Project Data Sheet

Project Data Sheets (PDS) contain summary information on the project or program: Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

PDS Creation Date 10 Jul 2006
PDS Updated as of 23 Jun 2014

Project Name IND: DAHEJ LNG TERMINAL EXPANSION PROJECT
Borrower/Equity Investment Name PETRONET LNG LTD
Country India
Project/Program Number 39921-014
Status Approved
Geographical Location Dahej, Gujarat, India.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Sector Energy
Subsector Conventional energy generation
Strategic Agendas
Drivers of Change
Gender Mainstreaming Categories

Project Sponsor

PETRONET LNG LTD

Financing

Type/Modality of Assistance Approval Number Source of Funding Approved Amount (thousand)
PS7245Local Currency Loan
(Fully Disbursed)
6,750,000
TOTAL INR 6,750,000

Summary of Environmental and Social Issues

During operation, the only cumulative environmental impacts of the Project will be increased gaseous emissions from the additional gas turbine generators and vaporizers. Nitrogen oxides, the major air pollutant, will be controlled through the use of lean-burn technology in the gas turbine generators and the high stacks for rapid dispersion of emission. The major risks for LNG terminal operations are pool-fire and vapor dispersion in case of LNG spills or leakage from the storage tanks, pipelines, and process equipments. PLL will comply with the well-established industry standards for design, construction, and operations of LNG terminal facilities, as well as emergency response and disaster management plan and procedures, which have been adopted since the first phase of the terminal.

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation and Consultation

Public consultation was carried out before the implementation of the first phase terminal also covering the proposed expansion to 10 MMTPA. Announcements were made in the local newspapers and on the website of the Ministry of Environment and Forests for pubilc comments. No objections were raised in these processes.

Description

IND: DAHEJ LNG TERMINAL EXPANSION PROJECT1

Objectives and Scope

Project Rationale and Linkage to Country/Regional Strategy

The Project is in line with ADB's India country strategy and energy sector strategy, which promote creating clean energy infrastructure for sustainable economic growth involving private sector.

Outputs and Implementation Progress

Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Status of Development Objectives
Since the first phase commercial operations started in April 2004, Petronet has already fulfilled all the main development objectives envisaged, i.e. provide additional, lower-cost, and environmentally sustainable alternate input to major industries, diversify the energy base, promote the use of clean energy, and form a good practice in PPP.
Material Changes
In May 2007, the structure of the ADB loan was revised from limited recourse financing for the Dahej expansion project to a corporate loan. This was due to the rapid expansion of PLL operations after ADB approval in August 2006, which included construction of the new LNG terminal at Kochi. This terminal was completed in December 2012.

Business Opportunities

Date of First Listing
Consulting Services
Procurement
Procurement and Consulting Notices
http://www.adb.org/projects/39921-014/business-opportunities

Timetable

Concept Clearance 16 Aug 2005
Fact-finding
Management Review Meeting 04 Jul 2006
Approval 30 Aug 2006
Last Review Mission 13 Mar 2006 to 23 Mar 2006

Milestones

Approval No. Approval Signing Effectivity Closing
Original Revised Actual
Private Sector 7245 30 Aug 2006 27 Jul 2007 09 Jul 2008 31 Dec 2010

Contacts and Update Details

Responsible ADB Officer Not Assigned
Responsible ADB Department Private Sector Operations Department
Responsible ADB Divisions Infrastructure Finance Division 1
Executing Agencies

Links

Project Website http://www.adb.org/projects/39921-014/main
List of Project Documents http://www.adb.org/projects/39921-014/documents