Project Data Sheet

Project Data Sheets (PDS) contain summary information on the project or program: Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

PDS Creation Date
PDS Updated as of 09 Oct 2014

Project Name Public Expenditure Performance Monitoring in Henan
Country China, People's Republic of
Project/Program Number 47080-001
Status Approved
Geographical Location
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Sector Public sector management
Subsector Public expenditure and fiscal management
Strategic Agendas Inclusive economic growth (IEG)
Drivers of Change Governance and capacity development (GCD)
Gender Equity and Mainstreaming Categories

Financing

Type/Modality of Assistance Approval Number Source of Funding Approved Amount (thousand)
Technical Assistance8490Technical Assistance Special Fund450
Counterpart 113
TOTAL US$ 563

Summary of Environmental and Social Issues

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation and Consultation

During Project Design
The TA mission will closely consult relevant stakeholders during project design, including EA/IA, other government agencies, think tanks, and beneficiaries.
During Project Implementation
The TA mission will closely consult relevant stakeholders during project implementation, including EA/IA, other government agencies, consulting team, think tanks, and beneficiaries.

Description

Project Rationale and Linkage to Country/Regional Strategy

Henan Province is located in the central region of the People's Republic of China (PRC). It is one of the country's most populous provinces, with over 94 million inhabitants, about 7% of the country's population. Henan's gross domestic product (GDP) in 2012 was CNY3 trillion accounting for 5.7% of the country's GDP, and its per capita GDP is 82.5% of the national average, which is low compared to central provinces. Fiscal expenditure in Henan has increased at a significantly faster pace than fiscal revenue over the past 10 years. Most of the outlays have been directed toward health and education, general public service, social security, agriculture, forestry and water resources, and transfer payment from the Henan Provincial Government to prefecture and county level governments. It is noteworthy that around 80% of the transfer payment is for special purpose projects. Due to the lack of adequate performance monitoring and evaluation mechanism, it is difficult to assess the efficiency and effectiveness of fiscal expenditure, including for special purpose projects. This is also a similar pattern in other provinces in the PRC. Improving the public finance system (including public financial management, intergovernmental fiscal transfers, and supervision and monitoring of public expenditure), and ensuring good governance at all levels of government and across all sectors are critical to support the PRC's long-term goal of building a harmonious and prosperous society by improving people s livelihood, and promoting balanced and environmentally sustainable growth. The central government stressed the need to improve the public finance system and the financial management of public finance. For example, in the 2008 Government Work Report, Premier Wen Jiabao proposed an administrative system of accountability and a budget performance management system. In 2010, President Hu Jintao, at the 18th collective study of the Political Bureau of the Communist Party of China (CPC) Central Committee, stressed that the country needed to improve the public finance system and the performance of financial management. In 2012, the new leadership also emphasized the importance of undertaking fiscal and taxation reform, and strengthening public finance system at the 18th National Congress of CPC. In recent years, the PRC has actively explored various forms of public financial management (including performance-based budgeting and performance monitoring) but they are still at the initial and exploratory stage. For example, regulations and systems of performance management and monitoring are inadequate, budget units lack the understanding and knowledge of performance management and monitoring, and the results of performance monitoring deviate markedly from the original targets. These issues have seriously hampered the efficient and effective use of fiscal funds. In this respect, it is important to further strengthen research, deepen the understanding of and awareness about performance monitoring, and propose appropriate policy recommendations to improve the overall public financial management. Henan is one of the provinces that are exploring measures to strengthen public financial management, which is a key area to ensure the proper functioning of the provinces. Sound public financial management improves accountability and efficiency in the management of public resources and delivery of public services to meet public expectations. Revenue reform is an important aspect of sound public financial management. However, as most tax bases and rates are set by the central government, it would be best pursued as part of a wider national agenda of fiscal reform. TA 8379-PRC: Public Finance Development Strategy 2020, approved in June 2013, is designed to help the PRC government to address the key national issues on fiscal and taxation reform. Effective public expenditure management is an essential part of sound public financial management. In this context, the Henan government specifically requests ADB to focus on one aspect of this agenda. It seeks ADB's technical assistance to help strengthen its public expenditure performance monitoring system to improve the efficiency and effectiveness of public spending to maximize value for money, increase the transparency of the transfer payment for special purpose projects, increase the government's administrative efficiency, and enhance the awareness of due diligence and responsibility of government departments at sub-provincial level. Such public expenditure performance monitoring framework could be applied in other provinces in the PRC, thus, contributing to achieving national objectives. Moreover, this TA project would help enhance the governance of public expenditure. The TA is consistent with the inclusive growth agenda, one of the three pillars of the strategic framework in the PRC's CPS. Improving public expenditure performance monitoring will ensure that public expenditure is targeted, the outputs are monitored and the outcomes are assessed against the objectives in order to maximize the development impact. The TA will also support good governance and capacity development, one of the drivers of change of the strategic framework in the PRC's CPS. Moreover, the TA will contribute to the government's efforts to strengthen the policy and regulatory frameworks and practices to improve municipal services and expand capacity development.

Development Impact

Strengthened public financial management in Henan through improved efficiency and effectiveness of public expenditure.

Project Outcome

Description of Outcome
Improve the efficiency and effectiveness of public expenditure through improved public expenditure performance monitoring in Henan.
Progress Towards Outcome
Project outcome will be evaluated once the project is completed.

Outputs and Implementation Progress

Description of Project Outputs
The outputs will contain 3 reports: 1. Research report; 2. Recommendations report; and 3. Final report. These outputs will establish a framework for public expenditure performance monitoring in Henan.
Status of Implementation Progress (Outputs, Activities, and Issues)
All consultants were recruited by the end of April and the inception workshop was conducted on 5 May 2014. Field surveys were completed in July and the survey report was submitted by the end of September 2014. The midterm report workshop was scheduled in late November 2014.
Status of Development Objectives
Material Changes

Business Opportunities

Date of First Listing 2013 Aug 30
Consulting Services
A total of 21 person-months of individual consulting services (one international consultant for 5 person-months and 2 national consultants for a total of 16 person-months) will be provided. The consultants will be engaged in line with ADB's Guidelines on the Use of Consultants (2010 as amended from time to time).
Procurement
Procurement and Consulting Notices
http://www.adb.org/projects/47080-001/business-opportunities

Timetable

Concept Clearance 24 Jul 2013
Fact-finding 19 Aug 2013 to 21 Aug 2013
Management Review Meeting
Approval 17 Oct 2013
Last Review Mission

Milestones

Approval No. Approval Signing Effectivity Closing
Original Revised Actual
Technical Assistance 8490 17 Oct 2013 19 Nov 2013 19 Nov 2013 30 Jun 2015

Utilization

Date Approval Number ADB (US$ thousand) Others (US$ thousand) Net Percentage
Cumulative Contract Awards
Cumulative Disbursements

TA Amount (US$ thousand)

Approval Number Approved Amount Revised Amount Total Commitment Uncommitted Balance Total Disbursement Undisbursed Balance
Technical Assistance 8490 450 450 228 222 32 418

Contacts and Update Details

Responsible ADB Officer Jian Zhuang (jianzhuang@adb.org)
Responsible ADB Department East Asia Department
Responsible ADB Divisions PRC Resident Mission
Executing Agencies

Links

Project Website http://www.adb.org/projects/47080-001/main
List of Project Documents http://www.adb.org/projects/47080-001/documents