India: Housing Finance II (HUDCO)

Sovereign Project | 30204-013 Status:

Summary

Latest Project Documents

Title Date
Housing Finance II Project Aug 2000

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents

None currently available.


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Housing Finance II (HUDCO)
Project Number 30204-013
Country India
Project Status
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 1758-IND: Housing Finance II (HUDCO)
Ordinary capital resources US$ 100.00 million
Loan 1759-IND: Housing Finance II (NHB)
Ordinary capital resources US$ 40.00 million
Loan 1760-IND: Housing Finance II (HDFC)
Ordinary capital resources US$ 80.00 million
Loan 1761-IND: Housing Finance II (ICICI)
Ordinary capital resources US$ 80.00 million
Strategic Agendas Inclusive economic growth
Drivers of Change Governance and capacity development
Knowledge solutions
Private sector development
Sector / Subsector

Finance - Housing finance

Gender Equity and Mainstreaming No gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Nationwide

Safeguard Categories

Environment B
Involuntary Resettlement
Indigenous Peoples

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation

Responsible Staff

Responsible ADB Officer Tetsu Ito
Responsible ADB Department South Asia Department
Responsible ADB Division India Resident Mission
Executing Agencies
Housing & Urban Dev't Corp Ltd
Mr. V. Swarup, Chief, Communities Development
habitat@mantraonline.com
HUDCO Bhawan India Habitat Centre, Lodhi Road New Delhi 11003, India

Timetable

Concept Clearance 26 Apr 2000
Fact Finding 18 Apr 2000 to 02 May 2000
MRM 15 May 2000
Approval -
Last Review Mission -
Last PDS Update 07 Feb 2007

Loan 1758-IND

Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 169.70 Cumulative Contract Awards
ADB 100.00 - 0.00 0.00 %
Counterpart 69.70 Cumulative Disbursements
Cofinancing 0.00 - 0.00 0.00 %

Loan 1759-IND

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
21 Sep 2000 18 Dec 2001 15 Feb 2002 30 Jun 2007 - 30 Jun 2007
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 69.46 Cumulative Contract Awards
ADB 40.00 21 Sep 2000 7.40 0.00 100%
Counterpart 29.46 Cumulative Disbursements
Cofinancing 0.00 21 Sep 2000 7.40 0.00 100%

Loan 1760-IND

Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 138.90 Cumulative Contract Awards
ADB 80.00 - 0.00 0.00 %
Counterpart 58.90 Cumulative Disbursements
Cofinancing 0.00 - 0.00 0.00 %

Loan 1761-IND

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
21 Sep 2000 18 Dec 2001 20 Dec 2002 30 Jun 2007 - 10 Oct 2007
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 138.90 Cumulative Contract Awards
ADB 80.00 21 Sep 2000 80.00 0.00 100%
Counterpart 58.90 Cumulative Disbursements
Cofinancing 0.00 21 Sep 2000 80.00 0.00 100%
Title Document Type Document Date
Housing Finance II Project Reports and Recommendations of the President Aug 2000

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.