Project Name Water Supply and Sanitation Sector Project
Project Number 45301-002
Country Lao People's Democratic Republic
Project Status Approved
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Grant 0363-LAO: Water Supply and Sanitation Sector Project
ADB Co-financed Assistance Fund US$ 6.00 million
Loan 3041-LAO: Water Supply and Sanitation Sector Project
Asian Development Fund US$ 35.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Governance and capacity development
Partnerships
Sector / Subsector

Water and other urban infrastructure and services - Urban policy, institutional and capacity development - Urban sanitation - Urban water supply

Gender Equity and Mainstreaming Effective gender mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact Expanded access to quality and reliable piped water supply and sanitation services for the urban population in Lao PDR.
Project Outcome
Description of Outcome Improved performance of participating provincial nam papas (provincial water utilities) in delivering sustainable water supply and sanitation services.
Progress Toward Outcome Ongoing.
Implementation Progress
Description of Project Outputs

1. Improved sector coordination and policy implementation.

2. Improved nonrevenue water management and water supply development.

3. Developed new water supply systems in small towns.

4. Enhanced community action in urban water supply and sanitation.

5. Strengthened capacity for project implementation and O&M.

Status of Implementation Progress (Outputs, Activities, and Issues) The project implementation consultants have been recruited and were mobilized in July 2015.
Geographical Location
Safeguard Categories
Environment B
Involuntary Resettlement B
Indigenous Peoples B
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Anupma Jain
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Urban Development and Water Division, SERD
Executing Agencies
Ministry of Public Works and Transport
Dept of Housing and Urban Planning, Lao
PDR, Lane-Xang Ave., Vientiane Lao PDR
P.O. Box 206
Timetable
Concept Clearance 05 Sep 2012
Fact Finding 03 Jul 2013 to 12 Jul 2013
MRM 01 Aug 2013
Approval 09 Oct 2013
Last Review Mission -
Last PDS Update 28 Oct 2015

GrantĀ 0363-LAO

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
09 Oct 2013 11 Oct 2013 07 Nov 2013 31 Mar 2022 - -
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 6.00 Cumulative Contract Awards
ADB 0.00 09 Oct 2013 0.00 0.25 4%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 6.00 09 Oct 2013 0.00 0.00 0%

LoanĀ 3041-LAO

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
09 Oct 2013 11 Oct 2013 07 Nov 2013 31 Mar 2022 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 40.60 Cumulative Contract Awards
ADB 35.00 09 Oct 2013 7.04 0.00 22%
Counterpart 5.60 Cumulative Disbursements
Cofinancing 0.00 09 Oct 2013 1.26 0.00 4%

 
This page was generated from http://www.adb.org/projects/45301-002/main on 08 February 2016