Project Name Second Textbook Development
Project Number 36510-013
Country Uzbekistan
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 2093-UZB: Second Textbook Development
Ordinary capital resources US$ 25.00 million
Strategic Agendas
Drivers of Change
Sector / Subsector

For classification - For classification

Gender Equity and Mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Nation-wide
Safeguard Categories
Environment C
Involuntary Resettlement
Indigenous Peoples
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Lan Wu
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Uzbekistan Resident Mission
Executing Agencies
Ministry of Public EducationMr. B. Doniyorov5 Mustaqillik Sq., 100000, Tashkent
Timetable
Concept Clearance 04 Apr 2003
Fact Finding 10 May 2004 to 28 May 2004
MRM 18 Jun 2004
Approval 29 Sep 2004
Last Review Mission -
PDS Creation Date 25 Jan 2007
Last PDS Update 27 Jul 2010

LoanĀ 2093-UZB

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
29 Sep 2004 02 Nov 2004 01 Dec 2004 30 Jan 2010 - 09 Aug 2010
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 55.00 Cumulative Contract Awards
ADB 25.00 29 Sep 2004 18.36 0.00 100%
Counterpart 30.00 Cumulative Disbursements
Cofinancing 0.00 29 Sep 2004 18.36 0.00 100%