PDS Creation Date 14 Nov 2006
PDS Updated as of 24 Jul 2014

Project Name Regional Airports Rehabilitation Project Phase I
Country Afghanistan
Project/Program Number 37136-013
Status Approved
Geographical Location Faizabad, Badakshan Province,Chaghcharan, Ghor Province,Qalai-Naw, Badshis Province,Maimana, Faryab Province
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Sector Transport
Subsector Air transport
Strategic Agendas Inclusive economic growth (IEG)
Drivers of Change
Gender Equity and Mainstreaming Categories No gender elements

Financing

Type/Modality of Assistance Approval Number Source of Funding Approved Amount (thousand)
Loan2105Asian Development Fund30,000
Counterpart 100
TOTAL US$ 30,100

Safeguard Categories

For more information about the safeguard categories, please see http://www.adb.org/site/safeguards/safeguard-categories

Environment B
Involuntary Resettlement B
Indigenous Peoples C

Summary of Environmental and Social Issues

Environmental Aspects
All environmental impacts were temporary and mitigation measures were manageable which were managed accordingly. Mitigation measures during the construction stage incorporated into contractors' job assignments, therefore the IEE report was made available to contractors.
Involuntary Resettlement
Land Acquisition and Resettlement Plan (LARP) document was prepared and approved by the cabinet of Afghanistan that was properly implemented in close consultation with all involved stakeholders.
Indigenous Peoples
Social analysis revealed that no indigenous people live in the project area. None of the ethnic communities were observed to be marginalized because of a dominant community in the region or because of project development.

Stakeholder Communication, Participation and Consultation

During Project Design
During the project design, the Ministries involved are as follow: Ministry of Finance (MoF), Ministry of Transport & Civil Aviation (MoTCA). Most of the rehabilitation work will be carried out on land already owned by the Ministry of Civil Aviation and Tourism (MCAT), but will involve some minimal acquisition of residential structures, and a few households currently cultivating Government land will suffer temporary losses of income. The study included the 90 meters width required to establish a graded runaway strip for assessing the Project's social impacts. All the structures and land within this width were examined and a detailed socio-economic survey was conducted. The social assessment and public consultation has been carried out for all seven airports in phase I and a sample socioeconomic survey was conducted at three regional airports, namely, Bamyan, Faizabad, and Qalai-Naw.
During Project Implementation
During project preparation, five levels of consultations were undertaken using a public information consultation tool. The first level was in Kabul at the national capital level with various funding agencies, research agencies, relevant international and local nongovernment organizations, and relevant ministries and Government departments. The second level was at the provincial level with provincial heads, local administrations, municipalities, agriculture departments, legal departments, airport authorities, cadastral departments, and relevant international and local nongovernment organizations. The third level was with community leaders and local educated people primarily to solicit information about natural resources, community facilities, and likely impacts of the Project. The fourth level was with affected communities. The fifth level included consultation with people potentially affected by the Project, including women members of affected families on an individual level. Prior to these consultations, relevant information, such as a description of the Project and its objectives and an explanation of possible adverse effects of the proposed Project, were disseminated in a form and language meaningful to the groups consulted. Major perceived benefits as identified during the community consultations were (i) reduced travel time; (ii) better access to public amenities; (iii) significant economic opportunities resulting from increased access to markets; (iv) benefits to local businesses from increased air traffic; and (v) increased regional development in terms of industry, tourism, and development of crafts industries. The major perceived losses included (i) loss of residential and agricultural properties; (ii) safety risks posed by increased numbers of aircraft; (iv) children's loss of playing areas following the fencing of airports; and (v) increased noise pollution. The results from the community consultation were taken into account during project planning and were incorporated into the preparation of the resettlement plan as well as the preparation of mitigation measures.

Description

The objective of the Project is to assist the Government in the reconstruction and rehabilitation of the country by rehabilitating regional airports damaged during two decades of conflict and neglect. The Project is to (i) rehabilitate 4 regional airports at Chaghcharan, Ghor Province, Faizabad, Badakshan Province, Maimana, Faryab Province and Qalai-Naw, Badshis Province ; (ii) provide human resources development program to strengthen the capacity of the Ministry of Civil Aviation and Tourism; (iii) provide postconstruction operations assistance after completion of airport rehabilitation; (iv) provide administrative support to set up and operate the project steering committee and the project implementation unit; and (v) engage a project management consultant.

Project Rationale and Linkage to Country/Regional Strategy

Improvement of regional airports was considered one of the urgent needs by the comprehensive needs assessment of the transport sector conducted by ADB in 2002. The nature of the terrain of Afghanistan makes internal air transportation a basic necessity for access to extremely remote areas. The continuous conflict and strife for over two decades had almost completely destroyed the civil aviation infrastructure. Many of these airports are merely gravel tracks with hardly any landside facilities. The reconstruction/rehabilitation of the important regional airports has become an urgent priority of the Government.

Development Impact

Sustainable economic growth.

