Project Data Sheet

Project Data Sheets (PDS) contain summary information on the project or program: Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

PDS Creation Date 31 Aug 2007
PDS Updated as of 18 Oct 2011

Project Name Regional Airports Rehabilitation Project
Country Afghanistan
Project/Program Number 37136-012
Status Closed
Geographical Location field changed
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Sector Transport and ICT
Subsector Air Transport
Strategic Agendas
Drivers of Change
Gender Equity and Mainstreaming Categories

Financing

Type/Modality of Assistance Approval Number Source of Funding Approved Amount (thousand)
Technical Assistance4210Technical Assistance Special Fund1,000
TOTAL US$ 1,000

Safeguard Categories

For more information about the safeguard categories, please see http://www.adb.org/site/safeguards/safeguard-categories

Environment B
Involuntary Resettlement B
Indigenous Peoples C

Summary of Environmental and Social Issues

field changed

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation and Consultation

field changed

During Project Design
During Project Implementation

Description

The prolonged state of conflict in Afghanistan has resulted in large-scale deterioration of the civil aviation infrastructure and depletion of the skilled manpower. In addition to lack of maintenance, the deterioration was further accelerated by the heavy damage inflicted during decades of civil strife and the recent military operations. A massive rebuilding effort is required to bring back the civil aviation infrastructure and institutions to a standard that assures safe and efficient civil aviation services in the country. The main objectives of the technical assistance are to (i) prepare a Civil Aviation Master Plan (CAMP) to provide the framework and time bound action plan for sustainable and effective development of the civil aviation sector in Afghanistan; (ii) undertake feasibility studies for rehabilitating selected major domestic airports and other regional airports and prepare an investment project suitable for ADB financing; and (iii) prepare an implementation program to strengthen the capacity of civil aviation sector institutions in Afghanistan.

Project Rationale and Linkage to Country/Regional Strategy

field changed

Development Impact

Project Outcome

Description of Outcome
Progress Towards Outcome

Outputs and Implementation Progress

Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Status of Development Objectives
Material Changes

Business Opportunities

Date of First Listing 2006 Dec 08
Consulting Services
The TA will require about 32 person-months of services of international consultants and about 20 person-months of domestic consultants. The international consultants should have experience in airport planning and engineering, air transport economics and poverty analysis, aviation management and financial analysis, social and environment assessment, and institutional capacity building and training. The domestic consultants will be engaged to carry out detailed surveys and consultations.
Procurement
Procurement and Consulting Notices
http://www.adb.org/projects/37136-012/business-opportunities

Timetable

Concept Clearance 25 Mar 2003
Fact-finding 03 Aug 2003 to 14 Aug 2003
Management Review Meeting
Approval 05 Nov 2003
Last Review Mission

Milestones

Approval No. Approval Signing Effectivity Closing
Original Revised Actual
Technical Assistance 4210 05 Nov 2003 24 Nov 2003 24 Nov 2003 31 Aug 2004 31 Dec 2005

Utilization

Date Approval Number ADB (US$ thousand) Others (US$ thousand) Net Percentage
Cumulative Contract Awards
Cumulative Disbursements

TA Amount (US$ thousand)

Approval Number Approved Amount Revised Amount Total Commitment Uncommitted Balance Total Disbursement Undisbursed Balance
Technical Assistance 4210 1,000 1,000 788 212 788 212

Contacts and Update Details

Responsible ADB Officer Prianka Seneviratne (pseneviratne@adb.org)
Responsible ADB Department Central and West Asia Department
Responsible ADB Divisions Transport and Communications Division, CWRD
Executing Agencies Ministry of Transport
Technical Deputy Director

Links

Project Website http://www.adb.org/projects/37136-012/main
List of Project Documents http://www.adb.org/projects/37136-012/documents