China, People's Republic of : Chongqing-Guizhou Roads Development: Chongqing Component (Leichong Expressway)
Project Details
-
Project Officer
Ojiro, Makoto
East Asia Department
Request for information -
Country/Economy
China, People's Republic of -
Sector
- Transport
Related Projects
Project Name | Chongqing-Guizhou Roads Development: Chongqing Component (Leichong Expressway) | ||||||||
Project Number | 29070-013 | ||||||||
Country / Economy | China, People's Republic of |
||||||||
Project Status | Closed | ||||||||
Project Type / Modality of Assistance | Loan |
||||||||
Source of Funding / Amount |
|
||||||||
Strategic Agendas | Inclusive economic growth |
||||||||
Drivers of Change | Governance and capacity development Knowledge solutions Private sector development |
||||||||
Sector / Subsector | Transport / Road transport (non-urban) |
||||||||
Gender | |||||||||
Description | |||||||||
Project Rationale and Linkage to Country/Regional Strategy | |||||||||
Impact |
Project Outcome | |
---|---|
Description of Outcome | |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location |
Safeguard Categories | |
---|---|
Environment | A |
Involuntary Resettlement | |
Indigenous Peoples |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Responsible ADB Officer | Ojiro, Makoto |
Responsible ADB Department | East Asia Department |
Responsible ADB Division | PRC Resident Mission (PRCM) |
Executing Agencies |
Chongqing Expressway Development Compnay Limited |
Timetable | |
---|---|
Concept Clearance | 31 Jan 1997 |
Fact Finding | 07 Sep 1999 to 23 Sep 1999 |
MRM | 31 Mar 2000 |
Approval | 21 Nov 2000 |
Last Review Mission | - |
PDS Creation Date | 24 Nov 2006 |
Last PDS Update | 08 Dec 2010 |
Loan 1783-PRC
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
21 Nov 2000 | 29 Aug 2001 | 27 Nov 2001 | 30 Sep 2005 | 31 Mar 2007 | 29 Jan 2008 |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 179.00 | Cumulative Contract Awards | |||
ADB | 120.00 | 17 Feb 2023 | 119.74 | 0.00 | 100% |
Counterpart | 59.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 17 Feb 2023 | 119.74 | 0.00 | 100% |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Chongqing-Guizhou Roads Development Project (Leichong Expressway) | Project/Program Completion Reports | Oct 2008 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Title | Document Type | Document Date |
---|---|---|
Chongqing-Guizhou Roads Development Project | Environmental Assessment and Measures | Mar 2000 |
Chongqing-Guizhou Roads Development: Chongqing Component (Leichong Expressway): Summary Minority Peoples' Development Plan | Indigenous Peoples Planning Frameworks/Indigenous Peoples Development Frameworks | Oct 2004 |
Evaluation Documents See also: Independent Evaluation
Title | Document Type | Document Date |
---|---|---|
People's Republic of China: Chongqing–Guizhou Roads Development Project (Leichong Expressway) | Validations of Project Completion Reports | Dec 2009 |
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Procurement Plan
None currently available.