Project Outcome

Description of Outcome
Improve air transport services in the project area.
Progress Towards Outcome
--

Outputs and Implementation Progress

Description of Project Outputs
Reconstruction of runways, taxiways, and aprons of seven regional airports. New construction or widening of runway strips of seven regional airports. New construction or renovation of terminal building of seven regional airports and ancillary facilities Equipment for precision approach path indicators and automatic weather observation systems in seven regional airports Strengthened capacity in MCAT for civil aviation sector management
Status of Implementation Progress (Outputs, Activities, and Issues)
Project Completed. Runways, taxiways, aprons, and runways strips of 4 airports have been widened and rehabilitated. Other 3 airports were dropped due to cost overrun which other donors committed to undertake. Runways strips of 4 airports have been widened and rehabilitated. Other 3 airports were dropped due to cost overrun which other donors committed to undertake. Four airports teminal buildings are constructed in accordance wtih specification. Other 3 airports were dropped due to cost overrun which other donors committed to undertake. PAPI Installed in all four airports. Other 3 airports were dropped due to cost overrun which other donors committed to undertake. Completed. MoTCA staff trained in India on civil aviation management
Status of Development Objectives
Material Changes

Business Opportunities

Date of First Listing 2006 Nov 14
Consulting Services
Consulting services will be required to assist the Executing Agency in implementation of the Project. The consulting services will involve (i) overall project management as part of Project Implementation Unit; (ii) assistance in procurement of civil works; (iii) supervision of construction and installation of equipment; (iv) testing and certifying completed works; (v) implementation and supervision of the training component; (vi) designing of accounting systems for project implementation and airport operation; (vii) provision of assistance for institutional capacity building of the Ministry of Civil Aviation and Tourism (MCAT); (viii) provision of postconstruction operations assistance and provision of on-the-job training for airport operations and maintenance; and (xi) benefit monitoring and evaluation. The consultants will be selected and appointed by the quality- and cost-based selection method using full technical proposals in accordance with ADB's Guidelines on the Use of Consultants and arrangements satisfactory to ADB for engaging domestic consultants. The consulting services will require about 301 person-months of international consultants and about 152 person-months of domestic consultants. For designing of accounting system, individual consultants will be engaged separately for 24 person-months of international and 24 person-months of domestic.
Procurement
Procurement of goods, services, and civil works to be financed under the Project will be carried out in accordance with the ADB's Guidelines for Procurement. Due to the emergency nature of implementing the Project, the Government requested flexible application of such guidelines. This involves, among others, shorter bidding period for international procurement if required. The Government Procurement Unit of Afghanistan Reconstruction and Development Services (ARDS) will undertake all international procurements, including recruitment of project management consultants. All contracts for civil works and supply of equipment will be divided into suitable contract packages. The civil works contracts are packaged as design-build to ensure delivery within the project implementation period. The civil works contracts will be awarded following international competitive bidding procedures. The contracts for navigational aid equipment will be procured using international shopping procedures in view of the fact that (i) limited number of suppliers are available; (ii) purchase of equipment needs to be expedited in consideration of the emergency nature of the Project. All ICAO-certified manufacturers and suppliers of concerned navigational aid equipment will be invited in the course of international shopping. Some of the project airports are located in the western part of the country, where ADB non-member countries, particularly in the Gulf region, are competitive sources of materials, especially bitumen, required for runway pavement. In order to maximize the benefits of the proposed assistance to Afghanistan, the Mission will seek ADB Management's and Board's consideration for relaxation of eligibility criteria for procurement of bitumen from non-member countries in the Gulf region.
Procurement and Consulting Notices
http://www.adb.org/projects/37136-013/business-opportunities

Timetable

Concept Clearance
Fact-finding 02 Aug 2004 to 14 Aug 2004
Management Review Meeting 08 Sep 2004
Approval 23 Nov 2004
Last Review Mission

Milestones

Approval No. Approval Signing Effectivity Closing
Original Revised Actual
Loan 2105 23 Nov 2004 07 Apr 2005 08 Jul 2005 31 Dec 2014

Utilization

Date Approval Number ADB (US$ thousand) Others (US$ thousand) Net Percentage
Cumulative Contract Awards
22 Sep 2014 Loan 2105 26,663 0 85.00%
Cumulative Disbursements
22 Sep 2014 Loan 2105 26,897 0 85.00%

Status of Covenants

Covenants are categorized under the following categories—audited accounts, safeguards, social, sector, financial, economic, and others. Covenant compliance is rated by category by applying the following criteria: (i) Satisfactory—all covenants in the category are being complied with, with a maximum of one exception allowed, (ii) Partly Satisfactory—a maximum of two covenants in the category are not being complied with, (iii) Unsatisfactory—three or more covenants in the category are not being complied with. As per the 2011 Public Communications Policy, covenant compliance ratings for Project Financial Statements apply only to projects whose invitation for negotiation falls after 2 April 2012.

Approval No. Category
Sector Social Financial Economic Others Safeguards Project Financial Statements
Loan 2105 Satisfactory Satisfactory Satisfactory Satisfactory Satisfactory

Contacts and Update Details

Responsible ADB Officer Witoon Tawisook (wtawisook@adb.org)
Responsible ADB Department Central and West Asia Department
Responsible ADB Divisions Afghanistan Resident Mission
Executing Agencies Ministry of Transport_and Civil Aviation