Bangladesh: Small Scale Water Resources Development Sector II

Sovereign Project | 30209-013

Latest Project Documents

Project Results

 

190,000

hectares of land improved through irrigation, drainage and/or flood management

 

193,200

households with reduced flood risk

 

28,180

microfinance loan accounts opened / end borrowers reached


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Small Scale Water Resources Development Sector II
Project Number 30209-013
Country Bangladesh
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 1831-BAN: Small Scale Water Resources Development Sector II
Asian Development Fund US$ 34.00 million
Strategic Agendas Inclusive economic growth
Drivers of Change
Sector / Subsector Agriculture, natural resources and rural development - Water-based natural resources management
Gender Equity and Mainstreaming
Description

The overall goal of the Project is to support the Government's poverty reduction effort by increasing sustainable agricultural and fishery production. The project objective is to develop sustainable stakeholder-driven, small-scale water resource management systems with special attention to the poorer section of the population. The objectives will be achieved by (i) developing improved means of beneficiary participation in the selection, design, implementation, and operation and maintenance of smallscale water resource management development systems; (ii) rehabilitating and constructing small-scale water resource management infrastructure with appropriate agricultural extension, fisheries extension, and aquaculture development; (iii) developing effective management of environmental and social impacts of subprojects, including on those engaged in practicing floodplain capture fisheries; and (iv) developing institutional strengthening and capacity building of relevant Government and stakeholder organizations to ensure adequate support for smallscale

water resources development at all levels.

Project Rationale and Linkage to Country/Regional Strategy

Sustainable water resource management is a critical element of the Government's poverty reduction strategy, as 90 per cent of the poor living in rural areas and water resources being the foundation of many traidiotnal rural activities engaged by the poor. Based on the Government's main instrument to have the strategy implemented, the SSWRDSP was launched in 1996 to enhance rural incomes by developing community-based water management associations (WMAs) and communitymanaged, small-scale infrastructure; this has proved to be an effective means to reduce rural poverty. Participatory water resources development and management is necessary to effectively implement key principles by strengthening the implementation framework; this was demonstrated under the SSWRDSP. Expansion of small-scale water resources development is one of the key elements in effectively reducing rural poverty.

Consistent with the National Water Policy of Bangladesh and with the water policy of ADB

Impact To support the Government's poverty reduction effort by increasing sustainable agricultural and fishery production.
Project Outcome
Description of Outcome Increase agricultural production in subproject areas through sustainable stakeholder-driven, small sacle water resource management systems [Taken from the Project Framework]
Progress Toward Outcome Overall implementation progress is 99%
Implementation Progress
Description of Project Outputs

Participatory Water Resources Development: Mobilization of Beneficiary Participation

Community-Based Infrastructure Development

Water Resources-Oriented Support Programs

Institutional Strengthening in the Small-Scale Water Resource Sector

Status of Implementation Progress (Outputs, Activities, and Issues)

Implementable subprojects target stood at 300.

100% contribution of O&M fund received for 300 subprojects.

WRS completed in 300 subprojects

Various water resources oriented support programs were undertaken in the completed subprojects

IEE/EIA included in feasibility reports.

BME systems established

Regular progress meetings held at management level

LGED training counterpart has been placed

Geographical Location Nationwide except for 3 hill districts
Safeguard Categories
Environment B
Involuntary Resettlement
Indigenous Peoples
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement The Project processed land acquisition for 48 subprojects for a total area of 43.42 ha, but funds were released for 15 subprojects only. Affected land owners in 10 subprojects voluntarily donated their lands at free of cost for the infrastructure sites even after obtaining administrative approval from the Ministry. EA agreed to make land payments to the affected land owners in future projects as these are scarce resources particularly for the vulnerable community who has small parcel of land.
Indigenous Peoples An indigenous peoples' development plan has been prepared for Boraghat subproject in Mymensingh.
Stakeholder Communication, Participation, and Consultation
During Project Design Beneficiaries participated in subproject selection, planning, implementation, and O&M. NGO facilitators were selected taking performance in the first phase of the Project into consideration. The facilitators were trained and fielded in April 2003. Total 2,948 subproject proposals were received from intended beneficiaries.
During Project Implementation

100 percent of beneficiaries fully contributed required annual O&M amounts in each subproject

A total of about 3.7 million person-days of local labors were engaged to complete about 9.7 million cubic meters of earthworks for the Project. This activity created employment opportunity for a total of 40,483 LCS members (35,077 male and 5,406 female) over the duration of the Project.

An empowerment process was ongoing and women were found to be elected as WMCA chair and treasurer. Women were also representing in the sub-committees and in some WMCAs they were heading the micro-finance (MF) Sub-committee, Fisheries Sub-Committee etc.

Business Opportunities
Consulting Services

Consulting services will assist project implementation with capacity building and institutional strengthening. Aa total of 962 person-months of consulting services are required, including 824 person-months of domestic and 138 person-months of international consultant inputs. The total cost of the consulting services will be financed by the Government of the Netherlands and the services will be administered by ADB.

ADB Management has approved advance procurement of urgently needed consultant services, materials, equipment and vehicles. Shortlisting is scheduled in July 2001.

Procurement Supplies to be procured under the Project will consist generally of service vehicles, construction equipment, computers and survey and laboratory equipment. All supplies, equipment and services will be purchased in accordance with ADB's Guidelines on Procurement. Civil works contracts for structures will be awarded under local competitive bidding procedures. Earthworks contracts valued at less than $5,000 will be carried out by LGED's force account utlizing Labor Contracting Societies. Supplies contracts not exceeding $500,000, will be awarded in accordance with the international shopping procedures. Other miscellaneous equipment and supplies, with each package value below the equivalent of $100,000, will be procured by direct purchase procedures.
Responsible ADB Officer Zahir Uddin Ahmad
Responsible ADB Department South Asia Department
Responsible ADB Division Bangladesh Resident Mission
Executing Agencies
Local Government Engineering DepartmentMr. Moshiur Rahmanmoshiur57@yahoo.comRDEC Bhaban (Level-5)
Timetable
Concept Clearance 15 May 2002
Fact Finding 17 May 2002 to 19 May 2002
MRM 18 Nov 2002
Approval 12 Jul 2001
Last Review Mission -
PDS Creation Date 04 Feb 2007
Last PDS Update 19 Jan 2012

Loan

Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 19.40 Cumulative Contract Awards
ADB 0.00 - 0.00 0.00 %
Counterpart 19.40 Cumulative Disbursements
Cofinancing 0.00 - 0.00 0.00 %

Loan 1831-BAN

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
12 Jul 2001 01 Aug 2001 09 Nov 2001 31 Dec 2009 30 Jun 2010 15 Jun 2010
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 53.40 Cumulative Contract Awards
ADB 34.00 12 Jul 2001 33.10 0.00 100%
Counterpart 19.40 Cumulative Disbursements
Cofinancing 0.00 12 Jul 2001 33.10 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating Satisfactory Satisfactory - - - Satisfactory
Title Document Type Document Date
Second Small-Scale Water Resources Development Sector Project Project/Program Completion Reports Aug 2012
Second Small-Scale Water Resources Development Sector Project Reports and Recommendations of the President Jun 2001

Safeguard Documents

See also: Safeguards

No documents found.

Evaluation Documents

See also: Independent Evaluation
Title Document Type Document Date
Bangladesh: Second Small-Scale Water Resources Development Sector Project Validations of Project Completion Reports Jul 2014

The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.