Project Data Sheet

Project Data Sheets (PDS) contain summary information on the project or program: Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

PDS Creation Date 21 Nov 2006
PDS Updated as of 15 Dec 2006

Project Name Assam Power Sector Development Program (Project Loan)
Country India
Project/Program Number 36318-013
Status Approved
Geographical Location Assam, India
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Sector Energy
Subsector Energy Sector Development
Strategic Agendas
Drivers of Change
Gender Equity and Mainstreaming Categories

Financing

Type/Modality of Assistance Approval Number Source of Funding Approved Amount (thousand)
Loan2037-0
TOTAL US$ 0

Safeguard Categories

For more information about the safeguard categories, please see http://www.adb.org/site/safeguards/safeguard-categories

Environment B

Summary of Environmental and Social Issues

The Project will have limited environmental impacts during construction and operational stages. The environmental assessment of policy actions of the reform program shows that the reform will benefit the environment. The establishment of the social and environmental management cell within ASEB will help promote environmentally responsible activities within ASEB. Capacity building of the cell will be supported by the TA under the investment loan.

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation and Consultation

ASEB engaged local NGOs/Representatives to monitor and verify the claims of affected people that may arise in the course of acquisition of land for the construction of proposed substations. Social and Environmental Cell was established in Feb 2004 and reconstituted on 18Apr06. Full Resettlement Plan for 220/132kV Transmission line was prepared by ASEB and posted in ADB website in May 2006.

During Project Design
During Project Implementation

Description

Improve the quality and quantity of electricity supply by strengthening transmission and distribution systems, introduce revenue management system; and rehabilitating rural distribution network.

Project Rationale and Linkage to Country/Regional Strategy

Development Impact

Project Outcome

Description of Outcome
Progress Towards Outcome

Outputs and Implementation Progress

Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Status of Development Objectives
Material Changes

Business Opportunities

Date of First Listing 2006 Nov 21
Consulting Services
Consultants will be recruited in accordance with the ADB's Guidelines on the Use of Consultants.
Procurement
Good and services procured by ASEB and financed by ADB under the Project will be in accordance with ADB's Guidelines for Procurement
Procurement and Consulting Notices
http://www.adb.org/projects/36318-013/business-opportunities

Timetable

Concept Clearance
Fact-finding 10 Jun 2003 to 27 Jun 2003
Management Review Meeting 28 Jul 2003
Approval 10 Dec 2003
Last Review Mission

Milestones

Approval No. Approval Signing Effectivity Closing
Original Revised Actual
Loan 2037 10 Dec 2003 11 Dec 2003 12 Dec 2003 30 Jun 2007 30 Jun 2009 11 Jun 2009

Utilization

Date Approval Number ADB (US$ thousand) Others (US$ thousand) Net Percentage
Cumulative Contract Awards
20 Aug 2014 Loan 2037 100,000 0 100.00%
Cumulative Disbursements
20 Aug 2014 Loan 2037 100,000 0 100.00%

Status of Covenants

Covenants are categorized under the following categories—audited accounts, safeguards, social, sector, financial, economic, and others. Covenant compliance is rated by category by applying the following criteria: (i) Satisfactory—all covenants in the category are being complied with, with a maximum of one exception allowed, (ii) Partly Satisfactory—a maximum of two covenants in the category are not being complied with, (iii) Unsatisfactory—three or more covenants in the category are not being complied with. As per the 2011 Public Communications Policy, covenant compliance ratings for Project Financial Statements apply only to projects whose invitation for negotiation falls after 2 April 2012.

Approval No. Category
Sector Social Financial Economic Others Safeguards Project Financial Statements
Loan 2037

Contacts and Update Details

Responsible ADB Officer Tomoyuki Kimura ( @adb.org)
Responsible ADB Department South Asia Department
Responsible ADB Divisions Energy Division, SARD
Executing Agencies Assam State Electricity Board
Mr. U.C. Sarma

Links

Project Website http://www.adb.org/projects/36318-013/main
List of Project Documents http://www.adb.org/projects/36318-013/documents