Sri Lanka: Coastal Resource Management

Sovereign Project | 31287-013 Status: Closed

Latest Project Documents

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Coastal Resource Management
Project Number 31287-013
Country Sri Lanka
Project Status Closed
Project Type / Modality of Assistance Grant
Source of Funding / Amount
Loan 1716-SRI: Coastal Resource Management
Asian Development Fund US$ 40.00 million
Grant 3477-SRI: Coastal Zone and Environment Protection
Netherlands Fund (with LoA) US$ 12.76 million
Strategic Agendas Inclusive economic growth
Drivers of Change
Sector / Subsector

For classification - For classification

Gender Equity and Mainstreaming
Project Rationale and Linkage to Country/Regional Strategy
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Northwestern Province: Puttalam District; Western Province:Gampaha, Colombo, & Panadura-Kalutara Districts; Southern Province: Galle, Matara & Hambantota Districts
Safeguard Categories
Environment A
Involuntary Resettlement
Indigenous Peoples
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Mookiah Thiruchelvam
Responsible ADB Department South Asia Department
Responsible ADB Division Sri Lanka Resident Mission
Executing Agencies
Ministry of Fisheries and Ocean Resources
Mr. H N R Perera
108/4, Rosmead Place
Colombo 07
Sri Lanka
Concept Clearance 26 Mar 1998
Fact Finding 19 Apr 1999 to 07 May 1999
MRM 07 Jun 1999
Approval 07 Dec 1999
Last Review Mission -
PDS Creation Date 06 Feb 2007
Last PDS Update 03 Oct 2008

Grant 3477-SRI

Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 12.76 Cumulative Contract Awards
ADB 0.00 - 0.00 0.00 %
Counterpart 0.00 Cumulative Disbursements
Cofinancing 12.76 - 0.00 0.00 %

Loan 1716-SRI

Approval Signing Date Effectivity Date Closing
Original Revised Actual
07 Dec 1999 14 Dec 1999 14 Jun 2000 30 Dec 2005 30 Jun 2008 02 Sep 2010
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 60.00 Cumulative Contract Awards
ADB 40.00 07 Dec 1999 39.28 0.00 98%
Counterpart 20.00 Cumulative Disbursements
Cofinancing 0.00 07 Dec 1999 40.16 0.00 100%
Title Document Type Document Date
Coastal Resource Management Project Project/Program Completion Reports Dec 2010
Coastal Resource Management Project Reports and Recommendations of the President Nov 1999

Safeguard Documents

See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Evaluation Documents

See also: Independent Evaluation
Title Document Type Document Date
Sri Lanka: Coastal Resource Management Project Validations of Project Completion Reports Mar 2012

Related Publications

None currently available.

The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.