Project Data Sheet

Project Data Sheets (PDS) contain summary information on the project or program: Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

PDS Creation Date
PDS Updated as of 22 Jul 2014

Project Name Greater Mekong Subregion: Rehabilitation of the Railway in Cambodia Project
Country Cambodia
Project/Program Number 37269-023
Status Approved
Geographical Location
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Sector Transport
Subsector Rail transport (non-urban)
Strategic Agendas Inclusive economic growth (IEG)
Regional integration (RCI)
Drivers of Change Gender equity and mainstreaming (GEM)
Partnerships (PAR)
Gender Equity and Mainstreaming Categories Category 3: Some gender elements (SGE)

Financing

Type/Modality of Assistance Approval Number Source of Funding Approved Amount (thousand)
Loan2602Asian Development Fund42,000
Grant0187Australian Grant960
Grant0187Australian Grant21,500
Counterpart 5,100
TOTAL US$ 69,560

Safeguard Categories

For more information about the safeguard categories, please see http://www.adb.org/site/safeguards/safeguard-categories

Environment B
Involuntary Resettlement A
Indigenous Peoples C

Summary of Environmental and Social Issues

Environmental Aspects
The railway alignment is outside environmentally sensitive areas such as national parks and other protected areas and their buffer zones and the proposed Project falls into environmental category B. The additional works to be implemented under the modified project do not introduce new or significantly different environmental impacts, since they are largely contained within or close to the areas already assessed under the original project s IEE. The implementation of the Project is not expected to cause significant environmental impacts. The site for Samrong Station consists of paddy fields and grassland with sparsely populated areas in nearby sites. Other components will consist of rehabilitation of existing siding and construction of relatively short spans of siding/spur lines from the existing main line. Appropriate mitigation measures during pre-construction, construction, and operation phases have been identified, implementation of which will minimize the negative impacts of the Project to acceptable levels.
Involuntary Resettlement
The original project was formulated to minimize potential risks related to involuntary resettlement. The scope of the modified project, which included the construction of a new freight facility at Samrong, is now being amended to remove the Samrong freight facilities, and instead include priority works for the Southern Line to improve operating speed and safety. These works are not expected to have resettlement impacts. The draft resettlement plan are updated, agreed, and implemented prior to civil works. An expanded income restoration program is being implemented which provides credit for business expansion through a community development fund and gives grants for emergencies through a social safety nets fund. The funds are provided to self-help groups in relocation sites.
Indigenous Peoples
The socioeconomic survey indicated that the original project is not expected to affect ethnic minority groups any differently than the majority Khmers. ADB s Policy on Indigenous Peoples (1998) is not triggered.

Stakeholder Communication, Participation and Consultation

During Project Design
With respect to involuntary resettlement, the government has held public consultation meetings; distributed public information booklets in the Khmer language to all affected households; and placed copies of the resettlement plan, translated into Khmer language, in the affected commune offices.
During Project Implementation
During the updating and implementation of the resettlement plan, consultations and information dissemination will continue with affected persons consistent with the project s participatory approach. The affected households will be made fully aware of their rights through verbal and written means during resettlement planning, updating, and implementation. In addition, the HIV/AIDS prevention program includes community participation during design and implementation.

Description

Project Rationale and Linkage to Country/Regional Strategy

Development Impact

Increase in domestic and regional trade movement on the railway

Project Outcome

Description of Outcome
The railway is sustainable and efficiently operated.
Progress Towards Outcome
The Southern line from Phnom Penh to Sihanoukville is completed. The section between Phnom Penh and Touk Meas was re-opened in October 2010, and the section between Touk Meas and Sihanoukville was re-opened in December 2012. About 20 trains circulate each week on the line carrying fuel, cement and bagged rice in containers. Northern line - of the 48 km of missing link between Sisophon to Poipet (Thai border), about 42 km is completed; and 23 km bifurcation to Bat Deong was completed. The contractor stopped the work in June 2012 and negotiations to resume the works failed. The Government has prepared Plan B to complete priority works with the available funds. The procurement of some of the priority works under Plan B is ongoing.

Outputs and Implementation Progress

Description of Project Outputs
Railway link to Thailand reconstructed Rail links to Sihanoukville port and the port in Phnom Penh rehabilitated and extended Freight facilities in Samrong and Phnom Penh constructed Railway department staffed and operational Affected households living within the railway ROW and stations satisfactorily compensated and assisted
Status of Implementation Progress (Outputs, Activities, and Issues)
Todate about 42 km was reconstructed. Construction ongoing and is expected to be completed third quarter of 2014. The Government has dropped this component due to shortage of funds. As a short-term alternative to the intermodal terminal planned for Samrong, the Concessionaire has constructed a hard stand facility at the CWT Dry Port in Phnom Penh, which is now being used for loading and unloading of train cargo. Access to CWT Dry port will be constructed. Completed. The Government requested removal of the Samrong Intermodal Terminal.
Status of Development Objectives
Material Changes

Business Opportunities

Date of First Listing 2012 Jan 09
Consulting Services
The consultants are selected by the Government in accordance with ADB's Guidelines on the Use of Consulting Services, using the quality and cost based selection procedure.
Procurement
The works are procured under the international competitive bidding procedures of ADB's Guidelines on Procurement.
Procurement and Consulting Notices
http://www.adb.org/projects/37269-023/business-opportunities

Timetable

Concept Clearance 13 May 2009
Fact-finding 29 Jul 2009 to 07 Aug 2009
Management Review Meeting 10 Sep 2009
Approval 12 Jan 2012
Last Review Mission

Milestones

Approval No. Approval Signing Effectivity Closing
Original Revised Actual
Grant 0187 15 Dec 2009 05 Oct 2010 05 Jan 2011 30 Sep 2013 31 Mar 2015

Utilization

Date Approval Number ADB (US$ thousand) Others (US$ thousand) Net Percentage
Cumulative Contract Awards
19 Aug 2014 Grant 0187 21,587 0 96.00%
Cumulative Disbursements
19 Aug 2014 Grant 0187 21,254 0 95.00%

Status of Covenants

Covenants are categorized under the following categories—audited accounts, safeguards, social, sector, financial, economic, and others. Covenant compliance is rated by category by applying the following criteria: (i) Satisfactory—all covenants in the category are being complied with, with a maximum of one exception allowed, (ii) Partly Satisfactory—a maximum of two covenants in the category are not being complied with, (iii) Unsatisfactory—three or more covenants in the category are not being complied with. As per the 2011 Public Communications Policy, covenant compliance ratings for Project Financial Statements apply only to projects whose invitation for negotiation falls after 2 April 2012.

Approval No. Category
Sector Social Financial Economic Others Safeguards Project Financial Statements
Loan 2602 Satisfactory Satisfactory Satisfactory Satisfactory Satisfactory
Grant 0187 Satisfactory Satisfactory Satisfactory Satisfactory Satisfactory

Contacts and Update Details

Responsible ADB Officer Peter Broch (pbroch@adb.org)
Responsible ADB Department Southeast Asia Department
Responsible ADB Divisions Transport and Communications Division, SERD
Executing Agencies Ministry of Public Works and Transport
*

Links

Project Website http://www.adb.org/projects/37269-023/main
List of Project Documents http://www.adb.org/projects/37269-023/documents