Project Data Sheet

Project Data Sheets (PDS) contain summary information on the project or program: Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

PDS Creation Date 13 Feb 2006
PDS Updated as of 14 Dec 2012

Project Name NAM NGUM 3 HYDROPOWER PROJECT
Borrower/Equity Investment Name NAM NGUM 3 POWER COMPANY
Country Lao People's Democratic Republic
Project/Program Number 40906-014
Status Terminated / Cancelled
Geographical Location The project is located on the Nam Ngum River, about 10 kms southwest of Ban Longcheng in Xiasomboun District of Vientianne, Lao PDR. It is approximately 260 kms by road from Vientianne.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Sector Not yet classified
Subsector For Classification
Strategic Agendas
Drivers of Change
Gender Equity and Mainstreaming Categories

Project Sponsors

GMS Lao Company Limited
Lao Holdings State Enterprise
Marubeni Corporation
Ratchaburi Electricity Generating Holding PLC

Financing

Type/Modality of Assistance Approval Number Source of Funding Approved Amount (thousand)
Private Sector Loan and Equity7341Others
(Documents under Negotiations)
150,000
Private Sector Loan and Equity7341Private Sector Loan
(Documents under Negotiations)
200,000
TOTAL USD 350,000

Summary of Environmental and Social Issues

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation and Consultation

Description

The NN3 plan will promote economic growth in Lao PDR by generating upwards of $770 million in export earnings for Lao PDR, of which more than $200 million is expected to go to poverty reduction and environmental protection programs. It will also provide critical energy to support sustainable economic growth and improve energy security in Thailand by diversifying the country s energy sources.1

Objectives and Scope

The NN3 plan will promote economic growth in Lao PDR by generating upwards of $770 million in export earnings for Lao PDR, of which more than $200 million is expected to go to poverty reduction and environmental protection programs. It will also provide critical energy to support sustainable economic growth and improve energy security in Thailand by diversifying the country s energy sources.

Project Rationale and Linkage to Country/Regional Strategy

ADB's participation in NN3 is consistent with its Country Strategy Program for Lao PDR (2007-2011), which calls for interventions designed to advance economic growth and poverty alleviation. The Country Strategy Program call for ADB to pursue public-private partnerships in large-scale infrastructure projects and projects promoting regional cooperation, among other activities.

Outputs and Implementation Progress

Description of Project Outputs
Construction of Nam Ngum 3 Hydropower Project in Lao PDR as a public-private partnership in an environmentally sustainable and socially inclusive manner
Status of Implementation Progress (Outputs, Activities, and Issues)
Status of Development Objectives
Material Changes

Business Opportunities

Date of First Listing
Consulting Services
Procurement and Consulting Notices
http://www.adb.org/projects/40906-014/business-opportunities

Timetable

Concept Clearance 17 Jan 2006
Due Diligence Mission
Investment Committee Meeting 14 Mar 2011
Approval 03 Nov 2011

Contacts and Update Details

Responsible ADB Officer Christine Genalin C. Uy (cguy@adb.org)
Responsible ADB Department Private Sector Operations Department
Responsible ADB Divisions Infrastructure Finance Division 2