and involve relatively small civil works contracts, the civil works are not likely to attract the interest of international contractors. All civil works contracts for the rehabilitation of roads and bridgets with a value of $2.5 million or more, will be awarded on the basis of international competitive bidding procedures. For suitable contract packages under $2.5 million,local competitive bidding procedures will be followed.
Procurement and Consulting Notices
http://www.adb.org/projects/34541-013/business-opportunities

Timetable

Concept Clearance
Fact-finding
Management Review Meeting
Approval 21 Dec 2000
Last Review Mission

Milestones

Approval No. Approval Signing Effectivity Closing
Original Revised Actual
Loan 1824 21 Dec 2000 22 Dec 2000 22 Dec 2000 30 Jun 2004 17 Jan 2006

Utilization

Date Approval Number ADB (US$ thousand) Others (US$ thousand) Net Percentage
Cumulative Contract Awards
20 Sep 2014 Loan 1824 0 0 98.00%
Cumulative Disbursements
20 Sep 2014 Loan 1824 0 0 100.00%

Status of Covenants

Covenants are categorized under the following categories—audited accounts, safeguards, social, sector, financial, economic, and others. Covenant compliance is rated by category by applying the following criteria: (i) Satisfactory—all covenants in the category are being complied with, with a maximum of one exception allowed, (ii) Partly Satisfactory—a maximum of two covenants in the category are not being complied with, (iii) Unsatisfactory—three or more covenants in the category are not being complied with. As per the 2011 Public Communications Policy, covenant compliance ratings for Project Financial Statements apply only to projects whose invitation for negotiation falls after 2 April 2012.

Approval No. Category
Sector Social Financial Economic Others Safeguards Project Financial Statements
Loan 1824

Contacts and Update Details

Responsible ADB Officer
Responsible ADB Department Southeast Asia Department
Responsible ADB Divisions Country Coordination and Regional Cooperation Division, SERD
Executing Agencies Project Monitoring and Coordination Unit
*

Ministry of Public Works and Transport
*

Ministry of Health
*

Ministry of Rural Development
*

Ministry of Water Resources and Meteorology
*

Ministry of Education, Youth and Sports
*

Links

Project Website http://www.adb.org/projects/34541-013/main
List of Project Documents http://www.adb.org/projects/34541-013/documents